Table of Content
1.1       Plant Availability during the Reporting
Month
1.2       Summary of EM&A Requirements
2.2       Summary of Results and Observations
3.2       Summary of Results and Observations
4.2       Summary of Results and Observations
4.3       Implementation Status on Thermal Plume and Residual
Chlorine Surveys
5.1       Review of Environmental Monitoring
Procedures
5.2       Assessment
of Environmental Monitoring Results
5.3       Implementation Status of Environmental
Mitigation Measures
5.4       Implementation Status of Event/Action Plans
5.5       Implementation Status of Environmental
Complaint Handling Procedures
6.1       Outage Plan for the coming 3 months
6.2       Key issues for the coming month
List of Tables
Table 2.1      Air
Quality Monitoring Parameter and Frequency
Table 3.1      Noise Monitoring Parameter and Frequency
Table 4.1      Water
Quality Monitoring Parameters and Frequencies
Table 5.1      Summary of Action/Limit Level Exceedances on Monitoring Parameters
Table 5.2      Environmental Complaints / Enquiries Received in April 2007
Table 5.3      Outstanding Environmental Complaints / Enquiries Carried Over
List of figure
Figure 3.1          Location
of Noise Monitoring Station
AppendiX
Appendix B Action and Limit Levels for Air Quality, Noise and Water Quality Monitoring
Appendix C Air Quality Monitoring Results
Appendix D      Noise Monitoring Results
Appendix E      Summary Results and Observations on Water Quality
Monitoring
EXECUTIVE SUMMARY
This is the seventh monthly Environmental Monitoring and Audit (EM&A) report for the Project “Operation of Lamma Power Station Extension prepared by the Environmental Team (ET). This report presents the results of impact monitoring on air quality, noise, water quality and environmental audit for the operation of the said project in April 2007.
Air quality,
noise and water quality monitoring were
performed. The results were checked against the established Action/Limit
(AL) levels.  The
implementation status
of the environmental mitigation measures, Event/Action
Plan and environmental complaint handling procedures were also checked.
Plant
Availability
Unit L9 was out of service during the following period:
| Period | Remark | 
| 04/04/2007
  20:00 to 07/04/2007 09:59 | Gas Turbine compressor off load blade washing | 
Environmental
Monitoring Works
Environmental monitoring works, as mentioned in the EM&A Manual (Operational
phase), were performed during the operation of Lamma Power Station Extension in the reporting
period.  
Air Quality
No exceedance of Action and Limit levels for stack NOx was
recorded in the reporting month
Noise
No exceedance of Action and Limit levels for noise was recorded in the reporting month.
Water Quality
No exceedance of Action and Limit levels for water quality was recorded in the reporting month.
Implementation
Status of Environmental Mitigation Measures
Environmental
mitigation measures were implemented in the reporting month.  
Environmental
Complaints
No
complaint against the Project was received in the reporting month.
Future key issues
Key issues to be considered in the coming month include:
Air Impact
· To continuously monitor the stack NOx for Lamma Power Station Extension.
Noise Impact
· To continuously monitor the noise for Lamma Power Station Extension.
Water Impact
· To continuously carry out the water quality monitoring for Lamma Power Station Extension.
Concluding
Remarks
The
environmental performance of the project was generally satisfactory.
The operational phase Lamma
Power Station Extension commenced in mid October 2006 following the completion of
erection works and commissioning tests for Unit L9.  The Environmental Team (hereinafter called
the “ET”) was formed within The Hongkong Electric Co.
Ltd (HEC) to undertake Environmental Monitoring and Audit for “Operation
of Lamma Power Station Extension” (hereinafter called the
“Project”).  Under the
requirements of Section 6 of Environmental Permit EP-071/2000/C, an EM&A
programme for impact environmental monitoring set out in the EM&A Manual (Operational
Phase) is required to be implemented.  In
accordance with the EM&A Manual, environmental monitoring of air quality,
noise and water quality are required for the Project.
This report
summarizes the environmental monitoring and audit work for the Project for the
month of April 2007.
