Appendix C Environmental Monitoring Schedule
Table C.1 Monitoring
schedule for 24hr and 1hr TSP monitoring
for Lamma
Extension Construction
(June 2023 to September 2023)
|
24hr TSP Monitoring |
1hr TSP Monitoring |
|
1/June/2023 |
1/June/2023 1500hr to 1800hr |
|
7/June/2023 |
7/June/2023 1500hr to 1800hr |
|
13/June/2023 |
13/June/2023 1500hr to 1800hr |
|
19/June/2023 |
19/June/2023 1500hr to 1800hr |
|
25/June/2023 |
25/June/2023 1500hr to 1800hr |
|
1/July/2023 |
1/July/2023 1500hr to 1800hr |
|
7/July/2023 |
7/July/2023 1500hr to 1800hr |
|
13/July/2023 |
13/July/2023 1500hr to 1800hr |
|
19/July/2023 |
19/July/2023 1500hr to 1800hr |
|
25/July/2023 |
25/July/2023 1500hr to 1800hr |
|
31/July/2023 |
31/July/2023 1500hr to 1800hr |
|
6/August/2023 |
6/August/2023 1500hr to 1800hr |
|
12/August/2023 |
12/August/2023 1500hr to 1800hr |
|
18/August/2023 |
18/August/2023 1500hr to 1800hr |
|
24/August/2023 |
24/August/2023 1500hr to 1800hr |
|
30/August/2023 |
30/August/2023 1500hr to 1800hr |
|
5/September/2023 |
5/September/2023 1500hr to 1800hr |
|
11/September/2023 |
11/September/2023 1500hr to 1800hr |
|
17/September/2023 |
17/September/2023 1500hr to 1800hr |
|
23/September/2023 |
23/September/2023 1500hr to 1800hr |
|
29/September/2023 |
29/September/2023 1500hr to 1800hr |