Appendix C   Environmental Monitoring Schedule

 

 

Table C.1         Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma Extension Construction (February 2019 to May 2019)

 

24hr TSP Monitoring

1hr TSP Monitoring

05/February/2019

05/February/2019 1500hr to 1800hr

11/February/2019

11/February/2019  1500hr to 1800hr

17/February/2019

17/February/2019  1500hr to 1800hr

23/February/2019

23/February/2019  1500hr to 1800hr

01/March/2019

01/March/2019  1500hr to 1800hr

07/March/2019

07/March/2019  1500hr to 1800hr

13/March/2019

13/March/2019  1500hr to 1800hr

19/March/2019

19/March/2019  1500hr to 1800hr

25/March/2019

25/March/2019  1500hr to 1800hr

31/March/2019

31/March/2019  1500hr to 1800hr

06/April/2019

06/April/2019 1500hr to 1800hr

12/April/2019

12/April/2019 1500hr to 1800hr

18/April/2019

18/April/2019 1500hr to 1800hr

24/April/2019

24/April/2019 1500hr to 1800hr

30/April/2019

30/April/2019 1500hr to 1800hr

06/May/2019

06/May/2019 1500hr to 1800hr

12/May/2019

12/May/2019 1500hr to 1800hr

18/May/2019

18/May/2019 1500hr to 1800hr

24/May/2019

24/May/2019 1500hr to 1800hr

30/May/2019

30/May/2019 1500hr to 1800hr