1.1        
Plant Availability during the Reporting
Month
Unit L9 was out of service during
the following period:
| Period | Remark | 
| 04/04/2007
  20:00 to 07/04/2007 09:59 | Gas Turbine compressor off load blade washing | 
1.2 Summary of EM&A Requirements
The EM&A program requires environmental monitoring for air quality, noise and water quality. The EM&A monitoring work for air quality, noise and water quality are described in Sections 2, 3 and 4 respectively.
The following
environmental audits are summarized in Section 5 of the
report:
·       
Environmental
monitoring results;
·       
The
implementation status of environmental protection and pollution control /
mitigation measures.
The future key issues for the Project will be reported in Section 6 of this report.
In accordance
with the EM&A Manual (Operational Phase) for Lamma Extension, stack
NOx is continuously monitored.  Stack NOx monitoring data would be checked
against the Action/Limit
Levels stated in the EM&A Manual. The monitoring frequency is shown in Table 2.1 below:
Table 2.1    Air Quality
Monitoring Parameter and Frequency
| Parameter | Frequency | 
| Hourly
  Average Stack NOx | Continuous | 
2.2        
Summary
of Results and Observations
Monitoring
of stack NOx was
conducted during the operation of Unit L9 in the reporting month.  A monthly summary of monitoring data is shown in Appendix
C.  
No Action/Limit Level
exceedance on stack NOx was
recorded in the reporting month.  
In accordance with the EM&A Manual
for Lamma Extension (Operational Phase), continuous noise monitoring at Ash Lagoon is carried out to calculate the noise arising from the operation of Lamma Extension at the critical NSR at Hung
Shing Ye.  Baseline noise levels are applied for
correction to the noise monitoring data. 
The data after corrections would be checked
against the Limit Levels specified in the EM&A Manual.  
The noise monitoring location is shown in Figure 3.1.  The monitoring parameter and frequency are shown in Table 3.1 below:
 
Table 3.1    Noise
Monitoring Parameter and Frequency
| Parameter | Frequency  | Time Period | 
| 30-min LAeq | continuous  | 0700-2300 hrs and 2300-0700 hrs of next
  day | 
3.2 Summary of Results and Observations
Continuous noise
monitoring was conducted at the monitoring station at Ash Lagoon.
The monitoring
results are shown in Appendix D.  
No Action/Limit Level exceedance on noise was recorded in the reporting month.
Figure 3.1          Location of
Noise Monitoring Station   
In accordance with the EM&A Manual for Lamma
Extension (Operational Phase), the monitoring requirements for the EM&A
work should strictly follow the discharge licence for L1-L9 & GT57 issued under
the Water Pollution Control Ordinance (WPCO). 
The parameters as stated in Table 4.1 were monitored and checked against the
Action/Limit Levels as given in Appendix B.  
Table 4.1    Water Quality
Monitoring Parameters and Frequencies
| Item | Parameters | Frequencies | 
| 1 | Cooling
  Water Temperature Rise | Daily | 
| 2 | Total
  Residual Chlorine | Bi-weekly
   | 
| 3 | Temperature of
  Blowdown Effluent | At
  least twice per year  | 
| 4 | Suspended
  Solids from Blowdown Effluent  | At
  least twice per year  | 
| 5 | Grease
  & Oil from Blowdown Effluent | At
  least twice per year | 
| 6 | Scum of
  foam in ambient water | Daily | 
4.2        
Summary
of Results and Observations
 
Monitoring of
various parameters as listed in Table 4.1 above were carried out during the
operation of Unit L9 in the reporting month.  A monthly summary of the data is shown in Appendix E.
The data recorded for the monitoring
parameters were all below their corresponding Action/Limit Levels.  No Action/Limit level exceedance was recorded in the reporting
month.  There was no foam present within
500 meters of Hung Sing Ye Beach in the reporting month.  Details of the foam
observation report are also given in Appendix E.
 The effluent quality was generally
satisfactory.
4.3        
Implementation Status on Thermal Plume and Residual
Chlorine Surveys
One survey for thermal plume and residual
chlorine concentration at the seawater around the discharges from the Lamma
Power Station and Lamma Power Station Extension shall be carried out after the
commissioning of each of the generating units for the Project.  The first survey would be tentatively
conducted in the summer of 2007 for the first gas-fired combined cycle unit L9.
