Appendix H: Summary of EMIS
Transmission System ¡V Civil Works (Part C of EIA Report)
Table H.1 Construction Phase Mitigation Measures and their Implementation
EM&A Log Ref. |
Mitigation Measures |
Implementation Status |
|
Air Quality |
|
J1 |
To mitigate potential construction related dust impacts, the dust control measures stipulated under the Air Pollution Control (Construction Dust) Regulation shall be complied with, such as: |
|
¡P all debris or materials shall be either covered or stored in a debris sheltered collection area; |
C |
|
¡P prior to any material handling, all dusty material shall be sprayed with water. |
C |
|
|
|
|
|
Water Quality |
|
K1 |
No mitigation measures are considered necessary. |
N/A |
|
|
|
|
Noise |
|
L1 |
Selection and use of quiet PMEs, or use of modest source noise controls with standard PMEs |
C |
L2 |
N5 Landing Point Selection and use of quiet PMEs
(particularly the barge-mounted crane), or use of comparably effective source
noise controls with the PMEs; |
C |
L3 |
For non-percussive piling ¡V use of equipment with a SWL of 113 dB(A) or less if there is no programme overlap of the piling with the site formation works, otherwise offsetting source noise controls shall be required. |
N/A |
L4 |
For percussive piling ¡V use of equipment with a SWL of 115 dB(A) or less, otherwise, offsetting source noise controls shall be required. |
N/A |
L5 |
If non-percussive piling and site formation activities are to be carried out simultaneously then careful equipment selection and source controls shall be required for both activities to reduce each by approximately 3 dB(A). |
N/A |
|
|
|
|
MARINE ECOLOGY |
|
M1 |
Construction of rubble mound seawalls for the
landing and launching points at |
C |
|
|
|
|
FISHERIES |
|
N1 |
No fisheries-specific mitigation measures are
required during the construction phase |
N/A |
|
|
|
|
TERRESTRIAL ECOLOGY The
following mitigation measures shall be implemented to protect the important
plant species and minimizing disturbance to the surrounding environment
through good construction practice, as recommended below: |
|
O1 |
Avoidance of impact on the uncommon and rare plant species Celtis biondii, Pteris dispar and Ardicia pusilla, and the restricted plants Vitis balansaeana, Pterospermum heterophyllum and Rhapis excelsa, by locating the landing points N4 & N5 and the connecting cable trough in areas outside where these plant species are located (Figures 9.4b & 9.4c, Part C, Volume 2), as well as close monitoring of the construction activity. |
C |
O2 |
The erection of fences along the boundary of construction sites before the commencement of works to prevent tipping, vehicle movements, and encroachment of personnel into adjacent wooded areas, particularly where the rare, uncommon and restricted plant species are located. |
C |
O3 |
Regular checking to ensue that the work site boundaries are not exceeded and that no damage occurs to surrounding areas. |
C |
O4 |
The prohibition and prevention of open fires within the work site boundary during construction and provision of temporary fire fighting equipment in the work area during construction. |
C |
|
|
|
|
Landscape and visual
impact |
|
P1 |
The visual impact of the Cable Landing Point I1 is considered negligible as it would have similar appearance as the existing sea wall and therefore no mitigation is required. |
N/A |
P2 |
The proposed landing points N2, N4 and N5, the following landscaping mitigation measures are recommended to minimize the potential impacts: |
|
|
¡P Although the size of the landing points varies (N2 is 26x70m, N4 is 27x65m and N5 is 33x56m), each has a finished platform level at +6.00mPD. With the Low Water Level at +1.00mPD, the platforms shall be a maximum of some 5m above the water level at low tide. In order to minimize the visual impact of the landing points, the exposed sides of the platforms and the cable slipways shall be screened with irregularly arranged boulders of varying sizes to mimic the natural coastline features. The horizontal platform surface shall be finished with natural materials such as stone pavings or tiles. |
C |
|
¡P The cable trough in between Landing Points N4 and N5 is 5.5m wide and 260m long. The walkway that is formed above the cable trough shall be shielded by boulders (or, where practicable, shrub planting) from potential viewers from the sea and horizontal surfaces be finished with natural materials such as stone paving. |
N/A |
|
¡P Appropriate compensatory landscaping shall be provided for any disruption to existing vegetation to blend in with the surrounding setting. |
N/A |
|
¡P As a planning gain, parts of the landing points N4 and N5 and the cable trough between the landing points can be used for amenity and recreational purposes. Some low maintenance fixtures, matching with the natural environment, shall be built or placed on the landing points for public use. HEC shall resolve any management and maintenance requirements of the proposed mitigation measures during the processing stage of wayleave agreements. If required by Government, HEC commit to bear the management and maintenance responsibilities of these facilities. |
N/A |
Remarks:
C - Compliance
with mitigation measure
NC - Non-compliance
with mitigation measure
N/A - Not
Applicable