Appendix H   Summary of Site Audit Findings

 

L10 Civil & Building Superstructure Work

 

Dates of Inspection: 06/03/2018, 13/03/2018, 20/03/2018 and 27/03/2018.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.

 


 

L10 Mechanical, Electrical, Instrumentation & Control Erection Work

 

Dates of Inspection: 02/03/2018, 09/03/2018, 16/03/2018, 23/03/2018 and 29/03/2018.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.


 

L11 Piling Foundation Work

 

Dates of Inspection: 02/03/2018, 09/03/2018, 16/03/2018, 23/03/2018 and 29/03/2018.

 

Summary of Findings

General

 

-                      No environmental deficiency identified.

 

Air Quality

 

-                      No environmental deficiency identified. 

 

Noise

 

-                      No environmental deficiency identified.

 

Water Quality

 

-                      No environmental deficiency identified.

 

Waste Management

 

-                      No environmental deficiency identified.