No survey was carried out in the reporting
month.  
5.1        
Review of Environmental
Monitoring Procedures 
The environmental monitoring
procedures were regularly reviewed by the Environmental Team.  No modification to the existing monitoring procedures was recommended.
5.2        
Assessment of Environmental Monitoring Results 
Monitoring results for Air Quality, Noise and Water Quality
The environmental monitoring results for air quality, noise and water quality in April 2007 presented in Sections 2, 3 and 4 respectively are summarized in Table 5.1.
Table 5.1    Summary of Action/Limit Level Exceedances on Monitoring Parameters 
| Item | Parameter Monitored | Monitoring Period | No. of Exceedances In | Event/Action Plan Implementation Status and Results | |
| Action Level | Limit Level | ||||
| Air | |||||
| 1 | Stack NOx | 01/04/07-30/04/07 | 0 | 0 |  | 
| Noise | |||||
| 1 | Noise levels at the critical NSR at Hung Shing Ye calculated by the noise alarm monitoring system | 01/04/07-30/04/07 | 0 | 0 |  | 
| Water | |||||
| 1 | Cooling Water Temperature Rise | 01/04/07-30/04/07 | 0 | 0 |  | 
| 2 | Total Residual Chlorine | 01/04/07-30/04/07 | 0 | 0 |  | 
| 3 | Temperature of Blowdown Effluent | 01/04/07-30/04/07 | N.A. | N.A.* |  | 
| 4 | Suspended Solids from Blowdown Effluent | 01/04/07-30/04/07 | N.A. | N.A.* |  | 
| 5 | Grease & Oil from Blowdown Effluent | 01/04/07-30/04/07 | N.A. | N.A.* |  | 
| 6 | Inspection of Scum/Foam in ambient water | 01/04/07-30/04/07 | 0 | 0 |  | 
Note: * Monitoring was not scheduled in the
reporting month
Land Contamination
There
was no land contamination incident happened in the reporting month.
Waste Management
Waste
management practice was properly implemented for operation of the project as
outlined in the Waste Management Plan for Lamma Power Station Extension. There was
no unacceptable environmental impact on waste management in the reporting
month.
5.3        
Implementation Status of
Environmental Mitigation Measures 
Mitigation measures
detailed in the permits and the EM&A Manual (Operational Phase) are
required to be implemented.  An updated
summary of the Environmental
Mitigation Implementation Schedule (EMIS) is presented in
Appendix F.
 
5.4 Implementation Status of Event/Action Plans
The Event/Action Plans for air quality, noise and water quality extracted from the EM&A Manual (Operational Phase) are presented in Appendix A.
5.5 Implementation Status of Environmental Complaint Handling Procedures
In April 2007, no complaint against the Project was received.
Table 5.2      Environmental
Complaints / Enquiries Received in April 2007
| Case Reference / Date, Time Received / Date, Time Concerned | Descriptions / Actions Taken | Conclusion / Status | 
| Nil | N/A | N/A | 
Table 5.3    Outstanding Environmental Complaints / Enquiries Carried Over 
| Case Reference / Date, Time Received / Date, Time Concerned | Descriptions / Actions Taken | Conclusion / Status | 
| Nil | N/A | N/A | 
6.1        
Outage
Plan for the coming 3 months
The major outage plan for the next 3 months is shown below:
| Date | Remark | 
| 05/06/2007 to 21/06/2007 | Combustor inspection and GRS defects rectification | 
6.2 Key issues for the coming month
Key issues to be considered in the coming month include:
Air Impact
· To continuously monitor the stack NOx for Lamma Power Station Extension.
Noise
Impact
· To continuously monitor the noise for Lamma Power Station Extension.
Water Impact
· To continuously carry out the water quality monitoring for Lamma Power Station Extension.
Environmental monitoring was performed as required in the reporting month. All monitoring results were checked and reviewed.
No Action/Limit
level exceedance
on stack NOx was recorded in the reporting month
No Action/Limit level exceedance on noise was recorded in the reporting month.
No Action/Limit level exceedance on water quality parameters was recorded in the reporting month.
Environmental
mitigation measures recommended in the EM&A Manual for the operational
activities were implemented in the reporting month.  No complaint against
the Project was received in the reporting month.  No prosecution was received for this Project in the
reporting period.  
