Table
of Content
1.2 Summary of EM&A Requirements
2.2 Summary of Results and Observations
2.3 Implementation Status of Monitoring of Ammonia
3.2 Summary of Results and Observations
4.2 Summary of Results and Observations
4.3 Implementation Status on Thermal
Plume and Residual Chlorine Surveys
5.1 Review of Environmental Monitoring Procedures
5.2 Assessment of Environmental Monitoring
Results
5.3 Status of Environmental Licensing and Permitting
5.4 Implementation Status of Environmental Mitigation Measures
5.5 Implementation Status of Event/Action Plans
5.6 Implementation Status of Environmental Complaint Handling Procedures
6.1 Outage Plan for the coming 3 months
6.2 Key issues for the coming month
List
of Tables
Table 2.1 Air
Quality Monitoring Parameter and Frequency
Table 3.1 Noise Monitoring Parameter and Frequency
Table 4.1 Water
Quality Monitoring Parameters and Frequencies
Table 5.1 Summary of Action/Limit Level Exceedances on Monitoring Parameters
Table 5.2 Summary of Environmental Licensing and Permit Status
Table 5.3 Environmental Complaints Received in August 2024
Table 5.4 Outstanding Environmental Complaints Carried Over
List
of figure
Figure 3.1 Location of
Noise Monitoring Station
AppendiX
Appendix B Action and Limit Levels for Air Quality,
Noise and Water Quality Monitoring
Appendix C Air Quality Monitoring Results
Appendix D Noise Monitoring Results
Appendix E Summary
Results and Observations on Water Quality Monitoring
This is the 215th monthly
Environmental Monitoring and Audit (EM&A) report for the Project “Operation
of Lamma Power Station Extension” prepared by the
Environmental Team (ET). This report presents the results of impact monitoring on air quality,
noise, water quality and environmental audit for
the operation of the said Project in August 2024.
Air
quality, noise and
water quality monitoring were performed. The results were checked
against
the established Action/Limit (AL) levels. The implementation status of the environmental mitigation measures, Event/Action Plan and environmental complaint handling
procedures were also checked.
Plant
Availability
Units L10, L11 and L12 were fully
available in the reporting month. Unit L9 was out of service during the
following period.
Unit |
Period |
Remark |
L9 |
09/08/2024 23:35 to 12/08/2024 06:09 |
Routine maintenance |
L9 |
17/08/2024 23:46 to 19/08/2024 05:45 |
HRSG flue gas leak
rectification |
Environmental
Monitoring Works
Environmental monitoring works, as mentioned in
the EM&A Manual (Operational phase),
were performed during the operation of Lamma
Power Station Extension in the reporting
period.
Air Quality
No
exceedance of Action and Limit levels for stack NOx was recorded in
the reporting month.
Noise
No exceedance of Action and Limit
levels for
noise was recorded in the reporting month.
Water Quality
No exceedance of Action and Limit
levels for
water
quality was recorded in the reporting month.
Environmental Licensing and
Permitting
Description |
Permit
/
Licence No. |
Valid Period |
Issued
To |
Date of Issuance |
|
From |
To |
||||
Environmental Permit |
EP-071/2000/D |
28/09/2020 |
- |
HK Electric |
28/09/2020 |
Specified Processes Licence issued under APCO |
L-7-002(14) |
04/07/2023 |
31/12/2024 |
HK Electric |
04/07/2023 |
WPCO Discharge Licence for L1-L12 |
WT10001965-2023 |
23/01/2024 |
30/11/2025 |
HK
Electric |
23/01/2024 |
Implementation
Status of Environmental Mitigation Measures
Environmental mitigation measures were implemented in the reporting
month.
Environmental
Complaints
No complaint in relation to the environmental impact of the
Project was
received in the reporting month.
Future Key Issues
Key
issues to be considered in the coming month include:
Air
Impact
·
To continuously
monitor the stack NOx for Lamma
Power Station Extension.
Noise
Impact
·
To continuously
monitor the noise for Lamma Power Station Extension.
Water
Impact
·
To continuously
carry out the water quality monitoring for Lamma
Power Station Extension.
Concluding
Remarks
The environmental performance of the Project was generally satisfactory.
The operational phase Lamma
Power Station Extension commenced in mid October 2006 following the completion
of erection works and commissioning tests for Unit L9. The Environmental Team (hereinafter called
the “ET”) was formed within The Hongkong Electric Co., Ltd. (HK Electric) to undertake Environmental Monitoring and
Audit for “Operation of Lamma Power Station
Extension” (hereinafter called the “Project”).
Under the requirements of Section 6 of Environmental Permit EP-071/2000/D,
an EM&A programme for impact environmental monitoring set out in the
EM&A Manual (Operational Phase) is required to be implemented. In accordance with the EM&A Manual,
environmental monitoring of air quality, noise and water quality are required
for the Project.
This
report summarizes the environmental monitoring and audit work for the Project
for the month of August 2024.
Units
L10, L11 and L12 were fully available in the reporting month. Unit L9 was out
of service during the following period.
Unit |
Period |
Remark |
L9 |
09/08/2024 23:35 to
12/08/2024 06:09 |
Routine maintenance |
L9 |
17/08/2024 23:46 to
19/08/2024 05:45 |
HRSG flue gas leak
rectification |
1.2
Summary of
EM&A Requirements
The EM&A program
requires environmental monitoring for air quality, noise and water quality. The EM&A monitoring work for air
quality, noise and water quality are
described in Sections 2,
3 and 4 respectively.
