Appendix H   Summary of Site Audit Findings

 

L10 Civil & Building Superstructure Work

 

Dates of Inspection: 04/07/2017, 11/07/2017, 18/07/2017 and 28/07/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.

 


 

L10 Mechanical, Electrical, Instrumentation & Control Erection Work

 

Dates of Inspection: 05/07/2017, 14/07/2017, 21/07/2017 and 28/07/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.


 

L11 Piling Foundation Work

 

Dates of Inspection: 07/07/2017, 14/07/2017, 20/07/2017 and 28/07/2017.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.