Appendix C Environmental
Monitoring Schedule
Table C.1 Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma Extension
Construction (December 2019 to March
2020)
24hr TSP Monitoring |
1hr TSP Monitoring |
2/December/2019 |
2/
December /2019 1500hr to 1800hr |
8/
December /2019 |
8/
December /2019 1500hr to 1800hr |
14/
December /2019 |
14/
December /2019 1500hr to 1800hr |
20/
December /2019 |
20/
December /2019 1500hr to 1800hr |
26/
December /2019 |
26/
December /2019 1500hr to 1800hr |
1/January/2020 |
1/January/2020
1500hr to 1800hr |
7/January/2020 |
7/January/2020
1500hr to 1800hr |
13/January/2020 |
13/January/2020
1500hr to 1800hr |
19/January/2020 |
19/January/2020
1500hr to 1800hr |
25/January/2020 |
25/January/2020
1500hr to 1800hr |
31/January/2020 |
31/January/2020
1500hr to 1800hr |
6/February/2020 |
6/February/2020
1500hr to 1800hr |
12/February/2020 |
12/February/2020
1500hr to 1800hr |
18/
February/2020 |
18/February/2020
1500hr to 1800hr |
24/February/2020 |
24/February/2020
1500hr to 1800hr |
1/March/2020 |
1/March/2020
1500hr to 1800hr |
7/March/2020 |
7/
March/2020 1500hr to 1800hr |
13/March/2020 |
13/
March/2020 1500hr to 1800hr |
19/
March/2020 |
19/
March/2020 1500hr to 1800hr |
25/March/2020 |
25/
March/2020 1500hr to 1800hr |