Appendix C Environmental
Monitoring Schedule
Table C.1 Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma Extension Construction (April 2004 to July 2004)
24hr TSP
Monitoring |
1hr TSP
Monitoring |
06/Apr/2004 |
06/Apr/2004 1500hr to 1800hr |
12/Apr/2004 |
12/Apr/2004 1500hr to 1800hr |
18/Apr/2004 |
18/Apr/2004 1500hr to 1800hr |
24/Apr/2004 |
24/Apr/2004 1500hr to 1800hr |
30/Apr/2004 |
30/Apr/2004 1500hr to 1800hr |
06/May/2004 |
06/May/2004 1500hr to 1800hr |
12/May/2004 |
12/May/2004 1500hr to 1800hr |
18/May/2004 |
18/May/2004 1500hr to 1800hr |
24/May/2004 |
24/May/2004 1500hr to 1800hr |
30/May/2004 |
30/May/2004 1500hr to 1800hr |
05/Jun/2004 |
05/Jun/2004 1500hr to 1800hr |
11/Jun/2004 |
11/Jun/2004 1500hr to 1800hr |
17/Jun/2004 |
17/Jun/2004 1500hr to 1800hr |
23/Jun/2004 |
23/Jun/2004 1500hr to 1800hr |
29/Jun/2004 |
29/Jun/2004 1500hr to 1800hr |
05/Jul/2004 |
05/Jul/2004 1500hr to 1800hr |
11/Jul/2004 |
11/Jul/2004 1500hr to
1800hr |
17/Jul/2004 |
17/Jul/2004 1500hr to 1800hr |
23/Jul/2004 |
23/Jul/2004 1500hr to
1800hr |
29/Jul/2004 |
29/Jul/2004 1500hr to 1800hr |
Table C.2 Manual Noise Monitoring Schedule for Transmission System Construction (May 2004 to July 2004)
Date |
Tentative Monitoring Start Time |
13/May/2004 |
11:00 |
17/May/2004 |
14:30 |
20/May/2004 |
11:00 |
24/May/2004 |
14:30 |
27/May/2004 |
11:00 |
31/May/2004 |
14:30 |
03/Jun/2004 |
11:00 |
07/Jun/2004 |
14:30 |
10/Jun/2004 |
11:00 |
14/Jun/2004 |
14:30 |
17/Jun/2004 |
11:00 |
21/Jun/2004 |
14:30 |
24/Jun/2004 |
11:00 |
28/Jun/2004 |
14:30 |
02/Jul/2004 |
11:00 |
06/Jul/2004 |
14:30 |
09/Jul/2004 |
11:00 |
13/Jul/2004 |
14:30 |
16/Jul/2004 |
11:00 |
20/Jul/2004 |
14:30 |
23/Jul/2004 |
11:00 |
27/Jul/2004 |
14:30 |
30/Jul/2004 |
11:00 |
Note: The hoarding works for
the construction of transmission system at Pak Kok Tsui were completed on 11/5/2002. The dredging
work for the formation of underwater trenches would tentatively commence in May 2004. As there would be no construction work
during the period from 12/5/2002 to end April 2004, the manual noise monitoring at Pak Kok
Tsui would temporarily be suspended within this period.