Working Zone* |
Construction Programme |
|
September 2004 |
|
|
AB |
3 Nos.** |
3 Nos.** |
AB |
||
BCn |
||
BCs |
||
Maximum |
21,200 |
33,200 |
Max |
972 |
1,522 |
RemarksNote:
*(1) : This table should be read in conjunction with
Figure 4 of Environmental Permit No. EP-165/2003
** : A maximum of 3 numbers of grab dredgers, each with a grab capacity of no less than 8 m3
is allowed.
Note:
The above maximum daily dredging rates are derived
based on 24-hour dredging operations.
If the daily workings hours are restricted, the maximum daily dredging rates
will have to be reduced proportionally based on the allowable working hours.