Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving Unit L9 Condensers

Weighted by Flowrates of Individual Streams (April 2008)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

01/04/2008

8.3

02/04/2008

8.3

03/04/2008

8.3

04/04/2008

8.4

05/04/2008

8.5

06/04/2008

7.3

07/04/2008

8.8

08/04/2008

8.8

09/04/2008

8.7

10/04/2008

8.3

11/04/2008

8.3

12/04/2008

8.6

13/04/2008

*

14/04/2008

8.7

15/04/2008

8.8

16/04/2008

8.3

17/04/2008

8.3

18/04/2008

8.3

19/04/2008

7.9

20/04/2008

6.1

21/04/2008

8.8

22/04/2008

8.4

23/04/2008

8.2

24/04/2008

8.2

25/04/2008

8.4

26/04/2008

8.2

27/04/2008

5.9

28/04/2008

8.3

29/04/2008

8.2

30/04/2008

8.2

 

 

Total Residual Chlorine Level at C.W. Outfall No. 3 (April 2008)

 

Date of sampling

10/04/2008

23/04/2008

Total Residual Chlorine, mg/L

0.40

0.35

 

 

Note:

1. * Unit L9 was not on load.