Improvement Dredging for Lamma Power Station Navigation Channel

Construction Phase Quarterly Water Quality Monitoring Report No. 2 (May–July 2020)

August 2020

 

 

Contents

Executive summary

1        Introduction

2        Monitoring Methodology

2.1      Monitoring Frequency and Locations

2.2      Monitoring Parameters

3        Water Quality Performance Limits

3.1      Action and Limit Levels

3.2      Alert Levels

4        Monitoring Results

5        Conclusion

Appendix

A.      Graphical Presentations of Water Quality Monitoring Results

 

Tables

Table 2.2: Locations of Water Quality Monitoring Stations  3

Table 3.1: Calculated Action and Limit Levels  5

Table 4.1: Calculated Initial Alert Levels  6

Table 5.1: Summary of DO Exceedances  7

Figures

Figure 2.1: Water Quality Monitoring Locations

  

 

 

Executive summary

The Project “Improvement Dredging for Lamma Power Station Navigation Channel” commenced on 18 February 2020. This is the second quarterly Water Quality Monitoring report for the Project. This report presents the results of impact monitoring on marine water quality for the Project from May to July 2020.

During this reporting period, a total of 40 days of marine water quality monitoring was carried out. The water quality monitoring results for all parameters, except dissolved oxygen (DO), obtained during the reporting period were within the corresponding Action and Limit Levels for sensitive receiver stations and within the Alert Levels for near stations as stipulated in the EM&A programme. Some of the DO (surface, middle and bottom layers) triggered the relevant Action or Limit Levels, and the corresponding investigations concluded that the cases were not related to the Project. To conclude, the dredging activities in the reporting period did not cause adverse impact to all water quality sensitive receivers.

 

 

 

1        Introduction

On 10 October 2017, the Environment Impact Assessment (EIA) Report (Register No.: AEIAR-212/2017) for the “Improvement Dredging for Lamma Power Station Navigation Channel” (the Project) was approved and an Environmental Permit (EP) (No. EP-535/2017) was issued for the construction and operation of the Project. Mott MacDonald Hong Kong Limited was commissioned by The Hongkong Electric Company, Limited to carry out the water quality monitoring works of the Project during the construction phase.

The purpose of the Project is to provide and maintain safe clearance for ocean-going marine vessels delivering coal to Lamma Power Station (LPS) via the Lamma Power Station Navigation Channel (the “Channel”), through the dredging of naturally accumulating sediment from the seabed. In order to meet the requirements for continued safe passage, the construction phase of the Project involves improvement dredging of the Channel to a target dredge depth[1] of -16.5 mPD.

The construction phase of the Project commenced on 18 February 2020. This Water Quality Monitoring Report summarizes the water quality monitoring as part of the EM&A programme for the Project for the months of May, June and July 2020.

 


[1] While the Project aims to dredge to a target depth of -16.5 mPD, some overdredge may occur due to the limited precision control of dredging depths in practice.

 

 

2        Monitoring Methodology

2.1        Monitoring Frequency and Locations

The water quality monitoring was conducted three days per week during the reporting period at mid-flood and mid-ebb tides. The monitoring was conducted at a total of 18 water quality monitoring stations, comprising ten SR stations, five near stations and three control stations. Details of the monitoring locations are shown in Figure 2.1 and Table 2.2. It should be noted that the location of SR8 provided in Table 2.2 is approximate due to changing location of fish rafts under different tidal and wind condition. Water quality monitoring at SR8 was conducted at the nearest safely accessible location to the Fish Culture Zone.

Table 2.2: Locations of Water Quality Monitoring Stations

ID

Station

Easting

Northing

Remarks

SR1

HK Electric Power Station Intake

829194

808600

Monitored for SS only

SR2

Hung Shing Yeh Beach

830200

808700

Monitored during bathing season only (March to October inclusive)

SR3

Lo So Shing Beach

830450

807300

Monitored during bathing season only (March to October inclusive)

SR4

Marine Ecological Habitat at Pak Kok

829600

811630

 

SR5

Marine Ecological Habitat at Shek Kok Tsui

828560

811100

 

SR6

Marine Ecological Habitat at Ha Mei Wan

829760

805520

 

SR7

Marine Ecological Habitat at Southwest of Lamma

829590

804520

 

SR8

Fish Culture Zone at Lo Tik Wan

831265

809115

 

SR9

Fish Culture Zone at Sok Kwu Wan

831600

807765

 

SR10

Fish Culture Zone at Cheung Sha Wan

819160

810780

 

A1

Near station for Zone 1

828543

809573

For monitoring potential impacts to SR5 and SR4 during flood tide

A2

Near station for Zone 2

829053

807945

For monitoring potential impacts to SR1 and SR2 during flood tide

A3

Near station for Zone 3

829187

807100

For monitoring potential impacts to SR3 during both flood and ebb tide

A4

Near station for Zone 4 (east)

829427

805520

For monitoring potential impacts to SR6 during ebb tide

A5

Near station for Zone 4 (south)

829267

805134

For monitoring potential impacts to SR7 during ebb tide

C1

Control Station 1

828000

813500

 

C2

Control Station 2

825000

808000

 

C3

Control Station 3

829000

802000

 

2.2      Monitoring Parameters

For the 10 SR stations (SR1 to SR10) and three control stations (C1 to C3), monitoring of DO, DO%, pH, temperature, turbidity, salinity, water depth and SS were undertaken. For monitoring of the five near stations (A1 to A5), only the in-situ parameters (DO, DO%, pH, temperature, turbidity, salinity and water depth) were recorded. Other relevant data were also recorded, including monitoring location, time, tidal stage, weather condition and sea condition.

