Contents
2.1 Monitoring Frequency and Locations
3 Water Quality Performance Limits
A. Graphical Presentations of Water Quality Monitoring Results
Tables
Table 2.2: Locations of Water Quality Monitoring Stations
Table 3.1: Calculated Action and Limit Levels
Table 4.1: Calculated Initial Alert Levels
Table 5.1: Summary of DO Exceedances
Figures
Figure
2.1: Water Quality Monitoring Locations
The Project “Improvement Dredging for Lamma Power Station Navigation Channel” commenced on 18 February 2020. This is the second quarterly Water Quality Monitoring report for the Project. This report presents the results of impact monitoring on marine water quality for the Project from May to July 2020.
During this reporting period, a total of 40 days of marine water quality monitoring was carried out. The water quality monitoring results for all parameters, except dissolved oxygen (DO), obtained during the reporting period were within the corresponding Action and Limit Levels for sensitive receiver stations and within the Alert Levels for near stations as stipulated in the EM&A programme. Some of the DO (surface, middle and bottom layers) triggered the relevant Action or Limit Levels, and the corresponding investigations concluded that the cases were not related to the Project. To conclude, the dredging activities in the reporting period did not cause adverse impact to all water quality sensitive receivers.
On 10 October 2017, the Environment Impact Assessment (EIA) Report (Register No.: AEIAR-212/2017) for the “Improvement Dredging for Lamma Power Station Navigation Channel” (the Project) was approved and an Environmental Permit (EP) (No. EP-535/2017) was issued for the construction and operation of the Project. Mott MacDonald Hong Kong Limited was commissioned by The Hongkong Electric Company, Limited to carry out the water quality monitoring works of the Project during the construction phase.
The purpose of the Project is to provide and maintain safe clearance for ocean-going marine vessels delivering coal to Lamma Power Station (LPS) via the Lamma Power Station Navigation Channel (the “Channel”), through the dredging of naturally accumulating sediment from the seabed. In order to meet the requirements for continued safe passage, the construction phase of the Project involves improvement dredging of the Channel to a target dredge depth[1] of -16.5 mPD.
The construction phase of the Project commenced
on 18 February 2020. This Water Quality Monitoring Report summarizes the water
quality monitoring as part of the EM&A programme for the Project for the
months of May, June and July 2020.
[1] While the Project
aims to dredge to a target depth of -16.5 mPD, some overdredge may occur due to the limited precision control
of dredging depths in practice.
The water quality monitoring was conducted three days per week during the reporting period at mid-flood and mid-ebb tides. The monitoring was conducted at a total of 18 water quality monitoring stations, comprising ten SR stations, five near stations and three control stations. Details of the monitoring locations are shown in Figure 2.1 and Table 2.2. It should be noted that the location of SR8 provided in Table 2.2 is approximate due to changing location of fish rafts under different tidal and wind condition. Water quality monitoring at SR8 was conducted at the nearest safely accessible location to the Fish Culture Zone.
Table 2.2: Locations of Water Quality Monitoring Stations
ID |
Station |
Easting |
Northing |
Remarks |
SR1 |
HK Electric Power Station Intake |
829194 |
808600 |
Monitored for SS only |
SR2 |
Hung Shing Yeh Beach |
830200 |
808700 |
Monitored during bathing season only (March to October inclusive) |
SR3 |
Lo So Shing Beach |
830450 |
807300 |
Monitored during bathing season only (March to October inclusive) |
SR4 |
Marine Ecological Habitat at Pak Kok |
829600 |
811630 |
|
SR5 |
Marine Ecological Habitat at Shek Kok Tsui |
828560 |
811100 |
|
SR6 |
Marine Ecological Habitat at Ha Mei Wan |
829760 |
805520 |
|
SR7 |
Marine Ecological Habitat at Southwest of Lamma |
829590 |
804520 |
|
SR8 |
Fish Culture Zone at Lo Tik Wan |
831265 |
809115 |
|
SR9 |
Fish Culture Zone at Sok Kwu Wan |
831600 |
807765 |
|
SR10 |
Fish Culture Zone at Cheung Sha Wan |
819160 |
810780 |
|
A1 |
Near station for Zone 1 |
828543 |
809573 |
For monitoring potential impacts to SR5 and SR4 during flood tide |
A2 |
Near station for Zone 2 |
829053 |
807945 |
For monitoring potential impacts to SR1 and SR2 during flood tide |
A3 |
Near station for Zone 3 |
829187 |
807100 |
For monitoring potential impacts to SR3 during both flood and ebb tide |
A4 |
Near station for Zone 4 (east) |
829427 |
805520 |
For monitoring potential impacts to SR6 during ebb tide |
A5 |
Near station for Zone 4 (south) |
829267 |
805134 |
For monitoring potential impacts to SR7 during ebb tide |
C1 |
Control Station 1 |
828000 |
813500 |
|
C2 |
Control Station 2 |
825000 |
808000 |
|
C3 |
Control Station 3 |
829000 |
802000 |
|
For the 10 SR stations (SR1 to SR10) and three control stations (C1 to C3), monitoring of DO, DO%, pH, temperature, turbidity, salinity, water depth and SS were undertaken. For monitoring of the five near stations (A1 to A5), only the in-situ parameters (DO, DO%, pH, temperature, turbidity, salinity and water depth) were recorded. Other relevant data were also recorded, including monitoring location, time, tidal stage, weather condition and sea condition.
