Lamma Power Station Extension - Air Quality Monitoring Data
24-hr TSP  (ug/m3) 1-hr TSP  (ug/m3)
Date Reservoir East Gate Ash Lagoon Tai Yuen Village Date Time Reservoir East Gate Ash Lagoon
(AM1) (AM2) (AM3) (AM4) (AM1) (AM2) (AM3)
06/01/2003 87 105 88 76 06/01/2003 15:00-15:59 72 80 62
12/01/2003 89 86 91 93 16:00-16:59 52 77 46
18/01/2003 59 50 54 51 17:00-17:59 47 59 43
24/01/2003 106 101 89 100 12/01/2003 15:00-15:59 100 96 91
30/01/2003 72 70 (1) 75 16:00-16:59 94 90 92
17:00-17:59 84 71 88
18/01/2003 15:00-15:59 39 35 39
16:00-16:59 67 75 61
17:00-17:59 52 51 54
24/01/2003 15:00-15:59 84 78 87
16:00-16:59 91 84 87
17:00-17:59 96 88 94
30/01/2003 15:00-15:59 73 68 71
16:00-16:59 69 65 70
17:00-17:59 80 68 75
Note : (1) Partisol TSP sampler at AM3 (Ash Lagoon) was found defective during the collection of filter paper on 04/02/2003,
     the first working day after the Chinese New Year Holiday.  The defect was rectified on the same day.  As the next
     sampling is scheduled on 05/02/2003, no make-up sampling was performed.