APPENDIX D AIR QUALITY MONITORING RESULTS
Site: Lamma Power
Station Extension
Month: December 2004
24 hour TSP
Measurement:-
Date |
TSP concentration (mg/m3) |
Weather Information (From Hong Kong Observatory) |
|||||
Reservoir (AM1) |
East Gate (AM2) |
Ash Lagoon (AM3) |
Tai Yuen Village (AM4) |
Mean Wind Speed (km/hr) |
Prevailing Wind Dir. (°) |
Mean R.H. (%) |
|
02/12/2004 |
70 |
57 |
71 |
54 |
26.1 |
050 |
76 |
08/12/2004 |
141 |
120 |
105 |
99 |
21.2 |
010 |
55 |
14/12/2004 |
79 |
65 |
73 |
64 |
29.3 |
070 |
72 |
20/12/2004 |
95 |
72 |
78 |
81 |
17.6 |
090 |
81 |
26/12/2004 |
(1) |
40 |
43 |
60 |
28.8 |
090 |
78 |
30/12/2004 |
158 |
- |
- |
- |
33.9 |
010 |
68 |
1 hour TSP Measurement:-
Date |
Time |
TSP concentration (mg/m3) |
||
Reservoir (AM1) |
East Gate (AM2) |
Ash Lagoon (AM3) |
||
02/12/2004 |
15:00-15:59 |
71 |
58 |
71 |
16:00-16:59 |
71 |
61 |
73 |
|
17:00-17:59 |
73 |
65 |
76 |
|
08/12/2004 |
15:00-15:59 |
91 |
98 |
96 |
16:00-16:59 |
88 |
87 |
90 |
|
17:00-17:59 |
87 |
72 |
91 |
|
14/12/2004 |
15:00-15:59 |
61 |
61 |
58 |
16:00-16:59 |
59 |
50 |
58 |
|
17:00-17:59 |
59 |
55 |
63 |
|
20/12/2004 |
15:00-15:59 |
87 |
90 |
53 |
16:00-16:59 |
79 |
69 |
54 |
|
17:00-17:59 |
86 |
81 |
60 |
|
26/12/2004 |
15:00-15:59 |
39 |
39 |
40 |
16:00-16:59 |
51 |
47 |
46 |
|
17:00-17:59 |
46 |
43 |
48 |
Remark:
(1)
The monitoring stations, Reservoir, East Gate
& Ash Lagoon are located within Lamma Power Station.
(2)
HVAS 24-hr TSP sampler at AM1
(Reservoir) was found defective on 28/12/2004, during the collection of filter
sample. Defect was rectified on 29/12/2004. A make-up
24-hr TSP sampling for AM1 was carried out on 30/12/2004.
1-hr
TSP 24-hr
TSP
(mg/m3) (mg/m3)
Action Level 340 190
Limit Level 500 260
Calibration: Calibration
details are shown in appendix F.
Equipment used:
Location |
1-hr TSP |
24-hr TSP |
Reservoir and East Gate |
TEOM 1400a |
High Volume Air Sampler |
Ash Lagoon |
Partisol Model 2000 Sampler |
|
Tai Yuen Village |
- |
MINIVOL Portable Sampler |