The environmental performance of the Project was
generally satisfactory.
Table A.1 Event/Action Plan for Air Quality
| Exceedance | ET Leader  | IEC | Operations Engineer | 
| Action Level | |||
| Exceedance of
  one sample | Identify source; Inform IEC
  verbally; Repeat
  measurement to confirm finding. | Check monitoring
  data submitted by ET Leader and advise ET Leader for any finding. | Rectify any
  unacceptable practice; Amend any working methods if appropriate. | 
|  |  |  |  | 
| Exceedance of
  two or more consecutive samples | Identify source; Inform IEC
  verbally; Repeat
  measurement to confirm finding; Increase
  monitoring frequency; Discuss with Operations Engineers on remedial actions required; If exceedance
  stops, discontinue additional monitoring. | Check monitoring
  data submitted by ET Leader and advise ET Leader for any finding; Verify the
  implementation of the remedial measures; | Discuss with ET Leader on remedial actions
  required; Implement the
  agreed remedial actions. | 
| Limit level | |||
| Exceedance of
  one sample | Repeat
  measurement to confirm finding; Identify the
  source(s) of the impact. Verbally inform IEC
  and EPD of the exceedance as soon as practicable;  Discuss with Operations Engineers on remedial actions required; Increase
  monitoring frequency; Assess the
  effectiveness of the remedial actions and keep IEC and EPD informed of the
  results. | Check monitoring
  data submitted by ET Leader and advise ET Leader of any finding; Verify the
  implementation of the remedial measures. | Take immediate
  action to avoid further exceedances; Discuss with ET Leader on remedial actions
  required; Implement the agreed
  remedial actions. | 
|  |  |  |  | 
| Exceedance of
  two or more consecutive samples | Identify source; Identify the
  source(s) of the impact.  Verbally inform IEC and EPD of the exceedance
  as soon as practicable;  Repeat
  measurement to confirm finding; Increase monitoring
  frequency; Carry out
  analysis on existing control procedures to determine
  possible mitigation to be implemented; Discuss with Operations Engineers on the remedial actions to be taken; If exceedance
  stops, discontinue additional monitoring. | Provide feedback
  and advise ET Leader/Operations Engineers on the effectiveness of the remedial actions proposed by them;  Verify the
  implementation of the remedial measures. | Take immediate
  action to avoid further exceedance; Discuss with ET Leader on remedial actions
  required; Implement the
  agreed remedial actions; Check the suspected defective parts if the problem still does not come
  under control. | 
Table A.2         Event/Action Plan for Noise
| Exceedance | ET Leader | IEC | Operations Engineer | 
| Action Level | If the complaint against Lamma
  Extension operation is valid, identify the source(s) of the noise and propose remedial measures if necessary; | Verify
  the implementation of the remedial measures. | Discuss
  with ET Leader on remedial
  actions required; Implement the agreed remedial actions.  | 
| Limit Level | Check monitoring data to confirm
  findings;  Identify
  the source(s) of the impact. If the exceedance is found to be valid and due to
  the Lamma Extension operation, verbally inform IEC and EPD of the exceedance as soon as practicable; Discuss with Operations Engineers on remedial actions required. | Check monitoring
  data submitted by ET Leader and advise ET Leader of any finding; Verify
  the implementation of the remedial measures. | Take
  action to avoid further exceedance;  Discuss
  with ET Leader on the
  remedial actions required; Implement the agreed remedial actions. | 
Table A.3         Event/Action Plan for Water Quality
| Exceedance
    | ET
   Leader | IEC | Operations Engineer | 
| Action
  Level |  | ||
| Exceedance on one sampling day | Identify
  source(s) of impact; Verbally
  inform IEC. | Check monitoring data submitted by ET Leader and
  advise ET Leader for any findings. | Rectify
  unacceptable practice; Amend any working methods if appropriate. | 
| Exceedances on more than one consecutive sampling day | Identify
  source(s) of impact; Verbally
  inform IEC; Repeat
  in-situ measurements to confirm findings; Discuss with Operations Engineers on remedial actions required; Increase monitoring frequency; If exceedance stops, discontinue additional
  monitoring. | Check
  monitoring data submitted by ET Leader and