The Action and Limit levels are summarized in Table 3.1.
Table 3.1: Calculated Action and Limit Levels
Parameters |
Action Level |
Limit Level |
||
SR1 |
|
|
||
SS in mg/L |
90 |
100 |
||
SR2 to SR7 |
|
|
||
DO in mg/L |
Wet |
Dry |
Wet |
Dry |
Surface & Middle |
3.1 |
5.6 |
2.6 |
4 |
Bottom |
2.4 |
5.8 |
1.9 |
2 |
SS in mg/L |
9.5 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
12.3 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
||
Turbidity in NTU |
9.7 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
11.8 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
||
SR8 to SR10 |
|
|
||
DO in mg/L |
Wet |
Dry |
Wet |
Dry |
Surface & Middle |
5 |
5.6 |
5 |
5 |
Bottom |
2.4 |
5.8 |
2 |
2 |
SS in mg/L |
9.5 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
12.3 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
||
Turbidity in NTU |
9.7 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
11.8 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
Notes:
1. Wet season: April to September; Dry season: October to March.
2. For DO measurement, non-compliance occurs when the monitoring result is lower than the limits.
3. For parameters other than DO, non-compliance of water quality occurs when the monitoring result is higher than the limits.
4. Depth-averaged results are used unless specified otherwise.
5. SR1 is monitored for SS only.
6. All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.
The Initial Alert levels for water quality at near stations are presented in Table 4.1.
Table 4.1: Calculated Initial Alert Levels
Alert Level |
A1 |
A2 |
A3 |
A4 |
A5 |
Turbidity (NTU) |
30.1 |
18.4 |
38.8 |
32.0 |
24.3 |
DO (mg/L) – Depth-average, Dry Season |
4 |
4 |
4 |
4 |
4 |
OR 0.1 mg/L less than the same day control, whichever is lower |
|||||
DO (mg/L) – Bottom, Dry Season |
2 |
2 |
2 |
2 |
2 |
OR 0.1 mg/L less than the same day control, whichever is lower |
|||||
DO (mg/L) – Depth-average, Wet Season |
3 |
3 |
3 |
3 |
3 |
OR 0.1 mg/L less than the same day control, whichever is lower |
|||||
DO (mg/L) – Bottom, Wet Season |
0.9 |
0.9 |
0.9 |
0.9 |
0.9 |
OR 0.1 mg/L less than the same day control, whichever is lower |
Note: Wet season: April to September; Dry season: October to March.
Marine water quality monitoring was conducted as scheduled during the reporting period. Graphical presentations of the monitoring results are provided in Appendix A.
The water quality monitoring results for turbidity and SS obtained during the reporting period were within their corresponding Action Levels, Limit Levels and Alert Levels.
For DO, some of the testing results at SR stations triggered the corresponding Action or Limit Levels. The IEC, Engineer and the construction contractor were informed of the exceedances and the Event and Action Plan of the Updated EM&A Manual was initiated. Table 5.1 presents the summary of the DO exceedances at SR stations during mid-ebb and mid-flood tide for the reporting period.
Table 5.1: Summary of DO Exceedances
Date |
Parameter(s) |
Affected Station(s) |
Tide |
Exceedance Type |
22 May |
DO (Surface & Middle) |
SR9, SR10 |
Flood tide |
Limit Level |
25 May |
DO (Surface & Middle) |
SR10 SR10 |
Ebb tide Flood tide |
Limit Level Limit Level |
27 May |
DO (Surface & Middle) |
SR8, SR9 |
Flood tide |
Limit Level |
8 June |
DO (Surface & Middle) |
SR10 SR8, SR9, SR10 |
Ebb tide Flood tide |
Limit Level Limit Level |
10 June |
DO (Surface & Middle) |
SR10 SR8, SR9 |
Ebb tide Flood tide |
Limit Level Limit Level |
12 June |
DO (Surface & Middle) |
SR8 |
Flood tide |
Limit Level |
15 June |
DO (Bottom) |
SR6, SR7 |
Flood tide |
Action Level |
19 June |
DO (Bottom) |
SR2, SR4, SR5 |
Flood tide |
Action Level |
29 June |
DO (Bottom) |
SR10 SR5, SR6 SR5 SR10 |
Ebb tide Ebb tide Flood tide Flood tide |
Action Level Limit Level Action Level Limit Level |
13 July |
DO (Bottom) |
SR2, SR10 |
Ebb tide |
Action Level |
The investigation findings are summarised below:
● 22, 25 and 27 May and 8, 10, 12, 15, 19 and 29 June 2020 – dredging work was suspended during this period hence the causes are not related to the Project.
● 13 July 2020 – the contractor confirmed that no abnormal operation and spillage occurred and all required mitigation measures were implemented. The investigations found that the exceedance appeared to be due to local factors not related to the Project.
As all investigations concluded that the cases were not related to the Project, no further action was required.
Monitoring work for water quality was conducted during the reporting period in accordance with the updated EM&A Manual.
The water quality monitoring results for all parameters, except DO, obtained during the reporting period were within the corresponding Action, Limit or Alert Levels stipulated in the EM&A programme. For DO (surface, middle and bottom layers), some of the results triggered the relevant Action and Limit Levels, and investigations were conducted accordingly. The investigations concluded that the cases were not related to the Project. To conclude, the construction activities in the reporting period did not cause adverse impact to all water quality sensitive receivers.