cover

 

Table of Content

 

EXECUTIVE SUMMARY

 

1.             INTRODUCTION.. 1

1.1       Background  1

1.2       Project Organisation  2

1.3       Plant Availability during the Reporting Period  2

1.4       Malfunction/Outage Records of Pollution Control Equipment 2

1.5       Summary of EM&A Requirements  2

2.             AIR QUALITY.. 9

2.1       Monitoring Requirements  9

2.2       Summary of Results and Observations  9

3.             WATER QUALITY.. 10

3.1       Monitoring Requirements  10

3.2       Summary of Results and Observations  10

4.             ENVIRONMENTAL AUDIT.. 12

4.1       Review of Environmental Monitoring Procedures  12

4.2       Assessment of Environmental Monitoring Results  12

4.3       Status of Environmental Licensing and Permitting  14

4.4       Implementation Status of Environmental Mitigation Measures  14

4.5       Implementation Status of Event/Action Plan  14

4.6       Implementation Status of Environmental Complaint Handling Procedures  14

5.             FUTURE KEY ISSUES. 16

5.1       Outage Plan for the coming 3 months  16

5.2       Key issues for the coming 3 months  16

6.             CONCLUSION.. 17

 

 

 

List of Tables

 

Table 2.1      Air Quality Monitoring Parameters and Frequency

Table 3.1      Water Quality Monitoring Parameters and Frequencies

Table 4.1      Summary of Action/Limit Level Exceedances on Monitoring Parameters

Table 4.2      Amount of Gypsum and Sludge Collected for Reuse by Contractor

Table 4.3      Summary of Environmental Licensing and Permit Status

Table 4.4      Environmental Complaints / Enquiries Received

Table 4.4      Outstanding Environmental Complaints / Enquiries Carried Over

 

 


 

List of figures

 

Figure 1.1         Location of New Facilities for L4 & L5 FGD Plant

Figure 1.2         General Arrangement of L4 & L5 FGD Plant

Figure 1.3         Schematic Diagram of L4 & L5 FGD Plant

Figure 1.4         Simplified Schematic Diagram of FGD Wastewater Treatment Plant

Figure 1.5         Organization Chart at Operational Phase

 

 

AppendiX

 

Appendix A      Event/Action Plans in Response to Exceedance of AL Levels

Appendix B      Air Quality Monitoring Results

Appendix C      Summary Results on Water Quality Monitoring

Appendix D      Summary of EMIS

 


EXECUTIVE SUMMARY

 

The operational phase of Lamma Unit L5 Flue Gas Desulphurization Plant (FGD) commenced in July 2009 following the completion of erection works and commissioning tests.  This is the first quarterly Environmental Monitoring and Audit (EM&A) report for the Project “Lamma Power Station Units L4 & L5 Flue Gas Desulphurization Plant Retrofit” prepared by the Environmental Team (ET).  This report presents the results of impact monitoring on air and water quality and environmental audit for the operation of the said project in the period from July to September 2009. 

 

Environmental monitoring for air quality and water quality were carried out for the purpose of this EM&A program as well as for fulfilling the requirements stipulated in the relevant licences.  The results were checked against the established Action/Limit (AL) levels.  The implementation status of the environmental mitigation measures, Event/Action Plan and environmental complaint handling procedures were also checked.

 

 

Plant Availability

Unit L5 was fully available in the reporting period.

 

 

Malfunction/Outage Records of Pollution Control Equipment

 

Equipment

Period

Cause

Actions Taken

L5 FGD

19/07/2009 10:05 to

21/07/2009 19:40

Defect rectification

Informed EPD by letter dated 22/07/2009.

L5 FGD

03/08/2009 00:13 to

08/08/2009 17:25

Installation of equipment for commissioning test, GGH washing and defect rectification

Informed EPD by letter dated 10/08/2009.

L5 FGD

09/08/2009 16:40 to 17:13

Defect rectification

Informed EPD by letter dated 10/08/2009.

L5 FGD

16/08/2009 00:09 to

27/09/2009 23:38

Internal inspection and defect rectification

Informed EPD by letters dated 14/8/2009 and 28/09/2009

 

 

Environmental Monitoring Works

Environmental monitoring works were performed during the operation of Unit L5 FGD Plant in the reporting period. 

 

Air Quality

No exceedance of Action and Limit levels for air quality were recorded in the reporting period.

 

Water Quality

No exceedance of Action and Limit levels for water quality were recorded in the reporting period.

 

Environmental Licensing and Permitting

 

Description

Permit / Licence No.

Valid Period

Issued To

Date of Issuance

From

To

Environmental Permit

EP-248/2006

25/04/2006

-

HK Electric

25/04/2006

Specified Processes Licence issued under APCO

L-7-002(7)

01/01/2009

31/12/2010

 

HK Electric

31/12/2008

WPCO discharge licence for Ash Lagoon

EP890/W2/XD018

16/04/2007

31/12/2011

HK Electric

16/04/2007

 

 

Implementation Status of Environmental Mitigation Measures

Environmental mitigation measures were implemented in the reporting period. 

 

 

Environmental Complaints

No complaint against the Project was received in the reporting period.

 

 

Future key issues

Key issues to be considered in the coming months include:

 

Air Impact

·          To continuously carry out the air quality monitoring for Unit L5.

 

Water Impact

·          To continuously carry out the water quality monitoring for FGD WWT plant.