The
following environmental audits are summarized in Section 5 of
the report:
·
Environmental monitoring results;
·
The implementation status of environmental protection and pollution
control / mitigation measures.
The future key issues for
the Project will be reported in Section 6 of this report.
In
accordance with the EM&A Manual (Operational Phase) for Lamma
Extension, stack NOx is continuously monitored. Stack NOx monitoring data would
be checked against the Action/Limit Levels stated
in the EM&A Manual. The monitoring frequency is shown in Table
2.1 below:
Table 2.1 Air Quality Monitoring Parameter and Frequency
Parameter |
Frequency |
Hourly Average Stack NOx |
Continuous |
2.2
Summary of Results and Observations
Monitoring of stack NOx was conducted during the operation of Units L9,
L10, L11 and L12 in the reporting month.
A monthly summary of monitoring data is shown in Appendix
C.
No Action/Limit Level exceedance on
stack NOx was recorded in the reporting month.
2.3
Implementation Status of Monitoring of Ammonia
Monitoring of ammonia for
the use of Selective Catalytic Reduction System for NOx control was conducted
pursuant to the requirement of Specified Process (SP) licence
under the Air Pollution Control Ordinance.
No non-compliance of SP licence requirement on
stack NH3 emission was recorded in the reporting month. The relevant data would be submitted to EPD
under a separate submission for the SP licence. To
avoid duplication of effort, the monitoring and reporting requirements for
ammonia under the SP licence will not be included in
this EM&A programme.
In accordance with the EM&A Manual for Lamma Extension (Operational Phase), continuous noise monitoring
at Ash Lagoon is carried out to calculate
the noise arising from the operation of Lamma
Extension at the critical NSR at Hung Shing Ye. Baseline noise levels are applied for
correction to the noise monitoring data.
The data after corrections would
be checked
against the Limit Levels specified in the
EM&A Manual.
The noise monitoring
location is shown in Figure 3.1. The monitoring parameter and frequency are
shown in Table 3.1 below:
Table
3.1 Noise Monitoring Parameter
and Frequency
Parameter |
Frequency |
Time
Period |
30-min LAeq |
continuous |
0700 - 2300 hrs and 2300 - 0700 hrs of next day |
With the endorsement of
the Independent Environmental Checker, the enhancement of calibration of sound
level meter at the noise monitoring station was implemented. The monthly manual on-site calibration using
sound level calibrator was replaced by the daily auto charge injection
calibration function of the sound level meter.
For additional quality assurance, manual on-site calibration is still conducted
for the noise monitoring station once every 6 months. The manual on-site calibration was carried
out in August 2024 and the next calibration was scheduled in February 2025. The verification of the sound level
meter/calibrator by the manufacturer or an accredited laboratory biennially /
annually remains unchanged.
3.2
Summary of Results and Observations
Continuous
noise monitoring was conducted at the monitoring station at Ash Lagoon. The monitoring results are shown in Appendix D.
No Action/Limit Level exceedance on noise was recorded in the
reporting month.
Figure
3.1 Location of Noise Monitoring Station
In accordance with the EM&A Manual for Lamma Extension (Operational Phase), the monitoring
requirements for the EM&A work should strictly follow the discharge licence
for L1-L12 issued under the Water Pollution Control Ordinance (WPCO).
The parameters as
stated in Table 4.1 were monitored and checked against the
Action/Limit Levels as given in Appendix B.
Table 4.1 Water Quality Monitoring Parameters and Frequencies
Item |
Parameters |
Frequencies |
1 |
Cooling Water Temperature
Rise |
Daily |
2 |
Total Residual
Chlorine |
Bi-weekly |
3 |
Temperature of Blowdown Effluent |
At least twice per year |
4 |
Suspended Solids from Blowdown Effluent |
At least twice
per year |
5 |
Grease & Oil from Blowdown Effluent |
At least twice
per year |
6 |
Scum of foam in
ambient water |
Daily |
4.2
Summary of Results and Observations
Monitoring of various parameters as listed in Table 4.1 above was
carried out during the operation of Units L9, L10, L11 and L12 in the reporting
month. A monthly summary
of the data is shown in Appendix E.
The data recorded for the
monitoring parameters were all below their corresponding Action/Limit Levels. No Action/Limit level exceedance was recorded
in the reporting month. There was no
foam present within 500 meters of Hung Sing Ye Beach in the reporting
month. Details of the foam observation report are also given in Appendix E. The effluent quality was generally
satisfactory.
4.3
Implementation Status on Thermal Plume and
Residual Chlorine Surveys
One
survey for thermal plume and residual chlorine concentration at the seawater
around the discharges from the Lamma Power Station
and Lamma Power Station Extension shall be carried
out after the commissioning of each of the generating units for the Project in
dry and wet seasons.
The
surveys for Units L9, L10 and L11 were completed in July 2007, August 2021 and
January 2023 respectively. The survey
for Unit L12 was scheduled tentatively in the coming winter and next summer for
dry and wet seasons respectively.
5.1
Review of
Environmental Monitoring Procedures
The environmental monitoring procedures were regularly reviewed by the Environmental Team. No modification to the existing monitoring
procedures was recommended.
5.2
Assessment of
Environmental Monitoring Results
Monitoring results for Air
Quality, Noise and Water Quality
The environmental
monitoring results for air quality, noise and water quality in August 2024 presented
in Sections 2, 3 and 4 respectively are summarized in Table 5.1.
