Lamma Power Station Extension - Summary Results on Water
Quality Monitoring
Maximum Outlet Temperature Rise (Deg.
Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9 Condensers
Weighted by Flowrates of Individual Streams (January 2018)
Date |
Maximum Outlet Temperature Rise (Deg. Celsius) |
1/1/2018 |
8.5 |
2/1/2018 |
8.5 |
3/1/2018 |
8.5 |
4/1/2018 |
8.5 |
5/1/2018 |
8.5 |
6/1/2018 |
8.4 |
7/1/2018 |
8.5 |
8/1/2018 |
* |
9/1/2018 |
* |
10/1/2018 |
* |
11/1/2018 |
* |
12/1/2018 |
* |
13/1/2018 |
* |
14/1/2018 |
* |
15/1/2018 |
* |
16/1/2018 |
* |
17/1/2018 |
* |
18/1/2018 |
* |
19/1/2018 |
* |
20/1/2018 |
* |
21/1/2018 |
* |
22/1/2018 |
* |
23/1/2018 |
* |
24/1/2018 |
* |
25/1/2018 |
* |
26/1/2018 |
* |
27/1/2018 |
* |
28/1/2018 |
* |
29/1/2018 |
* |
30/1/2018 |
* |
31/1/2018 |
* |
Note: * - Unit L9 was not on load.
Total Residual Chlorine Level at C.W. Outfall No. 3
(January 2018)
Date of sampling |
05/01/2018 |
19/01/2018 |
Total
Residual Chlorine, mg/L |
0.35 |
* |
Note: * - Uuit L9 was not
on load.