 

 

3        Water Quality Performance Limits

3.1        Action and Limit Levels

The Action and Limit levels are summarized in Table 3.1.

Table 3.1: Calculated Action and Limit Levels

Parameters

Action Level

Limit Level

SR1

 

 

SS in mg/L

90

100

SR2 to SR7

 

 

DO in mg/L

Wet

Dry

Wet

Dry

   Surface & Middle

3.1

5.6

2.6

4

   Bottom

2.4

5.8

1.9

2

SS in mg/L

9.5

OR

120% of upstream control station(s) at the same tide of the same day, whichever is higher

12.3

OR

130% of upstream control station(s) at the same tide of the same day, whichever is higher

Turbidity in NTU

9.7

OR

120% of upstream control station(s) at the same tide of the same day, whichever is higher

11.8

OR

130% of upstream control station(s) at the same tide of the same day, whichever is higher

SR8 to SR10

 

 

DO in mg/L

Wet

Dry

Wet

Dry

   Surface & Middle

5

5.6

5

5

   Bottom

2.4

5.8

2

2

SS in mg/L

9.5

OR

120% of upstream control station(s) at the same tide of the same day, whichever is higher

12.3

OR

130% of upstream control station(s) at the same tide of the same day, whichever is higher

Turbidity in NTU

9.7

OR

120% of upstream control station(s) at the same tide of the same day, whichever is higher

11.8

OR

130% of upstream control station(s) at the same tide of the same day, whichever is higher

Notes:

1.     Wet season: April to September; Dry season: October to March.

2.     For DO measurement, non-compliance occurs when the monitoring result is lower than the limits.

3.     For parameters other than DO, non-compliance of water quality occurs when the monitoring result is higher than the limits.

4.     Depth-averaged results are used unless specified otherwise.

5.     SR1 is monitored for SS only.

6.     All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

 

 

3.2        Alert Levels

The Initial Alert levels for water quality at near stations are presented in Table 4.1.

Table 4.1: Calculated Initial Alert Levels

Alert Level

A1

A2

A3

A4

A5

Turbidity (NTU)

30.1

18.4

38.8

32.0

24.3

DO (mg/L) – Depth-average, Dry Season

4

4

4

4

4

OR 0.1 mg/L less than the same day control, whichever is lower

DO (mg/L) – Bottom, Dry Season

2

2

2

2

2

OR 0.1 mg/L less than the same day control, whichever is lower

DO (mg/L) – Depth-average, Wet Season

3

3

3

3

3

OR 0.1 mg/L less than the same day control, whichever is lower

DO (mg/L) – Bottom, Wet Season

0.9

0.9

0.9

0.9

0.9

OR 0.1 mg/L less than the same day control, whichever is lower

Note: Wet season: April to September; Dry season: October to March.

 

 

4        Monitoring Results

Marine water quality monitoring was conducted as scheduled during the reporting period. Graphical presentations of the monitoring results are provided in Appendix A.

The water quality monitoring results for turbidity and SS obtained during the reporting period were within their corresponding Action Levels, Limit Levels and Alert Levels.

For DO, some of the testing results at SR stations triggered the corresponding Action or Limit Levels. The IEC, Engineer and the construction contractor were informed of the exceedances and the Event and Action Plan of the Updated EM&A Manual was initiated. Table 5.1 presents the summary of the DO exceedances at SR stations during mid-ebb and mid-flood tide for the reporting period.

Table 5.1: Summary of DO Exceedances

Date

Parameter(s)

Affected Station(s)

Tide

Exceedance Type

22 May

DO (Surface & Middle)

SR9, SR10

Flood tide

Limit Level

25 May

DO (Surface & Middle)

SR10

SR10

Ebb tide

Flood tide

Limit Level

Limit Level

27 May

DO (Surface & Middle)

SR8, SR9

Flood tide

Limit Level

8 June

DO (Surface & Middle)

SR10

SR8, SR9, SR10

Ebb tide

Flood tide

Limit Level

Limit Level

10 June

DO (Surface & Middle)

SR10

SR8, SR9

Ebb tide

Flood tide

Limit Level

Limit Level

12 June

DO (Surface & Middle)

SR8

Flood tide

Limit Level

15 June

DO (Bottom)

SR6, SR7

Flood tide

Action Level

19 June

DO (Bottom)

SR2, SR4, SR5

Flood tide

Action Level

29 June

DO (Bottom)

SR10

SR5, SR6

SR5

SR10

Ebb tide

Ebb tide

Flood tide

Flood tide

Action Level

Limit Level

Action Level

Limit Level

13 July

DO (Bottom)

SR2, SR10

Ebb tide

Action Level

The investigation findings are summarised below:

    22, 25 and 27 May and 8, 10, 12, 15, 19 and 29 June 2020 – dredging work was suspended during this period hence the causes are not related to the Project.

    13 July 2020 – the contractor confirmed that no abnormal operation and spillage occurred and all required mitigation measures were implemented. The investigations found that the exceedance appeared to be due to local factors not related to the Project.

As all investigations concluded that the cases were not related to the Project, no further action was required.

 

5        Conclusion

Monitoring work for water quality was conducted during the reporting period in accordance with the updated EM&A Manual.

The water quality monitoring results for all parameters, except DO, obtained during the reporting period were within the corresponding Action, Limit or Alert Levels stipulated in the EM&A programme. For DO (surface, middle and bottom layers), some of the results triggered the relevant Action and Limit Levels, and investigations were conducted accordingly. The investigations concluded that the cases were not related to the Project. To conclude, the construction activities in the reporting period did not cause adverse impact to all water quality sensitive receivers.