Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers

 

 

Weighted by Flowrates of Individual Streams (February 2013)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

1/2/2013

*

2/2/2013

*

3/2/2013

*

4/2/2013

*

5/2/2013

*

6/2/2013

6.3

7/2/2013

*

8/2/2013

*

9/2/2013

*

10/2/2013

*

11/2/2013

*

12/2/2013

*

13/2/2013

*

14/2/2013

6.6

15/2/2013

8.3

16/2/2013

8.0

17/2/2013

8.0

18/2/2013

8.0

19/2/2013

8.0

20/2/2013

8.0

21/2/2013

8.0

22/2/2013

8.0

23/2/2013

8.1

24/2/2013

8.1

25/2/2013

8.1

26/2/2013

8.1

27/2/2013

8.1

28/2/2013

8.1

Note:   * Unit L9 was not on load.

 

Total Residual Chlorine Level at C.W. Outfall No. 3 (February 2013)

 

Date of sampling

18/02/2013

Total Residual Chlorine, mg/L

0.40

Note:   Monitoring was not carried out during overhaul of Unit L9.