24-hr TSP  (ug/m3) 1-hr TSP  (ug/m3)
Date Reservoir East Gate Ash Lagoon Tai Yuen Village Date Time Reservoir East Gate Ash Lagoon
(AM1) (AM2) (AM3) (AM4) (AM1) (AM2) (AM3)
02/11/2004 117 95 99 94 02/11/2004 15:00-15:59 108 93 107
08/11/2004 50 46 44 50 16:00-16:59 99 88 96
14/11/2004 60 45 54 44 17:00-17:59 81 73 81
20/11/2004 99 82 91 93 08/11/2004 (1) 15:00-15:59 70 (9/11) 45 47
26/11/2004 164 138 125 103 16:00-16:59 72 (9/11) 45 48
17:00-17:59 68 (9/11) 48 51
14/11/2004 15:00-15:59 40 39 31
16:00-16:59 52 44 50
17:00-17:59 63 67 66
20/11/2004 15:00-15:59 89 84 90
16:00-16:59 99 95 101
17:00-17:59 87 81 88
26/11/2004 15:00-15:59 175 125 131
16:00-16:59 137 105 103
17:00-17:59 104 99 93
(1) TEOM 1-hr TSP sampler at AM1 (Reservoir) was found defective on 08/11/2004.  A make-up 1hr TSP sampling for AM1