| Lamma Power Station Extension - Air Quality Monitoring Data | ||||||||||
| 24-hr TSP (ug/m3) | 1-hr TSP (ug/m3) | |||||||||
| Date | Reservoir | East Gate | Ash Lagoon | Tai Yuen Village | Date | Time | Reservoir | East Gate | Ash Lagoon | |
| (AM1) | (AM2) | (AM3) | (AM4) | (AM1) | (AM2) | (AM3) | ||||
| 05/02/2003 | 66 | 58 | 60 | 56 | 05/02/2003 | 15:00-15:59 | 60 | 66 | 72 | |
| 11/02/2003 | 63 | 53 | 54 | 54 | 16:00-16:59 | 64 | 68 | 67 | ||
| 17/02/2003 | (1) | 33 | 35 | 31 | 17:00-17:59 | 63 | 63 | 68 | ||
| 19/02/2003 | 54 | - | - | - | 11/02/2003 | 15:00-15:59 | 62 | 52 | 48 | |
| 23/02/2003 | 38 | 40 | 40 | 40 | 16:00-16:59 | 61 | 61 | 57 | ||
| 17:00-17:59 | 58 | 49 | 52 | |||||||
| 17/02/2003 | 15:00-15:59 | 31 | 31 | 33 | ||||||
| 16:00-16:59 | 29 | 28 | 31 | |||||||
| 17:00-17:59 | 31 | 29 | 32 | |||||||
| 23/02/2003 | 15:00-15:59 | 32 | 37 | 42 | ||||||
| 16:00-16:59 | 38 | 34 | 36 | |||||||
| 17:00-17:59 | 37 | 34 | 35 | |||||||
| Note : | (1) High Volume Air Sampler at AM1 (Reservoir) was found defective during the collection of filter paper on 18/02/2003. | |||||||||
| The defect was rectified on the same day. A make-up 24 hour sampling was performed on 19/02/2003. | ||||||||||