Table 5.1 Summary of Action/Limit Level Exceedances on Monitoring Parameters
Item |
Parameter Monitored |
Monitoring Period |
No. of Exceedances In |
Event/Action Plan Implementation Status and
Results |
|
Action Level |
Limit Level |
||||
Air |
|||||
1 |
Stack NOx |
01/08/2024 31/08/2024 |
0 |
0 |
|
Noise |
|||||
1 |
Noise levels at the critical NSR at Hung Shing Ye calculated by the noise alarm monitoring system |
01/08/2024 31/08/2024 |
0 |
0 |
|
Water |
|||||
1 |
Cooling Water Temperature Rise |
01/08/2024 31/08/2024 |
0 |
0 |
|
2 |
Total Residual Chlorine |
01/08/2024 31/08/2024 |
0 |
0 |
|
3 |
Temperature of Blowdown Effluent |
01/08/2024 31/08/2024 |
N.A. |
N.A.* |
|
4 |
Suspended Solids from Blowdown Effluent |
01/08/2024 31/08/2024 |
N.A. |
N.A.* |
|
5 |
Grease & Oil from Blowdown Effluent |
01/08/2024 31/08/2024 |
N.A. |
N.A.* |
|
6 |
Inspection of Scum/Foam in ambient water |
01/08/2024 31/08/2024 |
0 |
0 |
|
Note: * Monitoring was not scheduled in the reporting month
Land Contamination
There was no land contamination incident happened in the reporting
month.
Waste Management
Waste management practice was properly implemented for operation of the Project
as outlined in the Waste Management Plan for Lamma
Power Station Extension. There was no unacceptable environmental impact on
waste management in the reporting month.
5.3 Status of Environmental Licensing and Permitting
All
permits/licenses obtained as of August 2024
are summarised in Table
5.2.
Table 5.2 Summary of
Environmental Licensing and Permit Status
Description |
Permit / Licence
No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit |
EP-071/2000/D |
28/09/2020 |
- |
Valid |
Specified Processes Licence issued under APCO* |
L-7-002(14) |
04/07/2023 |
31/12/2024 |
Valid |
WPCO Discharge Licence for L1-L12# |
WT10001965-2023 |
23/01/2024 |
30/11/2025 |
Valid |
Notes:
* - The SP licence varied for L12 operation was
granted on 4/7/2023.
# - The WPCO discharge licence
varied for L12 operation was granted on 22/5/2023 and was renewed on 23/1/2024.
5.4
Implementation
Status of Environmental Mitigation Measures
Mitigation measures detailed in
the permits and
the EM&A Manual (Operational Phase) are
required to be implemented. An updated
summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix F.
5.5
Implementation
Status of Event/Action Plans
The Event/Action Plans
for air quality, noise and water quality extracted from the EM&A Manual
(Operational Phase) are presented in Appendix A.
5.6
Implementation
Status of Environmental Complaint Handling Procedures
In August 2024, no
complaint in relation to the environmental impact of the Project was received.
Table 5.3 Environmental Complaints Received in August 2024
Case Reference / Date, Time Received / Date, Time Concerned |
Descriptions / Actions Taken |
Conclusion / Status |
Nil |
N/A |
N/A |
Table 5.4 Outstanding Environmental Complaints Carried Over
Case Reference / Date, Time Received / Date, Time Concerned |
Descriptions / Actions Taken |
Conclusion / Status |
Nil |
N/A |
N/A |
6.1
Outage Plan for the coming 3 months
No major outage plan in the coming three months.
6.2
Key issues for
the coming month
Key issues to be considered in
the coming month include:
Air Impact
·
To continuously
monitor the stack NOx for Lamma
Power Station Extension.
Noise Impact
·
To continuously
monitor the noise for Lamma Power Station Extension.
Water Impact
·
To continuously
carry out the water quality monitoring for Lamma
Power Station Extension.
Environmental monitoring
was performed as required in the reporting month. All
monitoring results were checked and reviewed.
No Action/Limit level exceedance on
stack NOx was recorded in the reporting
month
No Action/Limit level
exceedance on noise was recorded in the reporting month.
No Action/Limit level exceedance on water
quality parameters was recorded in the reporting month.
Environmental mitigation measures recommended in the EM&A Manual
for the operational activities were implemented in the reporting month. No complaint in
relation to the environmental impact of the Project was received in the reporting
month. No
prosecution was received for this Project
in the reporting period.
The environmental performance of the Project was generally satisfactory.
