Appendix H   Summary of Site Audit Findings

 

L10 Piling Foundation Work (275 kV S/S Construction Sites)

 

Dates of Inspection: 03/03/2017, 10/03/2017, 17/03/2017, 24/03/2017 and 31/3/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.

 

 


 

L10 Civil & Building Superstructure Work

 

Dates of Inspection: 07/03/2017, 14/03/2017, 21/03/2017 and 28/03/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.


 

L11 Piling Foundation Work

 

Dates of Inspection: 03/03/2017, 10/03/2017, 17/03/2017, 24/03/2017 and 31/3/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.