Cover

Table of Content

EXECUTIVE SUMMARY

1.             INTRODUCTION.. 1

1.1       Background  1

1.2       Project Organisation  1

1.3       Construction Works undertaken during the Reporting Month  1

1.4       Summary of EM&A Requirements  3

2.             AIR QUALITY.. 7

2.1       Monitoring Requirements  7

2.2       Monitoring Locations  7

2.3       Monitoring Equipment 7

2.4       Monitoring Parameters, Frequency and Duration  8

2.5       Monitoring Procedures and Calibration Details  8

2.6       Results and Observations  9

3.             NOISE.. 11

3.1       Monitoring Requirements  11

3.2       Monitoring Locations  11

3.3       Monitoring Equipment 12

3.4       Monitoring Parameters, Frequency and Duration  13

3.5       Monitoring Procedures and Calibration Details  13

3.6       Results and Observations  13

4.             WATER QUALITY MONITORING.. 15

4.1       Monitoring Requirements  15

4.2       Monitoring Locations  15

4.3       Monitoring Equipment 17

4.4       Monitoring Parameters, Frequency and Duration  17

4.5       Monitoring Procedures and Calibration Details  18

4.6       Results and Observations  19

5.             ENVIRONMENTAL AUDIT.. 21

5.1       Review of Environmental Monitoring Procedures  21

5.2       Assessment of Environmental Monitoring Results  21

5.3       Site Environmental Audit 22

5.4       Status of Environmental Licensing and Permitting  22

5.5       Implementation Status of Environmental Mitigation Measures  23

5.6       Implementation Status of Action/Limit Plans  23

5.7       Implementation Status of Environmental Complaint Handling Procedures  23

6.             FUTURE KEY ISSUES. 24

6.1       Status of Natural Gas supply  24

6.2       Key Issues for the Coming Month  24

6.3       Monitoring Schedules for the Next 3 Months  25

6.4       Construction Program for the Next 3 Months  25

7.             CONCLUSION.. 26

 


List of Tables

 

Table 1.1          Construction Activities and Their Corresponding Environmental Mitigation Measures

Table 2.1          Air Quality Monitoring Locations

Table 2.2          Air Quality Monitoring Equipment

Table 2.3          Air Quality Monitoring Parameter, Duration and Frequency

Table 3.1          Noise Monitoring Locations

Table 3.2          Noise Monitoring Equipment

Table 3.3          Noise Monitoring Duration and Parameter

Table 4.1          Water Quality Monitoring Locations

Table 4.2          Water Quality Monitoring Equipment

Table 4.3          Water Quality Monitoring Parameters and Frequency

Table 4.4          Laboratory Analysis Methodologies of Marine Water Samples

Table 5.1          Summary of AL Level Exceedances on Monitoring Parameters

Table 5.2          Estimated Amounts of Waste Generated in June 2002

Table 5.3          Summary of Environmental Licensing and Permit Status

Table 5.4          Environmental Complaints / Enquiries Received in June 2002

Table 5.5          Outstanding Environmental Complaints / Enquiries Received Before

 

 

List of figures

 

Figure 1.1         Layout of Work Site

Figure 1.2         Cable Route of Transmission System

Figure 1.3         Location of Dumping Area (from 12th June 2002)

Figure 2.1         Location of Air Quality Monitoring Stations

Figure 3.1         Location of Noise Monitoring Stations

Figure 4.1         Location of Water Quality Monitoring Stations

 

 

Appendices

 

Appendix A      Organization Chart

Appendix B      Action and Limit Levels for Air Quality, Noise, Water quality Monitoring

Appendix C      Environmental Monitoring Schedule

Appendix D      Air Quality Monitoring Results for June 2002

Appendix E      Noise Monitoring Results for June 2002

Appendix F      Water Quality Monitoring Results for June 2002

Appendix G      The QA/QC Procedures and Results

Appendix H      Event/Action Plans

Appendix I       Site Audit Summary

Appendix J       Summary of EMIS

Appendix K     Tentative Construction Programme



EXECUTIVE SUMMARY

 

 

This is the fifteenth monthly Environmental Monitoring and Audit (EM&A) report for the Project “Construction of Lamma Power Station Extension” prepared by the Environmental Team (ET).  This report presents the results of impact monitoring on air quality, noise and marine water quality for the said project in June 2002.

 

Air, noise and water quality monitoring were performed. The results were checked against the established Action/Limit (AL) levels.  An on-site audit was conducted once per week. The implementation status of the environmental mitigation measures, Event/Action Plan and environmental complaint handling procedures were also checked.

 

Construction Activities Undertaken

 

Construction activities for Lamma Extension during the reporting month were tabulated as follows:

 

Item

Construction Activities

Site Formation

Placing of drainage layer and rockfill, seawall construction, sand filling, and piling of foundation for link bridge.

Unit L9

Site investigation and bored pipe construction for piling foundation.

Transmission System

No construction activities.

 

Environmental Monitoring Works

 

The two environmental monitoring works were rescheduled as shown in the following table.