Table
A.1 Event/Action Plan for Air Quality
Exceedance |
ET
Leader |
IEC |
Operations Engineer |
Action
Level |
|||
Exceedance of one sample |
Identify source; Inform IEC verbally; Repeat measurement to
confirm finding. |
Check monitoring data
submitted by ET Leader and advise ET Leader for any finding. |
Rectify any unacceptable
practice; Amend any working methods if
appropriate. |
|
|
|
|
Exceedance of two or more
consecutive samples |
Identify source; Inform IEC verbally; Repeat measurement to
confirm finding; Increase monitoring
frequency; Discuss with Operations
Engineers
on remedial
actions required; If exceedance stops,
discontinue additional monitoring. |
Check monitoring data
submitted by ET Leader and advise ET Leader for any finding; Verify the implementation
of the remedial measures; |
Discuss with ET Leader
on remedial
actions required; Implement the agreed remedial
actions. |
Limit level |
|||
Exceedance of one sample |
Repeat measurement to
confirm finding; Identify the source(s) of
the impact. Verbally inform IEC and EPD of the exceedance as soon as practicable; Discuss with Operations
Engineers
on remedial
actions required; Increase monitoring frequency; Assess the effectiveness of
the remedial actions and keep IEC and EPD informed of the results. |
Check monitoring data
submitted by ET Leader and advise ET Leader of any finding; Verify the implementation
of the remedial measures. |
Take immediate action to
avoid further exceedances; Discuss with ET Leader
on remedial
actions required; Implement the agreed remedial
actions. |
|
|
|
|
Exceedance of two or more
consecutive samples |
Identify source; Identify the source(s) of
the impact. Verbally inform IEC and EPD
of the exceedance as soon as practicable; Repeat measurement to
confirm finding; Increase monitoring
frequency; Carry out analysis on existing
control procedures
to determine possible mitigation to be implemented; Discuss with Operations
Engineers
on the
remedial actions to be taken; If exceedance stops,
discontinue additional monitoring. |
Provide feedback and
advise ET Leader/Operations Engineers on the effectiveness of the remedial actions proposed
by them; Verify the implementation
of the remedial measures. |
Take immediate action to
avoid further exceedance; Discuss with ET Leader
on remedial
actions required; Implement the agreed remedial
actions; Check
the suspected defective parts if the problem still does not come under
control. |
Table A.2 Event/Action Plan for Noise
Exceedance |
ET
Leader |
IEC |
Operations
Engineer |
Action Level |
If the complaint against Lamma
Extension operation is valid, identify the source(s) of the noise and
propose remedial measures if necessary; |
Verify the
implementation of the remedial measures. |
Discuss with ET
Leader on remedial actions required; Implement the agreed remedial actions. |
Limit Level |
Check monitoring data to confirm findings; Identify the
source(s) of the impact. If the exceedance is found to be valid and due to the Lamma Extension operation, verbally inform IEC
and EPD of the
exceedance as soon as practicable; Discuss
with Operations Engineers on remedial actions
required. |
Check monitoring data
submitted by ET Leader and advise ET Leader of any finding; Verify the
implementation of the remedial measures. |
Take action to
avoid further exceedance; Discuss with ET
Leader on the remedial actions required; Implement the agreed remedial actions. |
Table A.3 Event/Action Plan for Water Quality
Exceedance |
ET Leader |
IEC |
Operations Engineer |
Action Level |
|
||
Exceedance on one sampling
day |
Identify
source(s) of impact; Verbally inform
IEC. |
Check monitoring data submitted by ET Leader and advise ET Leader for
any findings. |
Rectify
unacceptable practice; Amend any working methods if appropriate. |
Exceedances on more than
one consecutive sampling day |
Identify
source(s) of impact; Verbally inform
IEC; Repeat in-situ
measurements to confirm findings; Discuss with Operations
Engineers
on remedial
actions required; Increase monitoring frequency; If exceedance stops, discontinue additional monitoring. |
Check
monitoring data submitted by ET Leader and advise ET Leader for any finding; Verify the
implementation of the remedial measures. |
Discuss with ET Leader on remedial actions required; Implement the
agreed remedial actions. |
Limit Level |
|
|
|
Exceedance on one
sampling day |
Identify the
source(s) of impact; Verbally inform
IEC and EPD of the exceedance, as soon as practicable; Repeat
measurement to confirm finding; Discuss with Operations
Engineers
on remedial
actions required; Increase
monitoring frequency; Assess the
effectiveness of the remedial actions and keep IEC and EPD informed of the
results. |
Check
monitoring data submitted by ET Leader and advise ET Leader for any finding; Verify the
implementation of the remedial measures. |
Take immediate
action to avoid further exceedance; Discuss with ET Leader on remedial actions required; Implement the
agreed remedial actions. |
Exceedances on more than one consecutive sampling day |
Identify the
source(s) of impact; Verbally inform
IEC and EPD of the exceedance as soon as practicable; Repeat
measurement to confirm finding; Discuss with Operations
Engineers
on remedial
actions required; Increase
monitoring frequency; Carry out
analysis on existing control procedures to
determine possible mitigation to be implemented; If exceedance
stops, discontinue additional monitoring. |
Provide
feedback and advise ET Leader/Operations
Engineers on the effectiveness of the remedial
actions proposed; Verify the
implementation of the remedial measures. |
Take immediate
action to avoid further exceedance; Discuss with ET Leader on remedial actions required; Implement the
agreed remedial actions; Check the suspected defective parts if the problem still does not come
under control. |
Appendix B Action
and Limit Levels for Air Quality, Noise and Water Quality Monitoring
B.1 Air
Unit L9 |
|||
Parameter |
Frequency |
Action |
Limit |
Hourly
Average Stack NOx
(Natural Gas) |
Continuous |
81
mg/Nm3 |
90
mg/Nm3 |
Hourly
Average Stack NOx
(Light Oil) |
Continuous |
135
mg/Nm3 |
150
mg/Nm3 |
Unit L10, Unit L11, Unit
L12 |
|||
Parameter |
Frequency |
Action |
Limit |
Hourly
Average Stack NOx
(Natural Gas) |
Continuous |
81
mg/Nm3 (Loading
≤ 182 MW) |
90
mg/Nm3 (Loading≤182
MW) |
13.5
mg/Nm3 (182MW
≤ Loading ≤ 266 MW) |
15
mg/Nm3 |
||
4.5
mg/Nm3 |
5
mg/Nm3 (Loading
≥ 266 MW) |
||
Hourly
Average Stack NOx
(Light Oil) |
Continuous |
135
mg/Nm3 |
150
mg/Nm3 |
Note: Expressed as
at 0ºC, 101.325kPa, dry and corrected to 15% O2 condition.