  advise ET Leader for any
  finding; Verify
  the implementation of the remedial measures. | Discuss
  with ET Leader on remedial actions required; Implement
  the agreed remedial actions. | 
| Limit Level |  |  |  | 
| Exceedance on one sampling day | Identify
  the source(s) of impact; Verbally
  inform IEC and EPD of the exceedance, as soon as practicable; Repeat
  measurement to confirm finding; Discuss with Operations Engineers on remedial actions required; Increase
  monitoring frequency; Assess
  the effectiveness of the remedial actions and keep IEC and EPD informed of
  the results. | Check
  monitoring data submitted by ET Leader and
  advise ET Leader for any
  finding; Verify
  the implementation of the remedial measures. | Take
  immediate action to avoid further exceedance; Discuss
  with ET Leader on remedial actions required; Implement
  the agreed remedial actions. | 
| Exceedances on
  more than one consecutive sampling day | Identify
  the source(s) of impact;   Verbally
  inform IEC and EPD of the exceedance as soon as practicable; Repeat
  measurement to confirm finding; Discuss with Operations Engineers on remedial actions required; Increase
  monitoring frequency; Carry
  out analysis on existing control procedures
  to determine possible mitigation to be implemented; If
  exceedance stops, discontinue additional monitoring. | Provide
  feedback and advise ET
  Leader/Operations Engineers on the effectiveness of the remedial actions proposed; Verify
  the implementation of the remedial measures. | Take
  immediate action to avoid further exceedance; Discuss
  with ET Leader on remedial actions required; Implement
  the agreed remedial actions; Check the suspected defective parts if the problem
  still does not come under control.  | 
Appendix B     Action and Limit
Levels for Air Quality, Noise and Water Quality Monitoring
B.1      Air
| Parameter | Frequency | Action | Limit | 
| Hourly Average Stack NOx | Continuous | 81 mg/Nm3 | 90 mg/Nm3 | 
B.2. Noise
| Parameter | Frequency | Action | Limit | 
| Noise Levels at the critical
  NSR at Hung
  Shing Ye calculated by the noise alarm monitoring system | Continuous | When more than one complaint
  is received within two weeks, which are concerning the same event or location | a.  60
  dB(A) in LAeq,30
  min (07:00-23:00 hrs) b.  50
  dB(A) in LAeq,30
  min (23:00-07:00 hrs on next day) | 
B.3      Water
| Monitoring Area / Location | Parameters to be Monitored | Frequency | Concentration Not to Be Exceeded | Action | Limit | 
| Trade
  Effluent Cooling Water | Temperature | Daily, when the combined cycle unit is operating | Temperature at outfall should
  not exceed that at intake by > 10°C  | 9.5°C | +10°C
  above intake | 
| Total Residual Chlorine | Bi-weekly, when the combined cycle unit is
  operating | 0.5mg/L | 0.47 | 0.5 | |
| Trade Effluent Boiler Blowdown  | Temperature | At least twice per year, when the combined cycle unit is operating | 40°C | - | 40°C | 
| Suspended Solids | At least twice per year, when the combined cycle unit is operating  | 30 mg/L | - | 30 | |
| Grease & Oil | At least twice per year, when the combined cycle unit is operating | 20 mg/L | - | 20 | |
| Marine waters cooling water outfall | Scum
  of foam in ambient water | Daily, when the combined cycle unit is operating  | No scum within 500 m of Hung Shing Ye Beach | When scum passes the station south-west corner and north-west corner | No scum within 500 m of Hung Shing Ye Beach | 
Appendix
C     Air Quality Monitoring Results
Site:       Lamma Power Station – Unit L9
Month:  April 2007
Monthly Summary of
Stack NOx
   
| Date | Daily
   Maximum Stack NOx concentration (mg/Nm3)# | 
| 1/4/2007 | 63 | 
| 2/4/2007 | 63 | 
| 3/4/2007 | 75 | 
| 4/4/2007 | 77 | 
| 5/4/2007 | N.A. * | 
| 6/4/2007 | N.A. * | 
| 7/4/2007 | 62 | 
| 8/4/2007 | 70 | 
| 9/4/2007 | 73 | 
| 10/4/2007 | 69 | 
| 11/4/2007 | 70 | 
| 12/4/2007 | 74 | 
| 13/4/2007 | 70 | 
| 14/4/2007 | 67 | 
| 15/4/2007 | 68 | 
| 16/4/2007 | 61 | 
| 17/4/2007 | 59 | 
| 18/4/2007 | 75 | 
| 19/4/2007 | 72 | 
| 20/4/2007 | 70 | 
| 21/4/2007 | 64 | 
| 22/4/2007 | 62 | 
| 23/4/2007 | 60 | 
| 24/4/2007 | 60 | 
| 25/4/2007 | 70 | 
| 26/4/2007 | 70 | 
| 27/4/2007 | 67 | 
| 28/4/2007 | 65 | 
| 29/4/2007 | 63 | 
| 30/4/2007 | 62 | 
Note: # -    Hourly average value.  Expressed as at 0ºC, 101.325kPa, dry and
corrected to 15% O2 condition.
