Appendix C Environmental Monitoring Schedule
Table C.1 Monitoring
schedule for 24hr and 1hr TSP monitoring
for Lamma
Extension Construction
(November 2022 to February 2023)
24hr TSP Monitoring |
1hr TSP Monitoring |
3/November/2022 |
3/November/2022 1500hr to 1800hr |
9/November/2022 |
9/November/2022 1500hr to 1800hr |
15/November/2022 |
15/November/2022 1500hr to 1800hr |
21/November/2022 |
21/November/2022 1500hr to 1800hr |
27/November/2022 |
27/November/2022 1500hr to 1800hr |
3/December/2022 |
3/December/2022 1500hr to 1800hr |
9/December/2022 |
9/December/2022 1500hr to 1800hr |
15/December/2022 |
15/December/2022 1500hr to 1800hr |
21/December/2022 |
21/December/2022 1500hr to 1800hr |
27/December/2022 |
27/December/2022 1500hr to 1800hr |
2/January/2023 |
2/January/2023 1500hr to 1800hr |
8/January/2023 |
8/January/2023 1500hr to 1800hr |
14/January/2023 |
14/January/2023 1500hr to 1800hr |
20/January/2023 |
20/January/2023 1500hr to 1800hr |
26/January/2023 |
26/January/2023 1500hr to 1800hr |
1/February/2023 |
1/February/2023 1500hr to 1800hr |
7/February/2023 |
7/February/2023 1500hr to 1800hr |
13/February/2023 |
13/February/2023 1500hr to 1800hr |
19/February/2023 |
19/February/2023 1500hr to 1800hr |
25/February/2023 |
25/February/2023 1500hr to 1800hr |