Appendix C   Environmental Monitoring Schedule

 

 

Table C.1         Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma Extension Construction (May 2020 to August 2020)

 

24hr TSP Monitoring

1hr TSP Monitoring

6/May/2020

6/May/2020 1500hr to 1800hr

12/May/2020

12/May/2020 1500hr to 1800hr

18/May/2020

18/May/2020 1500hr to 1800hr

24/May/2020

24/May/2020 1500hr to 1800hr

30/May/2020

30/May/2020 1500hr to 1800hr

5/June/2020

5/June/2020 1500hr to 1800hr

11/June/2020

11/June/2020 1500hr to 1800hr

17/June/2020

17/June/2020 1500hr to 1800hr

23/June/2020

23/June/2020 1500hr to 1800hr

29/June/2020

29/June/2020 1500hr to 1800hr

5/July/2020

5/July/2020 1500hr to 1800hr

11/July/2020

11/June/2020 1500hr to 1800hr

17/July/2020

17/July/2020 1500hr to 1800hr

23/July/2020

23/July/2020 1500hr to 1800hr

29/July/2020

29/July/2020 1500hr to 1800hr

4/August/2020

4/August/2020 1500hr to 1800hr

10/August/2020

10/August/2020 1500hr to 1800hr

16/August/2020

16/August/2020 1500hr to 1800hr

22/August/2020

22/August/2020 1500hr to 1800hr

28/August/2020

28/August/2020 1500hr to 1800hr