          * -  
Unit L9 was not on load.
Appendix
D    Noise Monitoring Results
Site:                                    Lamma Power
Station Extension 
Measurement Location:       Ash Lagoon 
Measurement Parameter:    30-min Leq (07:00-23:00 hrs
and 23:00-07:00 hrs on next
day)
| Date | Time | Calculated Noise Level at  NSR
   at Hung Shing Ye (dB(A)) | Limit Noise Level (dB(A)) | |
| Max | Avg | |||
| 01/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 01/04/2007 | 23:00-07:00 | --- | --- | 50 | 
| 02/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 02/04/2007 | 23:00-07:00 | 34 | 28 | 50 | 
| 03/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 03/04/2007 | 23:00-07:00 | 33 | 29 | 50 | 
| 04/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 04/04/2007 | 23:00-07:00 | 26 | 24 | 50 | 
| 05/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 05/04/2007 | 23:00-07:00 | 39 | 32 | 50 | 
| 06/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 06/04/2007 | 23:00-07:00 | 32 | 28 | 50 | 
| 07/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 07/04/2007 | 23:00-07:00 | 39 | 32 | 50 | 
| 08/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 08/04/2007 | 23:00-07:00 | 43 | 37 | 50 | 
| 09/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 09/04/2007 | 23:00-07:00 | 45 | 37 | 50 | 
| 10/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 10/04/2007 | 23:00-07:00 | 48 | 39 | 50 | 
| 11/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 11/04/2007 | 23:00-07:00 | 35 | 33 | 50 | 
| 12/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 12/04/2007 | 23:00-07:00 | 34 | 30 | 50 | 
| 13/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 13/04/2007 | 23:00-07:00 | 35 | 32 | 50 | 
| 14/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 14/04/2007 | 23:00-07:00 | 37 | 31 | 50 | 
| 15/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 15/04/2007 | 23:00-07:00 | 34 | 32 | 50 | 
| 16/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 16/04/2007 | 23:00-07:00 | 32 | 29 | 50 | 
| 17/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 17/04/2007 | 23:00-07:00 | 33 | 31 | 50 | 
| 18/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 18/04/2007 | 23:00-07:00 | 36 | 33 | 50 | 
| 19/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 19/04/2007 | 23:00-07:00 | 40 | 37 | 50 | 
| 20/04/2007 | 07:00-23:00 | 41 | 41 | 60 | 
| 20/04/2007 | 23:00-07:00 | 31 | 29 | 50 | 
| 21/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 21/04/2007 | 23:00-07:00 | 30 | 30 | 50 | 
| 22/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 22/04/2007 | 23:00-07:00 | 37 | 37 | 50 | 
| 23/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 23/04/2007 | 23:00-07:00 | --- | --- | 50 | 
| 24/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 24/04/2007 | 23:00-07:00 | 34 | 29 | 50 | 
| 25/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 25/04/2007 | 23:00-07:00 | 31 | 29 | 50 | 
| 26/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 26/04/2007 | 23:00-07:00 | 34 | 30 | 50 | 
| 27/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 27/04/2007 | 23:00-07:00 | 42 | 35 | 50 | 
| 28/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 28/04/2007 | 23:00-07:00 | 36 | 33 | 50 | 
| 29/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 29/04/2007 | 23:00-07:00 | 31 | 28 | 50 | 
| 30/04/2007 | 07:00-23:00 | --- | --- | 60 | 
| 30/04/2007 | 23:00-07:00 | 35 | 30 | 50 | 
Note:    “---
“ represents the measured noise monitoring data lower than the
established notional background level/discarded
under strong wind.
