Lamma Power Station Extension - Summary Results on Water Quality Monitoring

 

Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers

 

Weighted by Flowrates of Individual Streams (January 2016)

 

Date

Maximum Outlet Temperature Rise

(Deg. Celsius)

1/1/2016

8.2

2/1/2016

8.2

3/1/2016

8.2

4/1/2016

*

5/1/2016

*

6/1/2016

*

7/1/2016

*

8/1/2016

*

9/1/2016

*

10/1/2016

*

11/1/2016

*

12/1/2016

*

13/1/2016

*

14/1/2016

*

15/1/2016

*

16/1/2016

*

17/1/2016

*

18/1/2016

*

19/1/2016

*

20/1/2016

*

21/1/2016

*

22/1/2016

*

23/1/2016

*

24/1/2016

*

25/1/2016

*

26/1/2016

*

27/1/2016

*

28/1/2016

*

29/1/2016

*

30/1/2016

*

31/1/2016

*

Note:   * Uuit L9 was not on load.


Total Residual Chlorine Level at C.W. Outfall No. 3 (January 2016)

 

Date of sampling

08/01/2016

22/01/2016

Total Residual Chlorine, mg/L

*

*

Note:   * Uuit L9 was not on load.