 

Monitoring work

Original Schedule

Makeup sampling

Reasons

1 hour TSP monitoring at AM1

16th June 2002

18th June 2002

Failure of air conditioning unit for TSP Sampler

Water quality monitoring

12th June 2002

18th June 2002

Damage of the monitoring probe cable

 

Other than these, all monitoring work at designated stations was performed as scheduled in the reporting period.

   

 

Air Quality

No exceedance of Action and Limit levels for air quality was recorded in the month.

 

Noise

The hoarding works for the construction of transmission system were completed on 11/5/2002.  The civil works would tentatively commence on 1/8/2002.  As there was no construction work in this reporting month, manual noise measurements for the construction of transmission system was suspended.  Construction work for Lamma Extension was carried out during the restricted hours including evening-time, holidays and night-time under valid Construction Noise Permits.  No exceedance of Action and Limit levels for noise arising from the construction of Lamma Extension was recorded in the month. 

  

Water Quality

There was no exceedance of Action and Limit Levels for water quality in the reporting month.

 

Site Environmental Audit

Site audits were carried out on a weekly basis to monitor environmental issues on the construction site.  The site conditions were generally satisfactory.  All required mitigation measures were implemented.

 

Environmental Licensing and Permitting

 

Description

Permit No.

Valid Period

Issued To

Date of Issuance

From

To

Varied Environmental Permit

EP-071/2000/B

13/07/01

-

HEC

13/07/01

Construction Noise Permit

GW-UW0076-02

17/04/02

09/09/02

Contractor

17/04/02

Construction Noise Permit

GW-UW0036-02

06/03/02

31/08/02

Contractor

06/03/02

Construction Noise Permit

GW-UW0099-02

07/05/02

06/11/02

Contractor

30/04/02

Registration of Chemical Waste Producer

WPN5213-912-G1050-01

01/06/02

-

Contractor

03/06/02

Dumping Permit

EP/MD/03-002

12/06/02

11/12/02

Contractor

10/12/02

 

Implementation Status of Environmental Mitigation Measures

Environmental mitigation measures for the construction activities as recommended in the EM&A manual were implemented in the reporting month.

 

Environmental Complaints

No complaint against the construction activities was received in the reporting month.

 

Future Key Issues

The future key issues to be considered in the coming month are as follows:

 

Site Formation

 

-         to continue monitoring the noise level during construction and to ensure compliance with the CNP’s already obtained;

-         to continue the preventive measures for noise exceedance and keep monitoring/ reviewing the performance;

-         to keep reviewing the monitoring results in order to take corresponding action to ensure the sea water quality;

-         to provide routine inspection and necessary maintenance for the silt curtain;

-         to complete the closure of the seawall by the end of July 2002 so that seawater quality impacts can further be minimized;

-         to remove the installed silt curtains after the closure of the seawall;

-         to carry out post project monitoring works for marine water quality for four weeks in the same manner as impact monitoring work after the closure of the seawall.  No further marine water quality monitoring is required after the post project monitoring is satisfactorily completed.

 

Transmission System

 

-         to closely monitor the construction activities, if any, in order to avoid disturbance to the rare plants; 

-         to provide temporary fire fighting equipment for prevention of fire within the work sites;

 

Unit L9 Piling Foundation

 

-         to continue monitoring the noise level during construction and to ensure compliance with the CNPs already obtained;

-         to continue the preventive measures for noise exceedance and keep monitoring/ reviewing the performance;

-         to spray water on the ground and road surface to prevent dust emission;

-         to continue monitoring and reviewing the emission of smoke from construction machines;

-         to recycle wastewater during the Bored Piling Works;

-         to implement the Waste Management Plan.

 

 

Concluding Remarks

The environmental performance of the project was generally satisfactory.



 


1.             INTRODUCTION

 

 

1.1         Background

 

The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for Construction of Lamma Power Station Extension” (hereinafter called the “Project”).  Under the requirements of Section 6 of Environmental Permit EP-071/2000/B, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented.  In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project.

 

The Project involves the construction of a gas-fired power station employing combined cycled gas turbine technology, forming an extension to the existing Lamma Power Station.  The key elements of the Project including the construction activities associated with the transmission system and submarine gas pipeline are outlined as follows.

 

·          dredging and reclamation to form approximately 22 hectares of usable area;

·          construction of six 300MW class gas-fired combined cycle units;

·          construction of a gas receiving station;

·          construction of a new transmission system linking the Lamma Extension to load centres on Hong Kong Island;

·          laying of a gas pipeline for the supply of natural gas to the new power station

 

This report summarizes the environmental monitoring and audit work for the Project for the month of June 2002.

 

 

1.2         Project Organisation

 

An Environmental Management Committee (EMC) has been set up in HEC to oversee the Project.  The management structure includes the following:

 

·          Environmental Protection Department (The Authority);

·          Environmental Manager (The Chairman of the Environmental Management Committee);

·          Engineer;

·          Independent Environmental Checker (IEC);

·          Environmental Team (ET);

·          Contractor.

