Appendix C   Environmental Monitoring Schedule

 

 

 

Table C.1        Monitoring schedule for 24hr and 1hr TSP monitoring for Lamma

Extension Construction (November 2021 to February 2022)

 

24hr TSP Monitoring

1hr TSP Monitoring

2/November/2021

2/November/2021 1500hr to 1800hr

8/November/2021

8/November/2021 1500hr to 1800hr

14/November/2021

14/November/2021 1500hr to 1800hr

20/November/2021

20/November/2021 1500hr to 1800hr

26/November/2021

26/November/2021 1500hr to 1800hr

2/December/2021

2/December/2021 1500hr to 1800hr

8/December/2021

8/December/2021 1500hr to 1800hr

14/December/2021

14/December/2021 1500hr to 1800hr

20/December/2021

20/December/2021 1500hr to 1800hr

26/December/2021

26/December/2021 1500hr to 1800hr

1/January/2022

1/January/2022 1500hr to 1800hr

7/January/2022

7/January/2022 1500hr to 1800hr

13/January/2022

13/January/2022 1500hr to 1800hr

19/January/2022

19/January/2022 1500hr to 1800hr

25/January/2022

25/January/2022 1500hr to 1800hr

31/January/2022

31/January/2022 1500hr to 1800hr

6/February/2022

6/February/2022 1500hr to 1800hr

12/February/2022

12/February/2022 1500hr to 1800hr

18/February/2022

18/February/2022 1500hr to 1800hr

24/February/2022

24/February/2022 1500hr to 1800hr