Appendix C Environmental Monitoring Schedule
Table C.1 Monitoring
schedule for 24hr and 1hr TSP monitoring
for Lamma
Extension Construction
(September 2022 to December 2022)
24hr TSP Monitoring |
1hr TSP Monitoring |
4/September/2022 |
4/September/2022 1500hr to 1800hr |
10/September/2022 |
10/September/2022 1500hr to 1800hr |
16/September/2022 |
16/September/2022 1500hr to 1800hr |
22/September/2022 |
22/September/2022 1500hr to 1800hr |
28/September/2022 |
28/September/2022 1500hr to 1800hr |
4/October/2022 |
4/October/2022 1500hr to 1800hr |
10/October/2022 |
10/October/2022 1500hr to 1800hr |
16/October/2022 |
16/October/2022 1500hr to 1800hr |
22/October/2022 |
22/October/2022 1500hr to 1800hr |
28/October/2022 |
28/October/2022 1500hr to 1800hr |
3/November/2022 |
3/November/2022 1500hr to 1800hr |
9/November/2022 |
9/November/2022 1500hr to 1800hr |
15/November/2022 |
15/November/2022 1500hr to 1800hr |
21/November/2022 |
21/November/2022 1500hr to 1800hr |
27/November/2022 |
27/November/2022 1500hr to 1800hr |
3/December/2022 |
3/December/2022 1500hr to 1800hr |
9/December/2022 |
9/December/2022 1500hr to 1800hr |
15/December/2022 |
15/December/2022 1500hr to 1800hr |
21/December/2022 |
21/December/2022 1500hr to 1800hr |
27/December/2022 |
27/December/2022 1500hr to 1800hr |