 

The project organisation chart for the construction EM&A programme is shown in Appendix A.

 

 

1.3         Construction Works undertaken during the Reporting Month

 

Construction activities undertaken during the reporting month for site formation were placing of drainage layer & rock fill, construction of seawall, sand filling, piling foundation for link bridge.  Construction activities for Unit L9 and its associated Transmission system were site investigation of piling foundation and erection of hoarding respectively.  Layout plans for site formation and transmission system are shown in Figure 1.1 and Figure 1.2 respectively.  Uncontaminated dredged/excavated materials arising from the piling foundation work of Unit L9 were dumped at the assigned location within the South Cheung Chau Spoil Disposal Area.  Figure 1.3 shows dumping location in June 2002.

 

The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1.  The implementation of major mitigation measures in the month is provided in Appendix J.

 

Table 1.1    Construction Activities and Their Corresponding Environmental Mitigation Measures

 

Item

Construction Activities

Environmental Mitigation Measures

Site Formation

1

Placing of Drainage Layer and Rockfill, Seawall Construction & Sandfilling

Water Quality

-        Silt curtain installed on the eastern, southern and northwestern sides of the site.

Noise

-        General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-        Waste Management Plan submitted and implemented.

 

Marine Ecology

-        All construction related vessels approached the site from the designated route/channel to avoid possible disturbance to the finless porpoise.

2

Piling Foundation for Link Bridge

Noise

-        General noise mitigation measures implemented and silenced type equipment deployed.

 

Air

-        Dust suppression measures implemented.

Construction of Transmission System

3

No construction activities

Terrestrial Ecology

-        Special care and close monitoring to avoid disturbances to the rare plant species.

-        Temporary fire fighting equipment provided within the work area during construction.

Construction of Unit L9 Piling Foundation

4

Bored Pile Construction for Piling Foundation

Water Quality

-        Wastewater is recycled during construction.

 

Noise

-        General noise mitigation measures implemented and silenced type equipment deployed.

 

Air

-        Dust suppression measures implemented.

 

Waste Management

-        Waste is sorted, stored & recycled.

 

 

 

1.4         Summary of EM&A Requirements

 

The EM&A program requires environmental monitoring for air, noise and water quality.  Regular environmental site audits for air quality, noise, water quality and waste management were carried out.  The detailed EM&A monitoring work for air quality, noise and water quality are described in Sections 2, 3 and 4 respectively.

 

The following environmental audits are summarized in Section 5 of this report:

 

·          Environmental monitoring results;

·          Waste Management Records;

·          Weekly site audit results;

·          The status of environmental licensing and permits for the Project;

·          The implementation status of environmental protection and pollution control/ mitigation measures.

 

Future key issues will be reported in Section 6 of this report.

 


 

 

Figure 1.1    Layout of Work Site


 

Figure 1.2    Cable Route of Transmission System


 

Figure 1.3  Location of Dumping Area (from 12th June 2002)


 


2.             AIR QUALITY

 

 

2.1         Monitoring Requirements

 

1-hour and 24-hour TSP monitoring at agreed frequencies were conducted to monitor air quality.  The impact monitoring data were checked against the Action/Limit Levels as determined in the Baseline Monitoring Report (Construction Phase).  Appendix B shows the established Action/Limit Levels for Air Quality.

 

 

2.2         Monitoring Locations

 

Three dust monitoring locations were selected for 1-hour TSP sampling (AM1, AM2 & AM3) while four monitoring locations were selected for 24-hour TSP sampling (AM1, AM2, AM3 and AM4).  Table 2.1 tabulates the monitoring stations.  The locations of the monitoring stations are shown in Figure 2.1.

 

Table 2.1    Air Quality Monitoring Locations

 

Location I.D.

Description

AM1

Reservoir

AM2

East Gate

AM3

Ash Lagoon

AM4

Tai Yuen Village

 

 

2.3         Monitoring Equipment

 

Continuous 24-hour TSP air quality monitoring was performed using the GS2310 High Volume Air Samplers (HVAS), Partisol Model 2000 Sampler and the MINIVOL Portable Sampler at AM1&2, AM3 and AM4 respectively.  TEOM Model 1400a continuous dust monitors were used to carry out 1-hour TSP monitoring at AM1, AM2 and AM3.  Table 2.2 summarises the equipment used in dust monitoring.

 


 

Table 2.2    Air Quality Monitoring Equipment

 

Equipment

Model and Make

24-hour sampling:

HVAS Sampler

 

 

Partisol Air Sampler

 

 

MINIVOL Portable Sampler

 

1-hour sampling:

Continuous TSP Dust Meter

 

Model GS2310

Anderson Instruments Inc.

 

Partisol Model 2000

Rupprecht & Patashnick

 

AIRMETRICS

 

 

TEOM Model 1400a

Rupprecht & Patashnick

 

 

2.4         Monitoring Parameters, Frequency and Duration

 

Table 2.3 summarises the monitoring parameters, duration and frequency of air quality monitoring.  The monitoring schedule for the reporting month is shown in Appendix C.

