24-hr TSP  (ug/m3) 1-hr TSP  (ug/m3)
Date Reservoir East Gate Ash Lagoon Tai Yuen Village Date Time Reservoir East Gate Ash Lagoon
(AM1) (AM2) (AM3) (AM4) (AM1) (AM2) (AM3)
05/06/2004 - 37 37 - 05/06/2004 15:00-15:59 44 43 52
08/06/2004 - - - 53 16:00-16:59 37 37 43
09/06/2004 72 - - - 17:00-17:59 31 35 43
11/06/2004 59 45 68 74 11/06/2004 15:00-15:59 65 63 64
17/06/2004 29 31 25 18 16:00-16:59 81 85 90
23/06/2004 60 55 45 47 17:00-17:59 79 73 80
29/06/2004 79 95 69 65 17/06/2004 15:00-15:59 13 32 16
16:00-16:59 26 29 24
17:00-17:59 16 27 19
23/06/2004 15:00-15:59 37 59 24
16:00-16:59 76 82 59
17:00-17:59 35 55 32
29/06/2004 15:00-15:59 69 99 88
16:00-16:59 181 172 157
17:00-17:59 122 126 105
(1)  HVAS at AM1 was found defective during collection of filter sample on 7/6/2004.  Defect was rectified on 8/6/2004.
       A make-up 24 hours TSP sampling at AM1 was conducted on 9/6/2004.
(2)  MiniVol at AM4 was found defective during collection of filter sample on 7/6/2004.  Defect was rectified on the same day.
       A make-up 24 hours TSP sampling at AM1 was conducted on 8/6/2004.