APPENDIX D  AIR QUALITY MONITORING RESULTS

 

Site: Lamma Power Station Extension

 

Month: March 2017

 

24 hour TSP Measurement:-

Date

TSP concentration (mg/m3)

Weather Information

(From Hong Kong Observatory)

Reservoir

 

(AM1)

East

Gate

(AM2)

Ash Lagoon

 

(AM3)

Tai Yuen Village

(AM4)

Mean Wind Speed

(km/hr)

Prevailing Wind Dir.

(°)

Mean R.H.

 

(%)

05/03/2017

53

50

58

71

15.9

040

83

11/03/2017

30

28

17

11

31.7

060

88

17/03/2017

45

58

39

26

34.4

060

86

23/03/2017

43

57

46

50

16.3

050

84

29/03/2017

85

73

66 (30/3)*

79

27.7

060

84

* -     TSP monitoring at AM3 (Ash Lagoon) was suspended on 29/03/2017 due to replacement work of TEOM TSP sampler.  Make-up 24-hr TSP sampling at AM3 was conducted on 30/03/2017.

 

 

1 hour TSP Measurement:-

Date

Time

TSP concentration (mg/m3)

Reservoir

(AM1)

East Gate

(AM2)

Ash Lagoon

(AM3)

05/03/2017

15:00 - 15:59

64

53

69

16:00 - 16:59

50

47

70

17:00 - 17:59

46

42

44

11/03/2017

15:00 - 15:59

19

24

12

16:00 - 16:59

20

24

11

17:00 - 17:59

22

32

18

17/03/2017

15:00 - 15:59

30

27

25

16:00 - 16:59

29

31

23

17:00 - 17:59

33

36

36

23/03/2017

15:00 - 15:59

13

25

22

16:00 - 16:59

27

33

28

17:00 - 17:59

35

33

31

29/03/2017

15:00 - 15:59

75

74

78 (30/3)*

16:00 - 16:59

82

80

75 (30/3)*

17:00 - 17:59

82

83

70 (30/3)*

* -     TSP monitoring at AM3 (Ash Lagoon) was suspended on 29/03/2017 due to replacement work of TEOM TSP sampler.  Make-up 1-hr TSP sampling at AM3 was conducted on 30/03/2017.

 

                                                                        1-hr TSP               24-hr TSP

                                                                         (mg/m3)                   (mg/m3)

Action Level                                                      340                         190

Limit Level                                                        500                         260

 

Calibration:          Calibration details are shown in appendix F.

 

Equipment used:

Location

1-hr TSP

24-hr TSP

Reservoir and East Gate

TEOM

High Volume Air Sampler

Ash Lagoon

TEOM

TEOM

Tai Yuen Village

-

MINIVOL Portable Sampler