 

Table 2.3    Air Quality Monitoring Parameter, Duration and Frequency

 

Monitoring Stations

Parameter

Duration

Frequency

AM1

1-hour TSP

1

3 hourly samples every 6 days

24-hour TSP

24

Once every 6 days

AM2

1-hour TSP

1

3 hourly samples every 6 days

24-hour TSP

24

Once every 6 days

AM3

1-hour TSP

1

3 hourly samples every 6 days

24-hour TSP

24

Once every 6 days

AM4

24-hour TSP

24

Once every 6 days

 

 

2.5         Monitoring Procedures and Calibration Details

 

24- hour TSP Monitor:

 

Preparation of Filter Papers

 

·          Visual inspection of filter papers was carried out to ensure that there were no pinholes, tears and creases;

·          The filter papers were then labelled before sampling.

·          The filter papers were equilibrated at room temperature and relative humidity < 50% for at least 24 hours before weighing.

 

Field Monitoring

 

·          During collection of the sampled filter paper, the information on the elapse timer was logged.  Site observations around the monitoring stations, which might have affected the monitoring results, were also recorded.  Major pollution sources, if any, would be identified and reported.  The flow record chart for the previous sampling was checked to see if there was any abnormality.

·          The post-sampling filter papers were removed carefully from the filter holder and folded to avoid loss of fibres or dust particles from the filter papers;

·          The filter holder and its surrounding were cleaned;

·          A pre-weighed blank filter paper for the next sampling was put in place and aligned carefully.  The filter holder was then tightened firmly to avoid leakage;

·          A new flow record chart was loaded into the flow recorder;

·          The programmable timer was set for the next 24 hrs sampling period, ! 1/2 hr;  

·          The post-sampling filter papers were equilibrated at room temperature and relative humidity < 50% for at least 24 hours before weighing.

 

1- hour TSP Monitor:

 

·          The following parameters of the TEOM model dust meters are regularly checked to ensure proper functionality:

 

o       Mass concentration;

o       Total mass;

o       Frequency of the tapered element;

o       Electrical noise;

o       Main flow;

o       Auxiliary flow.

 

Maintenance & Calibration

 

·          The monitoring equipment and their accessories are maintained in good working conditions.

·          Monitoring equipment is calibrated at monthly intervals.  Calibration details are shown in Appendix G.

 

 

2.6         Results and Observations

 

1 hour TSP sampling at AM1 (Reservoir) on 16th June 2002 was void due to the breakdown of the air conditioning unit for the TEOM TSP sampler.  The defect was rectified on 17th June 2002.  A make-up 1 hr TSP sampling was conducted on 18th June 2002.  Other than this incident, dust monitoring was conducted as scheduled in the reporting month. All monitoring data and graphical presentation of the monitoring results are provided in Appendix D.  Key findings and observations are provided below:

 


 

1-hour TSP

 

No exceedance of 1-hour TSP Action/Limit Level was recorded in the month.

 

24-hour TSP

 

No exceedance of 24-hour TSP Action/Limit Level was recorded in the month.

 

 

 


 

Figure 2.1           Location of Air Quality Monitoring Stations



3.             NOISE

 

3.1         Monitoring Requirements

 

Continuous noise alarm monitoring at Ash Lagoon/Ching Lam were carried out to calculate the noise contributed by the construction activities at the two critical NSR’s, viz. Long Tsai Tsuen/Hung Shing Ye and the school within the village of Tai Wan San Tsuen.  The impact monitoring data for construction noise other than percussive piling were checked against the limit levels specified in the EM&A Manual.  With the availability of the construction noise permits, impact monitoring for the construction work during the restricted hours was also carried out.  Section 5 presents the details of the construction noise permits.  The impact noise monitoring data were checked against the limit levels specified in the EM&A Manual.  Appendix B shows the established Action/Limit Levels for noise.

 

The hoarding works for the construction of transmission system were completed on 11/5/2002.  The civil works would tentatively commence on 1/8/2002.  As there was no construction work in June 2002, manual noise measurements at Pak Kok Tsui residences was suspended in this reporting month. 

 

 

3.2         Monitoring Locations

 

In accordance with the EM&A manual, the identified noise monitoring locations are listed in Table 3.1 and shown in Figure 3.1.

 

Table 3.1    Noise Monitoring Locations

 

Purpose of noise monitoring

Monitoring Location

Lamma Extension

Ash Lagoon

Lamma Extension

Ching Lam

 

 

3.3         Monitoring Equipment

 

The sound level meters used for noise monitoring complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1).  The noise monitoring equipment used is shown in Table 3.2.


