Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers

 

Weighted by Flowrates of Individual Streams (August 2015)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

1/8/2015

8.1

2/8/2015

8.2

3/8/2015

8.1

4/8/2015

7.9

5/8/2015

8.0

6/8/2015

8.0

7/8/2015

8.0

8/8/2015

8.0

9/8/2015

8.0

10/8/2015

7.9

11/8/2015

8.0

12/8/2015

8.0

13/8/2015

8.0

14/8/2015

7.9

15/8/2015

8.0

16/8/2015

8.0

17/8/2015

8.0

18/8/2015

8.0

19/8/2015

8.0

20/8/2015

8.0

21/8/2015

8.0

22/8/2015

7.9

23/8/2015

8.0

24/8/2015

8.0

25/8/2015

8.0

26/8/2015

8.0

27/8/2015

8.0

28/8/2015

8.0

29/8/2015

8.0

30/8/2015

8.0

31/8/2015

8.0


Total Residual Chlorine Level at C.W. Outfall No. 3 (August 2015)

 

Date of sampling

07/08/2015

21/08/2015

Total Residual Chlorine, mg/L

0.35

0.35