Appendix
E     Summary Results and Observations on Water Quality Monitoring
Maximum Outlet Temperature Rise (Deg. Celsius) of Cooling Water at
C.W. Outfall No.3 Serving L9 Condensers
Weighted by Flowrates of Individual Streams (April 2007)
| Date | Maximum Outlet Temperature Rise (Deg. Celsius) | 
| 01/04/2007 | 8.3 | 
| 02/04/2007 | 8.7 | 
| 03/04/2007 | 8.3 | 
| 04/04/2007 | 8.6 | 
| 05/04/2007 | N.A.* | 
| 06/04/2007 | N.A.* | 
| 07/04/2007 | 8.6 | 
| 08/04/2007 | 8.4 | 
| 09/04/2007 | 8.3 | 
| 10/04/2007 | 8.6 | 
| 11/04/2007 | 8.7 | 
| 12/04/2007 | 8.7 | 
| 13/04/2007 | 8.6 | 
| 14/04/2007 | 8.3 | 
| 15/04/2007 | 8.2 | 
| 16/04/2007 | 8.6 | 
| 17/04/2007 | 8.6 | 
| 18/04/2007 | 8.3 | 
| 19/04/2007 | 8.2 | 
| 20/04/2007 | 8.2 | 
| 21/04/2007 | 8.2 | 
| 22/04/2007 | 8.3 | 
| 23/04/2007 | 8.4 | 
| 24/04/2007 | 8.5 | 
| 25/04/2007 | 8.3 | 
| 26/04/2007 | 8.4 | 
| 27/04/2007 | 8.8 | 
| 28/04/2007 | 8.8 | 
| 29/04/2007 | 8.8 | 
| 30/04/2007 | 8.7 | 
Total
Residual Chlorine Level at C.W. Outfall No. 3 (April 2007)
| Date of sampling | 12/04/2007 | 26/04/2007 | 
| Total
  Residual Chlorine, mg/L | 0.30 | 0.30 | 
Blowdown from
Unit L9 Steam Turbine and HRSG to C.W. Outfall No. 3 (April 2007)
| Source of Discharge | HSRG | Steam Turbine | 
| Suspended Solid, mg/L | N.A. # | N.A. # | 
| Grease & Oil, mg/L | N.A. # | N.A. # | 
| Temperature, Deg. Celsius | N.A. # | N.A. # | 
Observation
of Scum Formation in Marine Waters Mixing Zone at Lamma Power Station Extension
(April 2007)
| Date | Observation | 
| 01/04/2007 | No
  scum within 500m of  | 
| 02/04/2007 | No
  scum within 500m of  | 
| 03/04/2007 | No
  scum within 500m of  | 
| 04/04/2007 | No
  scum within 500m of  | 
| 05/04/2007 | No
  scum within 500m of  | 
| 06/04/2007 | No
  scum within 500m of  | 
| 07/04/2007 | No
  scum within 500m of  | 
| 08/04/2007 | No
  scum within 500m of  | 
| 09/04/2007 | No
  scum within 500m of  | 
| 10/04/2007 | No
  scum within 500m of  | 
| 11/04/2007 | No
  scum within 500m of  | 
| 12/04/2007 | No
  scum within 500m of  | 
| 13/04/2007 | No
  scum within 500m of  | 
| 14/04/2007 | No
  scum within 500m of  | 
| 15/04/2007 | No
  scum within 500m of  | 
| 16/04/2007 | No
  scum within 500m of  | 
| 17/04/2007 | No
  scum within 500m of HSY Beach & NW/SW corner of the Station; Some foam
  outside CW Outfall and defoamer added to Outfall No.1 & No.2   | 
| 18/04/2007 | No
  scum within 500m of  | 
| 19/04/2007 | No
  scum within 500m of  | 
| 20/04/2007 | No
  scum within 500m of  | 
| 21/04/2007 | No
  scum within 500m of HSY Beach & NW/SW corner of the Station; Some foam
  outside CW Outfall and defoamer added to Outfall No.1 & No.2   | 
| 22/04/2007 | No
  scum within 500m of  | 
| 23/04/2007 | No
  scum within 500m of  | 
| 24/04/2007 | No
  scum within 500m of  | 
| 25/04/2007 | No
  scum within 500m of  | 
| 26/04/2007 | No
  scum within 500m of  | 
| 27/04/2007 | No
  scum within 500m of HSY Beach & NW/SW corner of the Station; Some foam
  outside CW Outfall and defoamer added to Outfall No.1 & No.2   | 
| 28/04/2007 | No
  scum within 500m of  | 
| 29/04/2007 | No
  scum within 500m of  | 
| 30/04/2007 | No
  scum within 500m of  | 
| Notes: |  | 
| 1.   *
  Unit L9 was not on load. | |
| 2.   #
  Monitoring was not scheduled in the reporting month. | |