Table 3.2    Noise Monitoring Equipment

 

Equipment

Model

Sound level meter

Rion NA-27

Sound level calibrator

Rion NC-74

 

 

3.4         Monitoring Parameters, Frequency and Duration

 

Continuous alarm monitoring of A-weighted Leq levels was carried out at Ash Lagoon and Ching Lam.  The measurement duration and parameter of noise monitoring were presented in Table 3.3 as follows:

 

Table 3.3    Noise Monitoring Duration and Parameter

 

Location

Time Period

Frequency

Parameter

Ash Lagoon

 

 

 

Ching Lam

Daytime:

0700-1900 hrs on normal weekdays

 

Evening-time & holidays:

0700-2300 hrs on holidays; and 1900-2300 hrs on all other days

 

Night-time:

2300-0700 hrs of next day

Daytime:

30 minutes

 

 

Evening-time & holidays:

5 minutes

 

 

Night-time:

5 minutes

30-min LAeq

 

 

5-min LAeq

 

 

5-min LAeq

 

 

3.5         Monitoring Procedures and Calibration Details

 

Monitoring Procedures

 

Continuous Noise Monitoring for Lamma Extension Construction

 

The measured noise levels (MNL's) were collected at the noise alarm monitoring stations at Ash Lagoon and Ching Lam.  The notional background noise levels (viz. baseline noise data at Ash Lagoon and Ching Lam) were applied to correct the corresponding MNL's in 30-min/5-min LAeq.

 

A wind speed sensor was installed at Station Building Rooftop.  The wind speed signal was used to determine whether the data from Ash Lagoon and Ching Lam noise alarm monitoring stations were affected.  The instantaneous data was discarded in case the instantaneous wind speed exceeded 10 m/s.  The 30-min/5-min LAeq was considered valid only if the amount of valid data was equal to or above 70%. 

 

When calibrating the noise measuring equipment, all observations around the monitoring stations, which might have affected the monitoring results, were recorded.

 

Equipment Calibration

 

The sound level meters and calibrators have been verified by the manufacturer or accredited laboratory. Equipment for continuous noise monitoring was calibrated at site on a monthly basis.  Calibration details are shown in Appendix G.

 

3.6         Results and Observations

 

Continuous noise monitoring was conducted at the two monitoring stations at Ash Lagoon and Ching Lam.  All monitoring results and their graphical presentations are provided in Appendix E.

 

No exceedance of noise Action/Limit Level was recorded in the month.

 


 

 

Figure 3.1    Location of Noise Monitoring Stations


 


4.             WATER QUALITY MONITORING


 

 

4.1         Monitoring Requirements

 

Marine water quality monitoring was carried out at the monitoring locations adjacent to the construction site.  The purpose was to ensure that deterioration of water quality, if any, would be detected and that timely action could be taken to rectify the situation.  The impact monitoring data were checked against the AL levels set out in the Baseline Monitoring Report (Construction Phase).  As there were no activities for the laying of the gas pipeline in the reporting month, no water quality impact monitoring at the relevant stations was carried out.

 

 

4.2         Monitoring Locations

 

A total of 12 water quality monitoring locations were selected.  7 Sensitive Receiver (SR) stations were chosen on the basis of their proximity to the construction site, 5 Marine Control stations (C) as recommended in the EIA were selected to facilitate comparison of the water quality of the SR stations with ambient water quality conditions. Table 4.1 describes the locations of these monitoring stations. Their locations are shown in Figure 4.1.

 

Table 4.1    Water Quality Monitoring Locations

 

Type

Monitoring Location

HK Metric Grid E

HK Metric Grid N

Sensitive Receiver Stations

SR1

830 224

811 528

SR2

829 004

810 903

SR3

829 194

(829 166)1

808 600

(808 592)1

SR4

830 119

808 650

SR5

830 386

807 189

SR6

829 977

805 758

SR7

829 566

804 545

Marine Control Stations

C1

830 542

813 492

C2

828 608

813 492

C3

826 776

809 978

C4

826 776

806 464

C5

830 440

802 186

1. Due to the construction programme, the monitoring location SR3 was slightly shifted since the monitoring on 16th April 2001.  EPD has verbally been informed of the shift of the monitoring location.

 


4.3         Monitoring Equipment

 

Table 4.2 summarizes the equipment used in the water-quality monitoring programme.

 

Table 4.2    Water Quality Monitoring Equipment

 

Equipment

Detection Limit

YSI 6920 Water Quality Monitor

Temperature: -5 to 45 0C; +/- 0.15 0C

Salinity: 0 to 70 ppt; +/- 0.1 ppt

Dissolved Oxygen: 0 to 200%; +/- 0.2%

0 to 20 mg/L; +/- 0.2 mg/L

Turbidity: 0 to 000 NTU; +/- 5% of the range

pH: 0 to 14 units; +/- 0.2 units

Trimble NT300D GPS

Accuracy better than 3m

 

 

4.4         Monitoring Parameters, Frequency and Duration

 

Table 4.3 summarizes the monitoring parameters, frequencies and total duration of water quality monitoring.  The monitoring schedule for reporting month is shown in Appendix C.