B.2. Noise
Parameter |
Frequency |
Action |
Limit |
Noise Levels at the critical NSR at Hung Shing
Ye
calculated by the noise
alarm monitoring system |
Continuous |
When more than one complaint is received
within two weeks, which are concerning the same event or location |
a. 60 dB(A) in LAeq,30 min (07:00-23:00 hrs) b. 50 dB(A) in LAeq,30 min (23:00-07:00 hrs
on next day) |
B.3 Water
Monitoring Area / Location |
Parameters to be Monitored |
Frequency |
Concentration Not to Be
Exceeded |
Action |
Limit |
Trade Effluent
Cooling Water |
Temperature |
Daily, when the combined cycle
unit is operating |
Temperature at outfall should not exceed that at intake by > 10°C |
9.5°C |
+10°C above intake |
Total Residual Chlorine |
Bi-weekly, when the combined cycle unit is
operating |
0.5mg/L |
0.47 mg/L |
0.5 mg/L |
|
Trade Effluent Boiler Blowdown |
Temperature |
At least twice per year, when
the combined cycle unit is operating |
40°C |
- |
40°C |
Suspended Solids |
At least twice per year, when
the combined cycle unit is operating |
30 mg/L |
- |
30 mg/L |
|
Grease & Oil |
At least twice per year, when
the combined cycle unit is operating |
20 mg/L |
- |
20 mg/L |
|
Marine waters cooling water
outfall |
Scum of foam in ambient water |
Daily, when
the combined cycle unit is operating |
No scum within 500 m
of Hung Shing Ye Beach |
When scum passes the station south-west corner and north-west corner |
No
scum within 500 m of Hung Shing Ye Beach |
Appendix
C Air Quality Monitoring Results
Site: Lamma Power Station – Unit L9
Month: August 2024
Monthly
Summary of Stack NOx
Date |
Daily Maximum
Stack NOx concentration (mg/Nm3)# |
1/8/2024 |
60 |
2/8/2024 |
63 |
3/8/2024 |
58 |
4/8/2024 |
58 |
5/8/2024 |
54 |
6/8/2024 |
57 |
7/8/2024 |
60 |
8/8/2024 |
69 |
9/8/2024 |
56 |
10/8/2024 |
* |
11/8/2024 |
* |
12/8/2024 |
56 |
13/8/2024 |
57 |
14/8/2024 |
57 |
15/8/2024 |
58 |
16/8/2024 |
61 |
17/8/2024 |
58 |
18/8/2024 |
* |
19/8/2024 |
60 |
20/8/2024 |
58 |
21/8/2024 |
59 |
22/8/2024 |
63 |
23/8/2024 |
61 |
24/8/2024 |
* |
25/8/2024 |
* |
26/8/2024 |
58 |
27/8/2024 |
58 |
28/8/2024 |
58 |
29/8/2024 |
62 |
30/8/2024 |
56 |
31/8/2024 |
62 |
Note: # - Hourly average value. Expressed as at 0ºC, 101.325kPa, dry and
corrected to 15% O2 condition.
* - Unit L9 was not on load.
Site: Lamma Power Station – Unit L10
Month: August 2024
Monthly
Summary of Stack NOx
Date |
Daily Maximum
Stack NOx concentration (mg/Nm3)# |
1/8/2024 |
3 |
2/8/2024 |
3 |
3/8/2024 |
3 |
4/8/2024 |
3 |
5/8/2024 |
3 |
6/8/2024 |
3 |
7/8/2024 |
3 |
8/8/2024 |
3 |
9/8/2024 |
3 |
10/8/2024 |
3 |
11/8/2024 |
4 |
12/8/2024 |
3 |
13/8/2024 |
3 |
14/8/2024 |
3 |
15/8/2024 |
3 |
16/8/2024 |
3 |
17/8/2024 |
3 |
18/8/2024 |
4 |
19/8/2024 |
4 |
20/8/2024 |
3 |
21/8/2024 |
4 |
22/8/2024 |
4 |
23/8/2024 |
3 |
24/8/2024 |
3 |
25/8/2024 |
3 |
26/8/2024 |
3 |
27/8/2024 |
3 |
28/8/2024 |
3 |
29/8/2024 |
3 |
30/8/2024 |
3 |
31/8/2024 |
3 |
The
daily maximum stack NOx concentration complies with the Action/Limit Level for
all unit loading ranges.
Note: # - Hourly average value. Expressed as at 0ºC, 101.325kPa, dry and
corrected to 15% O2 condition.
* - Unit L10 was
not on load.
^ - Unit L10 was
operating with loading less than 266 MW.
