Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers

 

Weighted by Flowrates of Individual Streams (March 2014)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

1/3/2014

8.5

2/3/2014

8.4

3/3/2014

8.3

4/3/2014

8.4

5/3/2014

8.3

6/3/2014

8.3

7/3/2014

8.3

8/3/2014

8.4

9/3/2014

8.4

10/3/2014

8.4

11/3/2014

9.0

12/3/2014

8.7

13/3/2014

8.7

14/3/2014

8.3

15/3/2014

8.4

16/3/2014

8.4

17/3/2014

8.4

18/3/2014

8.5

19/3/2014

8.5

20/3/2014

8.4

21/3/2014

8.3

22/3/2014

8.4

23/3/2014

8.4

24/3/2014

8.5

25/3/2014

8.5

26/3/2014

8.4

27/3/2014

8.5

28/3/2014

8.4

29/3/2014

8.4

30/3/2014

8.4

31/3/2014

8.3


 

Total Residual Chlorine Level at C.W. Outfall No. 3 (March 2014)

 

Date of sampling

07/03/2014

21/03/2014

Total Residual Chlorine, mg/L

0.40

0.35

 

Blowdown from Unit L9 Steam Turbine and HRSG to C.W. Outfall No. 3 (March 2014)

 

Source of discharge

HSRG

Steam Turbine

Date of sampling

17/03/2014

17/03/2014

Suspended Solid, mg/L

11

11

Grease & Oil, mg/L

<10

<10

Temperature, Deg. Celsius

33

31