 

Table 4.3    Water Quality Monitoring Parameters and Frequency

 

Monitoring  Stations

Parameters

Frequency

No. of Depths

No. of Samples

Sensitive Receiver Stations

SR1, SR2, SR4, SR5, SR6 & SR7

 

Marine Control Stations

C1, C2, C3, C4 & C5

 

·       Depth, m

·       Temperature, oC

·       Salinity, ppt

·       DO, mg/L

·       DO Saturation, %

·       Turbidity, NTU

·       SS, mg/L

·       pH

 

Three times per week

3

Surface,

Mid-Depth and Bottom

2

Mid-ebb and Mid-flood

 


4.5         Monitoring Procedures and Calibration Details

 

Monitoring Procedures

 

·               The monitoring stations were accessed using survey boat to within 3m, guided by Differential Global Positioning System (DGPS). 

 

·               The depth of the monitoring location was measured using depth meter in order to determine the sampling depths.  Afterwards, the water sampler was lowered into the water to the required depths of sampling.  Upon reaching the pre-determined depth, a messenger to activate the sampler was then released to travel down the wire. The water sample was sealed within the sampler before retrieving. 

 

·               All in-situ measurements at each monitoring stations were taken at 3 water depths, where appropriate, namely 1m below water surface, mid-depth, and 1 meter from seabed, except where the water depth was less than 6m, the mid-depth measurement was omitted.  If the water depth was less than 3m, only the mid-depth position was monitored.

 

·               At each measurement/sampling depth, two consecutive measurements were taken. The probes were retrieved out of the water after the first measurement and then redeployed for the second measurement.  Where the difference in the value between the first and the second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further samplings were taken.

 

·               The duplicate water samples for physical and chemical analysis were stored into a pre-labelled high-density polyethylene (HDPE) bottle pre-rinsed with the same water samples. The sample bottles were than packed in a cool-box (cooled to 4oC without being frozen) and delivered to a HOKLAS Laboratory for analysis upon the completion of each round of sampling. 

 

·               In addition, field information such as the general meteorological conditions and any observations regarding any significant activities in the vicinity of each monitoring location were also recorded.  Major water pollution sources, if any, were identified and recorded.

 

Equipment Calibration

 

The equipment deployed for in-situ measurement of marine water quality was calibrated before use.  The methodologies for the calibration follow the instruction manuals provided by the corresponding manufacturers.  The calibration records are shown in Appendix G.

 

 


Laboratory Analysis & QA/QC

 

The collected marine water samples were analyzed for Suspended Solids with methodologies summarized in Table 4.4.

 

Table 4.4    Laboratory Analysis Methodologies of Marine Water Samples

 

Parameter

Method

Limit of Reporting (mg/L)

Suspended Solids

APHA 17 ed 2540 D

1.0

 

In order to ensure that the laboratory analysis works were carried out properly, stringent QA/QC procedures (which includes the sample preparation as well as the subsequent instrumentation analysis) were followed.  According to the requirements stipulated in the EM&A Manual, QA/QC requirements for laboratory testing include:

 

1)      "Blind" duplicate samples analysis of 10% collected marine water samples; and

2)      in-house QA/QC procedures of the testing laboratory (this includes the use of blank, batch duplicates and quality control samples).

 

Blind Duplicate:

In order to cross check the precision of the measurement results obtained from the laboratory analysis, “blind” duplicate samples of 10% of the collected marine water samples were analysed alongside the normal samples.  The sample codes for the “blind” duplicates were determined by the sampling team and are not identifiable by the laboratory.  The results of the “blind” duplicate samples are summarized in Appendix G.

 

A total of 864 sets of samples (for Suspended Solids analysis) were received during the marine monitoring period including both ebb and flood tides.  At least 5% laboratory blanks, batch duplicates, quality control samples and recovery tests for each parameter were conducted.  The acceptance criteria are outlined in each type of Quality Control data. 

 

Blank:

A laboratory blank is an analyte free matrix to which all reagents are added in the same volumes or proportions as used in the standard sample preparation to monitor contamination introduced in laboratory.  All the laboratory blank values and acceptance criterion of suspended solids are summarized in Appendix G.    

 

Batch Duplicate:

Batch duplicate is an intra-laboratory split sample randomly selected from the sample batch to monitor the method precision in a given matrix.  The acceptance limit of duplicate values of suspended solids and their duplicate results are summarized in Appendix G.

 

Quality Control Sample:

The quality control sample is the analysis of a material with a known concentration of contaminants to determine the accuracy of results in a given matrix.  The quality control samples results for suspended solids are shown in Appendix G.

 

The QA/QC results in Appendix G indicated that the laboratory analysis works of the collected marine water samples were properly carried out and the measurement results obtained were valid in accordance with the Hong Kong Laboratory Accreditation Scheme (HOKLAS) requirements.  On the other hand, the “blind” duplicate measurement results indicated that the precision of the measurements for Suspended Solids are in compliance with the HOKLAS requirements.

