Appendix
F Event/Action
Plans
Table F.1 Event
and Action Plans for Construction Noise
Exceedance |
ET Leader |
IEC |
Engineer |
Contractor |
Action Level |
Undertake noise measurement/check monitoring data to establish validity of complaint. If the complaint is valid, inform Engineer and IEC verbally. Identify the source(s) of the noise. Discuss remedial actions required with Contractor and Engineer. Increase manual monitoring frequency to assess efficacy of remedial measures. If exceedance continues, review implementation of appropriate mitigation measures. |
Review the analysed results submitted by the ET. Review the remedial measures proposed by the Contractor and advise the Engineer and ET accordingly. Verify the implementation of the remedial measures. |
Notify Contractor of the complaint if proven. Check Contractor's working methods and advise IEC and ET accordingly. Remind the Contractor of his contractual obligations and discuss remedial actions. Keep the Contractor informed of the efficacy of remedial actions. |
Submit proposals for remedial actions to Engineer. Amend proposals if required by the Engineer. Implement the remedial actions immediately upon instruction from the Engineer. Liaise with the Engineer to optimise the effectiveness of the agreed mitigation. |
Limit Level |
Repeat manual measurement/check monitoring data to confirm findings. Identify the source(s) of the impact. If the exceedance is found to be valid and due to the Construction works, verbally advise the Contractor, Engineer and IEC, and inform the EPD of the exceedance, as soon as practicable. Discuss remedial actions required with Engineer. Increase manual monitoring frequency to assess efficacy of remedial measures. |
Agree potential remedial actions with Engineer, ET and Contractor. Review Contractor¡¦s remedial actions / measures to ensure their effectiveness and advise the Engineer and ET accordingly. Verify the implementation of the remedial measures |
Notify Contractor of exceedance. Check Contractor's working methods and advise IEC and ET accordingly. Discuss with Contractor the remedial actions to be implemented. Keep the Contractor informed of the efficacy of remedial actions. If the exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop the portion of work until the exceedance is abated |
Take immediate action to avoid further exceedance. Submit proposals for remedial actions to Engineer. Amend proposals if required by the Engineer. Implement remedial actions immediately upon instruction from the Engineer. If the exceedance continues, consider what portion of the work is responsible and, as instructed by the Engineer, stop the portion of work until the exceedance is abated |