Appendix C   Environmental Monitoring Schedule

 

 

Table C.1         Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma Extension Construction (January 2020 to April 2020)

 

24hr TSP Monitoring

1hr TSP Monitoring

1/January/2020

1/January/2020 1500hr to 1800hr

7/January/2020

7/January/2020 1500hr to 1800hr

13/January/2020

13/January/2020 1500hr to 1800hr

19/January/2020

19/January/2020 1500hr to 1800hr

25/January/2020

25/January/2020 1500hr to 1800hr

31/January/2020

31/January/2020 1500hr to 1800hr

6/February/2020

6/February/2020 1500hr to 1800hr

12/February/2020

12/February/2020 1500hr to 1800hr

18/ February/2020

18/February/2020 1500hr to 1800hr

24/February/2020

24/February/2020 1500hr to 1800hr

1/March/2020

1/March/2020 1500hr to 1800hr

7/March/2020

7/March/2020 1500hr to 1800hr

13/March/2020

13/March/2020 1500hr to 1800hr

19/ March/2020

19/March/2020 1500hr to 1800hr

25/March/2020

25/March/2020 1500hr to 1800hr

31/March/2020

31/March/2020 1500hr to 1800hr

6/April/2020

6/April/2020 1500hr to 1800hr

12/April/2020

12/April/2020 1500hr to 1800hr

18/April/2020

18/April/2020 1500hr to 1800hr

24/April/2020

24/April/2020 1500hr to 1800hr

30/April/2020

30/April/2020 1500hr to 1800hr