 

 

4.6         Results and Observations

 

The marine water monitoring work on 12th June 2002 was rescheduled to 18th June 2002 due to damage of the monitoring probe cable.  Other than this, marine water monitoring was conducted as scheduled in the reporting month.  All monitoring data and graphical presentation of the monitoring results are provided in Appendix F. 

 

There was no Action / Limit Level exceedance for water quality in the reporting month.

 

 

 

Figure 4.1    Location of Water Quality Monitoring Stations

 


 


5.             ENVIRONMENTAL AUDIT


 

 

5.1         Review of Environmental Monitoring Procedures

 

The environmental monitoring procedures were regularly reviewed by the Environmental Team.  No modification to the existing monitoring procedures was recommended.

 

 

5.2         Assessment of Environmental Monitoring Results

 

Monitoring results for Air Quality, Noise and Water Quality

 

The environmental monitoring results for Air Quality, Noise and Water Quality in the reporting month presented in sections 2,3 and 4 respectively are summarized in Table 5.1.

 

Table 5.1    Summary of AL Level Exceedances on Monitoring Parameters

 

Item

Parameter Monitored

Monitoring Period

No. of Exceedances In

Event/Action Plan Implementation Status and Results

Action Level

Limit

Level

Air

1

Ambient TSP

(24-hour)

01/06/02-30/06/02

0

0

 

2

Ambient TSP

(1-hour)

01/06/02-30/06/02

0

0

 

Noise

1

Noise level at the critical NSR’s predicted by the noise alarm monitoring system

01/06/02-30/06/02

0

0

 

2

Manual noise monitoring at the Pak Kok Tsui residences

01/06/02-30/06/02

N/A

N/A

Hoarding works at Pak Kok Tsui were completed on 11/5/2002.  Civil works would tentatively commence on 1/8/2002.  Manual noise monitoring was suspended during the period from 12/5/2002 to 30/6/2002.

Water

1

DO

(Surface & Middle)

01/06/02-30/06/02

0

0

 

2

DO (Bottom)

01/06/02-30/06/02

0

0

 

3

SS

01/06/02-30/06/02

0

0

 

4

Turbidity

01/06/02-30/06/02

0

0

 

 

 

Waste Management  Records

 

The estimated amounts of different types of waste generated in June 2002 are shown in Table 5.2.

 

Table 5.2    Estimated Amounts of Waste Generated in June 2002

 

Waste Type

Examples

Estimated Amount

Site Formation

Dredged Materials

Marine Mud

-

Construction Waste

Concrete Waste, Used formwork

-

Excavated Materials

Rock and soil

-

General Refuse

Domestic wastes collected on site

2 m3

Unit L9 Piling Foundation

Construction Waste

Concrete Waste, Used formwork

-

Excavated Materials

Rock and soil

3,200m3

General Refuse

Domestic wastes collected on site

1.7 ton

Recycled Paper

Domestic wastes collected on site

15 kg

Aluminium

Domestic wastes collected on site

34 kg

 

 

5.3         Site Environmental Audit

 

Site audits were carried out by ET on a weekly basis to monitor environmental issues at the construction sites to ensure that all mitigation measures were implemented timely and properly.  The site conditions were generally satisfactory.  All required mitigation measures were implemented.  The weekly site inspection results are attached in Appendix I. 

 

 

5.4         Status of Environmental Licensing and Permitting

 

All permits/licenses obtained for the project are summarised in Table 5.3.

 

Table 5.3    Summary of Environmental Licensing and Permit Status

 

Description

Permit No.

Valid Period

highlights

Status

From

To

Varied Environmental Permit

EP-071/2000/B

 

13/07/01

 

-

The whole construction work site.

Valid

Construction Noise Permit

GW-UW0076-02

 

 

 

 

 

 

 

17/04/02

09/09/02

8 groups (A-H) of PME’s are assigned.

 

Only one group can be used.  Group G and H shall not be operated between 23:00 and 07:00 on next day.

Valid

 

 

Construction Noise Permit

GW-UW0036-02

06/03/02

31/08/02

Operation of specified PME’s allowed during the restricted hours (07:00-23:00 on holidays and 19:00-23:00 on all other days)

Valid. 

 

 

Construction Noise Permit

GW-UW0099-02

07/05/02

06/11/02

Operation of specified PME’s allowed during the restricted hour (23:00-07:00 on next day).  2 groups of PME’s are assigned and only one group can be used.  

Valid

 

Registration of Chemical Waste Producer

WPN5213-912-G1050-01

01/06/02

-

Unit L9 piling foundation work.

Valid

Dumping Permit

EP/MD/03-002

12/06/02

11/12/02

Dumping at South Cheung Chau Disposal Area; Unit L9 piling foundation work.

Valid

 

 

5.5         Implementation Status of Environmental Mitigation Measures

 

Mitigation measures detailed in the permits and the EM&A Manual (Construction Phase) are required to be implemented.  An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix J.

 

 

5.6         Implementation Status of Action/Limit Plans

 

The Action/Event Plans for air quality, noise and water quality extracted from the EM&A Manual (Construction Phase) and the review report on marine water quality monitoring are presented in Appendix H.

