Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers

 

Weighted by Flowrates of Individual Streams (July 2013)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

1/7/2013

8.7

2/7/2013

8.6

3/7/2013

8.6

4/7/2013

8.7

5/7/2013

8.7

6/7/2013

8.7

7/7/2013

8.6

8/7/2013

8.6

9/7/2013

8.7

10/7/2013

8.7

11/7/2013

8.8

12/7/2013

8.7

13/7/2013

8.7

14/7/2013

8.7

15/7/2013

8.7

16/7/2013

8.6

17/7/2013

8.7

18/7/2013

8.7

19/7/2013

8.6

20/7/2013

8.3

21/7/2013

7.6

22/7/2013

8.7

23/7/2013

8.7

24/7/2013

8.7

25/7/2013

8.6

26/7/2013

8.7

27/7/2013

8.8

28/7/2013

8.8

29/7/2013

8.7

30/7/2013

8.7

31/7/2013

8.7


 

Total Residual Chlorine Level at C.W. Outfall No. 3 (July 2013)

 

Date of sampling

11/07/2013

26/07/2013

Total Residual Chlorine, mg/L

0.40

0.40