Appendix C Environmental Monitoring Schedule
Table C.1 Monitoring
schedule for 24hr and 1hr TSP monitoring
for Lamma
Extension Construction
(May 2022 to August 2022)
24hr TSP Monitoring |
1hr TSP Monitoring |
1/May/2022 |
1/May/2022 1500hr to 1800hr |
7/May/2022 |
7/May/2022 1500hr to 1800hr |
13/May/2022 |
13/May/2022 1500hr to 1800hr |
19/May/2022 |
19/May/2022 1500hr to 1800hr |
25/May/2022 |
25/May/2022 1500hr to 1800hr |
31/May/2022 |
31/May/2022 1500hr to 1800hr |
6/June/2022 |
6/June/2022 1500hr to 1800hr |
12/June/2022 |
12/June/2022 1500hr to 1800hr |
18/June/2022 |
18/June/2022 1500hr to 1800hr |
24/June/2022 |
24/June/2022 1500hr to 1800hr |
30/June/2022 |
30/June/2022 1500hr to 1800hr |
6/July/2022 |
6/July/2022 1500hr to 1800hr |
12/July/2022 |
12/July/2022 1500hr to 1800hr |
18/July/2022 |
18/July/2022 1500hr to 1800hr |
24/July/2022 |
24/July/2022 1500hr to 1800hr |
30/July/2022 |
30/July/2022 1500hr to 1800hr |
5/August/2022 |
5/August/2022 1500hr to 1800hr |
11/August/2022 |
11/August/2022 1500hr to 1800hr |
17/August/2022 |
17/August/2022 1500hr to 1800hr |
23/August/2022 |
23/August/2022 1500hr to 1800hr |
29/August/2022 |
29/August/2022 1500hr to 1800hr |