 

As all the action/limit level exceedances were not related to the construction work, no further action can be devised.  Nevertheless, EPD, IEC and the construction contractor have been informed of the exceedances accordingly as per the requirements in the EM&A Manual. 

 

 

 

5.7         Implementation Status of Environmental Complaint Handling Procedures

 

In June 2002, no complaint against the construction activities was received.

 

Table 5.4    Environmental Complaints / Enquiries Received in June 2002

 

Case Reference /

Date, Time Received /

Date, Time Concerned

Descriptions /Actions Taken

Conclusion /

Status

 

Nil

 

 

N/A

 

 

N/A

 

 

Table 5.5    Outstanding Environmental Complaints / Enquiries Received Before

 

Case Reference /

Date, Time Received /

Date, Time Concerned

Descriptions /Actions Taken

Conclusion /

Status

 

Nil

 

 

N/A

 

N/A

 




6.             FUTURE KEY ISSUES

 

 

6.1         Status of Natural Gas supply

 

Based on current project schedule, HEC anticipates there is no delay in the supply of natural gas.

 

 

6.2         Key Issues for the Coming Month

 

Key issues to be considered in the coming month include:

 

Site Formation

 

Noise Impact

·          To continue monitoring the noise level during construction and to ensure compliance with the CNP’s already obtained.

·          To continue the preventive measures for noise exceedance and keep monitoring/ reviewing the performance.

 

Water Impact

·          To keep reviewing the monitoring results in order to take corresponding action to ensure acceptable seawater quality.

·          To provide routine inspection and necessary maintenance for the silt curtain.

·          To complete the closure of the seawall by the end of July 2002 so that seawater quality impacts can further be minimized.

·          To remove the installed silt curtains after the closure of the seawall.

·          To carry out post project monitoring works for marine water quality for four weeks in the same manner as impact monitoring work after the closure of the seawall.  No further marine water quality monitoring is required after successful completion of post project monitoring.

 

In end June 2002, EPD and IEC have been informed of the schedule for removal of silt curtains and completion of marine water quality monitoring program.  The above arrangements are scheduled according to the requirements stipulated in the EIA report and the EM&A Manual (Construction Phase) for Lamma Extension.  HEC shall continue to exercise good site practice to ensure acceptable seawater quality.  Every effort will be made to eliminate impact on seawater.

 

Transmission System

 

Terrestrial Ecology Impact

·          To closely monitor the construction activities, if any, in order to avoid disturbance to the rare plants; 

·          To provide temporary fire fighting equipment for prevention of fire within the work sites.

                                      

 

Unit L9 Piling Foundation

 

Noise Impact

·          To continue monitoring the noise level during construction and to ensure compliance with the CNPs already obtained.

·          To continue the preventive measures for noise exceedance and keep monitoring/ reviewing the performance.

 

Air Impact

·          To spray water on the ground and road surface to prevent dust emission.

·          To continue monitoring and reviewing the emission of smoke from construction machines.

 

Water Impact

·          To recycle wastewater during the Bored Piling Works

 

Waste Management

·          To implement the Waste Management Plan.

 

6.3         Monitoring Schedules for the Next 3 Months

 

According to the EIA Report (Volume 2, Part F Section 5.1.1 Page 17), marine water quality monitoring has been carried out during the dredging operations.  As water quality impacts will further be minimized after the closure of the seawall (tentatively scheduled to complete by the end of July 2002), impact monitoring work will no longer be required and therefore should be terminated by that time.  Post project monitoring work shall then be carried out in the following four weeks (i.e. in August 2002) in the same manner as impact monitoring work. 

 

The hoarding works for the construction of transmission system at Pak Kok Tsui were completed on 11/5/2002. The civil works would tentatively commence in on 1/8/2002.  As there was no construction work during the period from 12/5/2002 to end June 2002, the manual noise monitoring at Pak Kok Tsui was suspended in June 2002.  The tentative environmental monitoring schedules for the next 3 months are shown in Appendix C.

 

 

6.4         Construction Program for the Next 3 Months

 

The tentative construction program for the next 3 months is shown in Appendix K.

 



7.             CONCLUSION

 

 

1-hour TSP monitoring work was rescheduled due to failure of the air conditioning unit for monitoring equipment and one marine water quality monitoring work was rescheduled due to damage of the monitoring probe cable.  Other than this, environmental monitoring and site inspection were performed as scheduled in the reporting month.  All monitoring results were checked and reviewed.

 

No Action/Limit level exceedance on 1-hour and 24-hour TSP level was recorded in the reporting month.

 

No Action/Limit level exceedance on noise was recorded in the reporting month.

 

No Action/Limit level exceedance on water quality parameters was recorded in the reporting month.

 

Environmental mitigation measures recommended in the EM&A manual for the construction activities were implemented in the reporting month.  No complaint against the construction activities was received in the reporting month.  No prosecution was received for this Project in the reporting period.

 

The environmental performance of the Project was generally satisfactory.