| EM&A Log Ref. | Mitigation Measures | Implementation Status | 
|  | Air Quality |  | 
| A1 | Implement the gas-fired units as base-load units. For the existing power station, the more efficient units incorporating FGD and low NOx systems shall be operated first under normal situation to meet system demand. In case of any deviations from this, EPD shall be notified of the details and circumstances for the deviation. | Complied | 
| A2 | HEC shall
  undertake annual revisions and update of its GHG emissions inventory, which
  covers all HEC existing facilities and new extension, for at least the six
  GHGs specified under the Kyoto Protocol (CO2, CH4, N2O, HFCs, PFCs and
  SF6).  The inventory shall be established
  and maintained in accordance with the latest IPCC Guidelines or any other
  guidelines issued by Government, with details documented for regular reviews
  and updates. The inventory shall be reported on an annual basis, including
  actual figures and targets for the previous and current years, as well as the
  next year's forecast.  Discrepancies
  for actual versus target figures and actions for improvement or enhancement
  shall be discussed.  HEC shall update
  the inventory according to the figures of the electricity load forecast, upon
  every subsequent review by the Government. 
  This shall also be reported in the annual report.   (The annual report of GHG emissions inventory shall be deposited with the Director of Environmental Protection within three months after the end of the reporting period.) | Complied | 
|  |  |  | 
|  | Water Quality |  | 
| B1 | No further mitigation measures were found to be necessary provided the
  discharge of cooling water and residual chlorine are kept below the rates
  assumed in the water quality assessment*. *All discharges of effluent/wastewater shall be controlled through licensing under the Technical Memoradum for Effluents Discharged into Drainage and Sewerage Systems. Inland and Coastal Waters, issued under Section 21 of the Water Pollution Control Ordinance. | Complied | 
|  |  |  | 
|  | Noise |  | 
| C1 | HEC shall implement the gas-fired units for based-load operation to minimize the noise generated from the existing units. | Complied | 
|  |  |  | 
|  | Landscape & Visual impacts |  | 
| D1 | No mitigation measures were considered necessary. | N/A | 
|  |  |  | 
| EM&A Log Ref. | Mitigation Measures | Implementation Status | 
|  | LAND CONTAMINATION AND WASTE MANAGEMENT |  | 
| E1 | HEC shall
  maintain records of the following items: -        
  integrity
  testing of light oil tanks*; 
 
 
 -        
  quantities
  of chemical and chemical waste; -        
  incident
  of spillage and remediation actions; and  -        
  emergency
  response training and drills. * As the
  Light Gas Oil (LGO) for Lamma Extension is supplied from the existing LGO
  storage tanks located at Lamma Power Station, there is no LGO storage tank at
  Lamma Extension. | Complied | 
|  | Marine Ecology |  | 
| F1 | No mitigation measures were considered necessary. | N/A | 
|  |  |  | 
|  | fisheries |  | 
| G1 | No mitigation measures were considered necessary. | N/A | 
|  |  |  | 
|  | RISK ASSESSMENT |  | 
| H1 | No mitigation measures were considered necessary. | N/A |