APPENDIX D  AIR QUALITY MONITORING RESULTS

 

Site: Lamma Power Station Extension

 

Month: October 2017

 

24 hour TSP Measurement:-

Date

TSP concentration (mg/m3)

Weather Information

(From Hong Kong Observatory)

Reservoir

 

(AM1)

East

Gate

(AM2)

Ash Lagoon

 

(AM3)

Tai Yuen Village

(AM4)

Mean Wind Speed

(km/hr)

Prevailing Wind Dir.

(°)

Mean R.H.

 

(%)

1/10/2017

12

29

27

35

28.5

90

86

7/10/2017

40

39

17

65

39.7

70

74

13/10/2017

37 (17/10)*

69

56

63

34.8

360

64

19/10/2017

58

75

43

22

33.5

350

71

25/10/2017

66

63

60

71

32.3

70

69

31/10/2017

103

92

94

89

31.2

70

61

Note:

* -    TSP monitoring at AM1 (Reservoir) was suspended on 13/10/2017 due to the breakdown of the High
        Volume Air Sampler. Make-up 24-hr TSP sampling at AM1 was conducted on 17/10/2017.

 

1 hour TSP Measurement:-

Date

Time

TSP concentration (mg/m3)

Reservoir

(AM1)

East Gate

(AM2)

Ash Lagoon

(AM3)

1/10/2017

15:00 - 15:59

35

27

30

16:00 - 16:59

19

23

23

17:00 - 17:59

28

22

21

7/10/2017

15:00 - 15:59

65

54

67 (9/10)*

16:00 - 16:59

49

38

51 (9/10)*

17:00 - 17:59

47

37

43 (9/10)*

13/10/2017

15:00 - 15:59

39

57

45

16:00 - 16:59

33

70

68

17:00 - 17:59

66

82

76

19/10/2017

15:00 - 15:59

73

71

78

16:00 - 16:59

48

72

64

17:00 - 17:59

49

65

51

25/10/2017

15:00 - 15:59

54

54

56

16:00 - 16:59

55

55

55

17:00 - 17:59

55

55

54

31/10/2017

15:00 - 15:59

108

92

93

16:00 - 16:59

108

90

87

17:00 - 17:59

99

88

82

Note:

* -    TSP monitoring at AM3 (Ash Lagoon) was suspended on 07/10/2017 due to the breakdown of the TEOM TSP sampler. Make-up 1-hr TSP sampling at AM3 was conducted on 09/10/2017.

 

                                                                        1-hr TSP               24-hr TSP

                                                                         (mg/m3)                   (mg/m3)

Action Level                                                      340                         190

Limit Level                                                        500                         260

 

Calibration:          Calibration details are shown in appendix F.

 

Equipment used:

 

Location

1-hr TSP

24-hr TSP

Reservoir and East Gate

TEOM

High Volume Air Sampler

Ash Lagoon

TEOM

TEOM

Tai Yuen Village

-

MINIVOL Portable Sampler