Lamma Power Station
Extension - Summary Results on Water Quality Monitoring
Maximum Outlet Temperature
Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.3 Serving L9, L10 &
L11
Weighted by Flowrates of
Individual Streams (November 2024)
Date |
Maximum Outlet
Temperature Rise (Deg. Celsius) |
1/11/2024 |
5.5 |
2/11/2024 |
6.2 |
3/11/2024 |
5.5 |
4/11/2024 |
5.7 |
5/11/2024 |
5.6 |
6/11/2024 |
5.5 |
7/11/2024 |
5.6 |
8/11/2024 |
5.5 |
9/11/2024 |
6.0 |
10/11/2024 |
4.7 |
11/11/2024 |
4.6 |
12/11/2024 |
5.0 |
13/11/2024 |
4.8 |
14/11/2024 |
5.2 |
15/11/2024 |
4.6 |
16/11/2024 |
5.3 |
17/11/2024 |
4.5 |
18/11/2024 |
5.0 |
19/11/2024 |
6.1 |
20/11/2024 |
5.6 |
21/11/2024 |
5.8 |
22/11/2024 |
6.1 |
23/11/2024 |
5.7 |
24/11/2024 |
5.2 |
25/11/2024 |
6.1 |
26/11/2024 |
6.1 |
27/11/2024 |
6.1 |
28/11/2024 |
5.8 |
29/11/2024 |
6.2 |
30/11/2024 |
6.2 |
Maximum Outlet Temperature
Rise (Deg. Celsius) of Cooling Water at C.W. Outfall No.4 Serving Unit L12
Weighted by
Flowrates of Individual Streams (November 2024)
Date |
Maximum Outlet
Temperature Rise (Deg. Celsius) |
1/11/2024 |
5.9 |
2/11/2024 |
* |
3/11/2024 |
* |
4/11/2024 |
6.2 |
5/11/2024 |
6.3 |
6/11/2024 |
6.2 |
7/11/2024 |
5.8 |
8/11/2024 |
5.6 |
9/11/2024 |
* |
10/11/2024 |
* |
11/11/2024 |
5.2 |
12/11/2024 |
5.4 |
13/11/2024 |
5.1 |
14/11/2024 |
5.0 |
15/11/2024 |
5.0 |
16/11/2024 |
* |
17/11/2024 |
* |
18/11/2024 |
4.9 |
19/11/2024 |
* |
20/11/2024 |
* |
21/11/2024 |
5.7 |
22/11/2024 |
5.3 |
23/11/2024 |
5.4 |
24/11/2024 |
6.5 |
25/11/2024 |
6.3 |
26/11/2024 |
6.2 |
27/11/2024 |
6.2 |
28/11/2024 |
6.4 |
29/11/2024 |
6.5 |
30/11/2024 |
* |
Note: * - Unit L12 was not on load.
Total Residual Chlorine Level at C.W. Outfall No. 3
(November 2024)
Date of sampling |
07/11 |
22/11 |
Total Residual Chlorine, mg/L |
0.40 |
0.40 |
Total Residual Chlorine Level at C.W. Outfall No. 4
(November 2024)
Date of sampling |
07/11 |
22/11 |
Total Residual Chlorine, mg/L |
0.40 |
0.40 |