Site: Lamma Power Station – Unit L11
Month: August 2024
Monthly
Summary of Stack NOx
Date |
Daily Maximum
Stack NOx concentration (mg/Nm3)# |
1/8/2024 |
3 |
2/8/2024 |
4 |
3/8/2024 |
3 |
4/8/2024 |
3 |
5/8/2024 |
3 |
6/8/2024 |
3 |
7/8/2024 |
3 |
8/8/2024 |
3 |
9/8/2024 |
3 |
10/8/2024 |
3 |
11/8/2024 |
3 |
12/8/2024 |
3 |
13/8/2024 |
3 |
14/8/2024 |
3 |
15/8/2024 |
3 |
16/8/2024 |
3 |
17/8/2024 |
3 |
18/8/2024 |
3 |
19/8/2024 |
3 |
20/8/2024 |
3 |
21/8/2024 |
3 |
22/8/2024 |
3 |
23/8/2024 |
3 |
24/8/2024 |
3 |
25/8/2024 |
3 |
26/8/2024 |
3 |
27/8/2024 |
3 |
28/8/2024 |
3 |
29/8/2024 |
3 |
30/8/2024 |
3 |
31/8/2024 |
3 |
The
daily maximum stack NOx concentration complies with the Action/Limit Level for
all unit loading ranges.
Note: # - Hourly average value. Expressed as at 0ºC, 101.325kPa, dry and
corrected to 15% O2 condition.
* - Unit L11 was
not on load.
^ - Unit L11 was
operating with loading less than 266 MW.
Site: Lamma Power Station – Unit L12
Month: August 2024
Monthly
Summary of Stack NOx
Date |
Daily Maximum
Stack NOx concentration (mg/Nm3)# |
1/8/2024 |
4 |
2/8/2024 |
4 |
3/8/2024 |
4 |
4/8/2024 |
4 |
5/8/2024 |
4 |
6/8/2024 |
4 |
7/8/2024 |
4 |
8/8/2024 |
4 |
9/8/2024 |
4 |
10/8/2024 |
4 |
11/8/2024 |
3 |
12/8/2024 |
4 |
13/8/2024 |
4 |
14/8/2024 |
4 |
15/8/2024 |
4 |
16/8/2024 |
4 |
17/8/2024 |
4 |
18/8/2024 |
4 |
19/8/2024 |
4 |
20/8/2024 |
4 |
21/8/2024 |
4 |
22/8/2024 |
4 |
23/8/2024 |
4 |
24/8/2024 |
4 |
25/8/2024 |
4 |
26/8/2024 |
4 |
27/8/2024 |
4 |
28/8/2024 |
4 |
29/8/2024 |
3 |
30/8/2024 |
3 |
31/8/2024 |
4 |
The
daily maximum stack NOx concentration complies with the Action/Limit Level for
all unit loading ranges.
Note: # - Hourly average value. Expressed as at 0ºC, 101.325kPa, dry and
corrected to 15% O2 condition.
* - Unit L12 was
not on load.
^ - Unit L12 was
operating with loading less than 266 MW.
Appendix
D Noise Monitoring Results
Site: Lamma Power Station
Extension
Measurement
Location: Ash Lagoon
Measurement Parameter: 30-min Leq (07:00-23:00 hrs and 23:00-07:00 hrs on next day)
Time |
Calculated Noise Level at NSR at Hung Shing
Ye (dB(A)) |
Limit Noise Level (dB(A)) |
||
Max |
Avg |
|||
07:00-23:00 |
50 |
45 |
60 |
|
1/8/2024 |
23:00-07:00 |
45 |
42 |
50 |
2/8/2024 |
07:00-23:00 |
52 |
48 |
60 |
2/8/2024 |
23:00-07:00 |
38 |
38 |
50 |
3/8/2024 |
07:00-23:00 |
39 |
39 |
60 |
3/8/2024 |
23:00-07:00 |
44 |
42 |
50 |
4/8/2024 |
07:00-23:00 |
52 |
48 |
60 |
4/8/2024 |
23:00-07:00 |
47 |
45 |
50 |
5/8/2024 |
07:00-23:00 |
53 |
47 |
60 |
5/8/2024 |
23:00-07:00 |
49 |
46 |
50 |
6/8/2024 |
07:00-23:00 |
57 |
57 |
60 |
6/8/2024 |
23:00-07:00 |
44 |
43 |
50 |
7/8/2024 |
07:00-23:00 |
56 |
51 |
60 |
7/8/2024 |
23:00-07:00 |
49 |
47 |
50 |
8/8/2024 |
07:00-23:00 |
60 |
55 |
60 |
8/8/2024 |
23:00-07:00 |
49 |
44 |
50 |
9/8/2024 |
07:00-23:00 |
59 |
54 |
60 |
9/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
10/8/2024 |
07:00-23:00 |
57 |
53 |
60 |
10/8/2024 |
23:00-07:00 |
35 |
35 |
50 |
11/8/2024 |
07:00-23:00 |
43 |
40 |
60 |
11/8/2024 |
23:00-07:00 |
42 |
40 |
50 |
12/8/2024 |
07:00-23:00 |
44 |
44 |
60 |
12/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
13/8/2024 |
07:00-23:00 |
42 |
42 |
60 |
13/8/2024 |
23:00-07:00 |
47 |
45 |
50 |
14/8/2024 |
07:00-23:00 |
56 |
50 |
60 |
14/8/2024 |
23:00-07:00 |
44 |
43 |
50 |
15/8/2024 |
07:00-23:00 |
59 |
53 |
60 |
15/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
16/8/2024 |
07:00-23:00 |
59 |
54 |
60 |
16/8/2024 |
23:00-07:00 |
44 |
38 |
50 |
17/8/2024 |
07:00-23:00 |
57 |
52 |
60 |
17/8/2024 |
23:00-07:00 |
48 |
45 |
50 |
18/8/2024 |
07:00-23:00 |
52 |
46 |
60 |
18/8/2024 |
