Lamma Power Station Extension - Summary
Results on Water Quality Monitoring
Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at C.W.
Outfall No.3 Serving L9, L10 & L11 Condensers
Weighted by Flowrates of Individual Streams (August 2025)
Date |
Maximum Outlet Temperature Rise (Deg. Celsius) |
1/8/2025 |
6.5 |
2/8/2025 |
6.4 |
3/8/2025 |
6.2 |
4/8/2025 |
6.7 |
5/8/2025 |
6.6 |
6/8/2025 |
6.7 |
7/8/2025 |
6.5 |
8/8/2025 |
7.0 |
9/8/2025 |
7.3 |
10/8/2025 |
6.7 |
11/8/2025 |
6.3 |
12/8/2025 |
6.4 |
13/8/2025 |
6.3 |
14/8/2025 |
6.3 |
15/8/2025 |
6.1 |
16/8/2025 |
6.7 |
17/8/2025 |
6.2 |
18/8/2025 |
6.6 |
19/8/2025 |
7.0 |
20/8/2025 |
6.4 |
21/8/2025 |
6.3 |
22/8/2025 |
6.6 |
23/8/2025 |
6.6 |
24/8/2025 |
6.5 |
25/8/2025 |
6.5 |
26/8/2025 |
6.6 |
27/8/2025 |
6.6 |
28/8/2025 |
6.6 |
29/8/2025 |
6.8 |
30/8/2025 |
6.6 |
31/8/2025 |
6.5 |
Maximum Outlet Temperature Rise (Deg. Celsius)
of Cooling Water at C.W. Outfall No.4 Serving Unit L12
Weighted by Flowrates of Individual Streams (August 2025)
Date |
Maximum Outlet Temperature Rise (Deg. Celsius) |
1/8/2025 |
6.8 |
2/8/2025 |
6.5 |
3/8/2025 |
5.7 |
4/8/2025 |
6.8 |
5/8/2025 |
6.7 |
6/8/2025 |
6.7 |
7/8/2025 |
6.8 |
8/8/2025 |
6.8 |
9/8/2025 |
6.8 |
10/8/2025 |
6.8 |
11/8/2025 |
6.8 |
12/8/2025 |
6.8 |
13/8/2025 |
6.8 |
14/8/2025 |
6.4 |
15/8/2025 |
6.3 |
16/8/2025 |
6.8 |
17/8/2025 |
6.7 |
18/8/2025 |
6.7 |
19/8/2025 |
6.7 |
20/8/2025 |
6.8 |
21/8/2025 |
6.8 |
22/8/2025 |
6.8 |
23/8/2025 |
6.8 |
24/8/2025 |
6.8 |
25/8/2025 |
6.7 |
26/8/2025 |
6.7 |
27/8/2025 |
6.8 |
28/8/2025 |
6.8 |
29/8/2025 |
6.8 |
30/8/2025 |
6.8 |
31/8/2025 |
6.6 |
Total
Residual Chlorine Level at C.W. Outfall No. 3 Serving Units L9, L10 & L11
(August 2025)
Date of sampling |
01/08 |
15/08 |
29/08 |
Total Residual Chlorine, mg/L |
0.30 |
0.20 |
0.20 |
Total
Residual Chlorine Level at C.W. Outfall No. 4 Serving Units L12 (August 2025)
Date of sampling |
01/08 |
15/08 |
29/08 |
Total Residual Chlorine, mg/L |
0.20 |
0.10 |
0.20 |