APPENDIX D  AIR QUALITY MONITORING RESULTS

 

Site: Lamma Power Station Extension

 

Month: November 2004

 

24 hour TSP Measurement:-

Date

TSP concentration (mg/m3)

Weather Information

(From Hong Kong Observatory)

Reservoir

 

(AM1)

East

Gate

(AM2)

Ash Lagoon

 

(AM3)

Tai Yuen Village

(AM4)

Mean Wind Speed

(km/hr)

Prevailing Wind Dir.

(°)

Mean R.H.

 

(%)

02/11/2004

117

95

99

94

21.7

010

71

08/11/2004

50

46

44

50

28.5

080

78

14/11/2004

60

45

54

44

12.7

060

82

20/11/2004

99

82

91

93

26.9

080

68

26/11/2004

164

138

125

103

33.5

010

66

 

1 hour TSP Measurement:-

Date

Time

TSP concentration (mg/m3)

Reservoir

(AM1)

East Gate

(AM2)

Ash Lagoon

(AM3)

02/11/2004

15:00-15:59

108

93

107

16:00-16:59

99

88

96

17:00-17:59

81

73

81

08/11/2004 (2)

15:00-15:59

70 (9/11)

45

47

16:00-16:59

72 (9/11)

45

48

17:00-17:59

68 (9/11)

48

51

14/11/2004

15:00-15:59

40

39

31

16:00-16:59

52

44

50

17:00-17:59

63

67

66

20/11/2004

15:00-15:59

89

84

90

16:00-16:59

99

95

101

17:00-17:59

87

81

88

26/11/2004

15:00-15:59

175

125

131

16:00-16:59

137

105

103

17:00-17:59

104

99

93

 

Remark:

(1)            The monitoring stations, Reservoir, East Gate & Ash Lagoon are located within Lamma Power Station.

(2)            TEOM 1-hr TSP sampler at AM1 (Reservoir) was found defective on 08/11/2004.  A make-up 1hr TSP sampling for AM1 was carried out on 09/11/2004.                                                                                         

 

                                                                               

 

                                                                        1-hr TSP                24-hr TSP

                                                                          (mg/m3)                   (mg/m3)

Action Level                                                      340                          190

Limit Level                                                          500                          260

 

 

 

Calibration:            Calibration details are shown in appendix F.

 

 

 

 

Equipment used:

Location

1-hr TSP

24-hr TSP

Reservoir and East Gate

TEOM 1400a

High Volume Air Sampler

Ash Lagoon

Partisol Model 2000 Sampler

Tai Yuen Village

-

MINIVOL Portable Sampler