23:00-07:00 |
44 |
44 |
50 |
19/8/2024 |
07:00-23:00 |
59 |
53 |
60 |
19/8/2024 |
23:00-07:00 |
44 |
40 |
50 |
20/8/2024 |
07:00-23:00 |
57 |
53 |
60 |
20/8/2024 |
23:00-07:00 |
46 |
43 |
50 |
21/8/2024 |
07:00-23:00 |
53 |
49 |
60 |
21/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
22/8/2024 |
07:00-23:00 |
--- |
--- |
60 |
22/8/2024 |
23:00-07:00 |
46 |
45 |
50 |
23/8/2024 |
07:00-23:00 |
45 |
45 |
60 |
23/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
24/8/2024 |
07:00-23:00 |
--- |
--- |
60 |
24/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
25/8/2024 |
07:00-23:00 |
45 |
45 |
60 |
25/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
26/8/2024 |
07:00-23:00 |
--- |
--- |
60 |
26/8/2024 |
23:00-07:00 |
49 |
49 |
50 |
27/8/2024 |
07:00-23:00 |
--- |
--- |
60 |
27/8/2024 |
23:00-07:00 |
49 |
49 |
50 |
28/8/2024 |
07:00-23:00 |
--- |
--- |
60 |
28/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
29/8/2024 |
07:00-23:00 |
51 |
48 |
60 |
29/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
30/8/2024 |
07:00-23:00 |
51 |
47 |
60 |
30/8/2024 |
23:00-07:00 |
--- |
--- |
50 |
31/8/2024 |
07:00-23:00 |
29 |
29 |
60 |
31/8/2024 |
23:00-07:00 |
37 |
35 |
50 |
Note: 1. “---“represents the measured noise monitoring data lower than the
established notional background level/discarded
under strong wind/ bird sound.
2. Pursuant to the EM&A Manual (Operational
Phase), the corrections for accounting the differences of barrier attenuations
and atmospheric absorption attenuations for the noise monitoring station and
noise sensitive receiver are 5 dB(A) and 2 dB(A) respectively.
Appendix
E Summary Results and Observations on Water Quality Monitoring
Maximum Outlet Temperature Rise (Deg. Celsius) of
Cooling Water at C.W. Outfall No.3 Serving Units L9, L10 & L11
Weighted by Flowrates of Individual Streams (August 2024)
Date |
Maximum Outlet Temperature Rise (Deg. Celsius) |
1/8/2024 |
7.5 |
2/8/2024 |
7.2 |
3/8/2024 |
6.5 |
4/8/2024 |
6.1 |
5/8/2024 |
6.5 |
6/8/2024 |
6.5 |
7/8/2024 |
7.2 |
8/8/2024 |
6.4 |
9/8/2024 |
6.5 |
10/8/2024 |
6.4 |
11/8/2024 |
6.4 |
12/8/2024 |
6.4 |
13/8/2024 |
6.4 |
14/8/2024 |
6.4 |
15/8/2024 |
6.3 |
16/8/2024 |
7.0 |
17/8/2024 |
6.8 |
18/8/2024 |
6.3 |
19/8/2024 |
6.9 |
20/8/2024 |
6.9 |
21/8/2024 |
7.0 |
22/8/2024 |
7.1 |
23/8/2024 |
7.1 |
24/8/2024 |
6.6 |
25/8/2024 |
6.6 |
26/8/2024 |
6.6 |
27/8/2024 |
6.6 |
28/8/2024 |
6.6 |
29/8/2024 |
6.5 |
30/8/2024 |
6.4 |
31/8/2024 |
7.2 |
Maximum Outlet Temperature Rise (Deg. Celsius) of
Cooling Water at C.W. Outfall No.4 Serving Unit L12
Weighted by Flowrates of Individual Streams (August 2024)
Date |
Maximum Outlet Temperature Rise (Deg. Celsius) |
1/8/2024 |
6.6 |
2/8/2024 |
6.0 |
3/8/2024 |
6.5 |
4/8/2024 |
5.0 |
5/8/2024 |
6.3 |
6/8/2024 |
6.1 |
7/8/2024 |
6.4 |
8/8/2024 |
5.8 |
9/8/2024 |
5.7 |
10/8/2024 |
6.1 |
11/8/2024 |
6.0 |
12/8/2024 |
6.3 |
13/8/2024 |
6.5 |
14/8/2024 |
6.3 |
15/8/2024 |
6.4 |
16/8/2024 |
6.6 |
17/8/2024 |
6.7 |
18/8/2024 |
6.7 |
19/8/2024 |
6.6 |
20/8/2024 |
6.6 |
21/8/2024 |
6.2 |
22/8/2024 |
6.7 |
23/8/2024 |
6.7 |
24/8/2024 |
6.6 |
25/8/2024 |
5.1 |
26/8/2024 |
6.5 |
27/8/2024 |
6.4 |
28/8/2024 |
6.3 |
29/8/2024 |
6.2 |
30/8/2024 |
6.5 |
31/8/2024 |
6.5 |
Total
Residual Chlorine Level at C.W. Outfall No. 3 (August 2024)
Date of sampling |
02/08 |
15/08 |
30/08 |
Total Residual Chlorine, mg/L |
0.20 |
0.20 |
0.40 |
Total
Residual Chlorine Level at C.W. Outfall No. 4 (August 2024)
Date of sampling |
02/08 |
15/08 |
30/08 |
Total Residual Chlorine, mg/L |
0.10 |
0.20 |
0.30 |
Blowdown from Units L9, L10 and L11 Steam Turbine and HRSG to C.W.
Outfall No. 3 (August 2024)
Source of discharge |
Unit
L9 HSRG |
Unit
L9 Steam
Turbine |
Unit
L10 HSRG |
Unit
L10 Steam
Turbine |
Unit
L11 HSRG |
Unit
L11 Steam
Turbine |
Date of sampling |
# |
# |
# |
# |
# |
# |
Suspended Solid, mg/L |
# |
# |
# |
# |
# |
# |
Grease & Oil, mg/L |
# |
# |
# |
# |
# |
# |
Temperature, Deg. Celsius |
# |
# |
# |
# |
# |
# |
Note: #
Monitoring was not scheduled in the reporting month. The last monitoring was
carried out in May 2024.
Blowdown from Unit L2 Steam Turbine and HRSG to C.W. Outfall No. 4 (August
2024)
Source of discharge |
Unit
L12 HSRG |
Unit
L12 Steam
Turbine |
Date of sampling |
# |
# |
Suspended Solid, mg/L |
# |
# |
Grease & Oil, mg/L |
# |
# |
Temperature, Deg. Celsius |
# |
# |
Note: #
Monitoring was not scheduled in the reporting month. The last monitoring was
carried out in June 2024.
Observation of Scum Formation in Marine Waters Mixing Zone at Lamma Power Station Extension (August 2024)
Date |
Observation |
1/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.1 |
2/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.2 |
3/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.2 |
4/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.2 |
5/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
6/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
dispersed by ferry |
7/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
8/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
reduced chlorination output and defoamer added to Outfall No.1 & 2 |
9/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.1 & No.2 |
10/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
11/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
12/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.2 |
13/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.2 |
14/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.2 |
15/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.2 |
16/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and defoamer
added to Outfall No.2 |
17/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall and
defoamer added to Outfall No.2 |
18/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
19/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
20/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
21/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
22/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
23/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
24/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
25/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station & CW Outfall |
26/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
27/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
28/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
29/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.1 & No.2 |
30/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall,
dispersed by ferry and defoamer added to Outfall No.2 |
31/8/2024 |
No scum within 500m of HSY
Beach & NW/SW corner of the Station; Some foam outside CW Outfall, dispersed
by ferry and defoamer added to Outfall No.1 |
Note: The
water spraying system at C.W. Outfall No.1 was put in service in the reporting
month.
EM&A Log Ref. |
Mitigation Measures |
Implementation Status |
|
Air Quality |
|
A1 |
Implement the gas-fired units as base-load units. For the existing power station, the more efficient units incorporating FGD and low NOx systems shall be operated first under normal situation to meet system demand. In case of any deviations from this, EPD shall be notified of the details and circumstances for the deviation. |
Complied |
A2 |
HK Electric shall undertake annual revisions and update of its
GHG emissions inventory, which covers all HK Electric existing facilities and new extension, for at least the six GHGs
specified under the Kyoto Protocol (CO2, CH4, N2O, HFCs, PFCs and SF6). The inventory shall be established and
maintained in accordance with the latest IPCC Guidelines or any other
guidelines issued by Government, with details documented for regular reviews
and updates. The inventory shall be reported on an annual basis, including
actual figures and targets for the previous and current years, as well as the
next year's forecast. Discrepancies
for actual versus target figures and actions for improvement or enhancement
shall be discussed. HK Electric shall update the inventory according to the figures
of the electricity load forecast, upon every subsequent review by the
Government. This shall also be
reported in the annual report. (The annual report of GHG emissions inventory shall be deposited with the Director of Environmental Protection within three months after the end of the reporting period.) |
Complied |
|
|
|
|
Water Quality |
|
B1 |
No
further mitigation measures were found to be necessary provided the discharge
of cooling water and residual chlorine are kept below the rates assumed in
the water quality assessment*. *All discharges of effluent/wastewater shall be controlled through licensing under the Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems. Inland and Coastal Waters, issued under Section 21 of the Water Pollution Control Ordinance. |
Complied |
|
|
|
|
Noise |
|
C1 |
HK Electric shall implement the gas-fired units for based-load operation to minimize the noise generated from the existing units. |
Complied |
|
|
|
|
Landscape & Visual impacts |
|
D1 |
No mitigation measures were considered necessary. |
N/A |
|
|
|
EM&A Log Ref. |
Mitigation Measures |
Implementation Status |
|
LAND CONTAMINATION AND WASTE MANAGEMENT |
|
E1 |
HK Electric shall
maintain records of the following items: - integrity testing of light oil tanks; - daily inspection of the light oil tanks and bunded areas; - quantities of oily waste and sludge generated from oil
interceptors and chemical waste generated from operation of the power
station; - deposal oil oily waste/sludge and chemical waste to licenced site; - quantities of chemical and chemical waste; - incident of spillage and remediation actions; and - emergency response training and drills. |
Complied |
|
Marine Ecology |
|
F1 |
No mitigation measures were considered necessary. |
N/A |
|
|
|
|
fisheries |
|
G1 |
No mitigation measures were considered necessary. |
N/A |
|
|
|
|
RISK ASSESSMENT |
|
H1 |
No mitigation measures were considered necessary. |
N/A |