 

 

Concluding Remarks

The environmental performance of the project was generally satisfactory.


 

1.             INTRODUCTION

 

The operational phase of Lamma L5 FGD Plant commenced in July 2009 following the completion of erection works and commissioning tests.  The Environmental Team (hereinafter called the “ET”) was formed within The Hongkong Electric Co. Ltd (HK Electric) to undertake Environmental Monitoring and Audit for the “Operation of Lamma Power Station Units L4 & L5 Flue Gas Desulpurization Plant Retrofit Project”) under the requirements of Clause 2.18 of Environmental Permit (EP) No. EP-248/2006. 

 

This report summarizes the environmental monitoring and audit work for the Project for the period from July to September 2009.

 

 

1.1         Background

 

The Project involves retrofitting the two existing 350MW coal-fired generating Units L4 and L5 of Lamma Power Station with Flue Gas Desulphurisation (FGD) plant for reducing sulphur dioxide emissions in support of Government policy to improve the air quality of the Pearl River Delta.

 

The Project includes the installation and operation of FGD plants with flue gas desulphurization efficiency of 90% for the two 350MW coal-fired Units L4 & L5 to reduce the overall SO2 emissions from Lamma Power Station.  The process adopted for the FGD plants is “Wet Limestone-Gypsum”, a technology which has already been used in, and proved effective and reliable for the existing coal-fired units L6, L7 & L8.  The flue gas from the boiler is directed to the FGD absorber inside which removal of SO2 is take place by reaction with limestone slurry. After passing through the absorber, the treated flue gas is heated up by a gas-gas heater to over 80ºC at boiler rated capacity and directed back to the existing chimney for discharge to the atmosphere. Figure 1.1, Figure 1.2 and Figure 1.3 show the location and schematic of the FGD plants.

 

Wastewater filtrated from the reacted limestone slurry, i.e. gypsum slurry, is produced and it is directed to the existing FGD wastewater treatment plant (WWTP).  The FGD WWTP is designed to treat the effluent from FGD plants by alkalization, precipitation and neutralization processes. The schematic diagram of the FGD WWTP is illustrated in Figure 1.4.

 

The additional equipment for the FGD Plant retrofit project for Units L4 and L5 includes:

 

·          Two sets of FGD absorbers and associated ductworks

·          Two sets of booster fans

·          Two sets of gas-gas heaters

·          FGD Switchgear and Equipment Building

·          Gypsum dewatering system comprising two sets of hydrocyclones and belt filters

 

 

 

1.2         Project Organisation

 

The management structure to oversee the Project includes the following:

 

·          Environmental Protection Department (The Authority);

·          General Manager (Corporate Development) (The official contact person between HK Electric and EPD);

·          Environmental Team Leader (ET Leader);

·          Environmental Team (ET).

 

The organization chart for the Operation EM&A programme is shown in Figure 1.5.

 

 

1.3         Plant Availability during the Reporting Period

 

Unit L5 was fully available in the reporting period.

 

 

1.4         Malfunction/Outage Records of Pollution Control Equipment

 

Equipment

Period

Cause

Actions Taken

L5 FGD

19/07/2009 10:05 to

21/07/2009 19:40

Defect rectification

Informed EPD by letter dated 22/07/2009.

L5 FGD

03/08/2009 00:13 to

08/08/2009 17:25

Installation of equipment for commissioning test, GGH washing and defect rectification

Informed EPD by letter dated 10/08/2009.

L5 FGD

09/08/2009 16:40 to 17:13

Defect rectification

Informed EPD by letter dated 10/08/2009.

L5 FGD

16/08/2009 00:09 to

27/09/2009 23:38

Internal inspection and defect rectification

Informed EPD by letters dated 14/8/2009 and 28/09/2009

 

 

1.5         Summary of EM&A Requirements

 

Environmental Monitoring and Audit (EM&A) requirements have been discussed in the Environmental Impact Assessment (EIA) Report for the Project.  The assessment results indicate that environmental monitoring work required for the EM&A programmes of this Project is already in place or would be implemented under Lamma Power Station Extension Environmental Permit or environmental licenses for the operation of the existing Lamma Power Station.   Such monitoring works are considered adequate for this Project and no additional EM&A activities are required.  Hence, environmental monitoring for air quality and water quality are carried out for the purpose of this EM&A program as well as for fulfilling the requirements stipulated in the relevant licences.

 

The EM&A monitoring work for air and water quality are described in Section 2 and Section 3 respectively.

 

The following environmental audits are summarized in Section 4 of the report:

 

·        Environmental monitoring results;

·        The status of environmental licensing and permits for the Project;

·        The implementation status of environmental protection and pollution control / mitigation measures.

 

The future key issues for the Project will be reported in Section 5 of this report.

 


 

Figure 1.1    Location of New Facilities for L4 & L5 FGD Plant


 

Figure 1.2         General Arrangement of L4 & L5 FGD Plant


 

Figure 1.3         Schematic Diagram of the L4 & L5 FGD Plant


 

Figure 1.4         Simplified Schematic Diagram of FGD Wastewater Treatment Plant


 

Figure 1.5    Organization Structure at Operational Phase of the Project


 

2.             AIR QUALITY

 

 

2.1         Monitoring Requirements

 

Since the Project will bring a general air quality improvement, no additional EM&A activities are considered required, besides those already in place, such as those required by specific process licenses for the operation of the existing Lamma Power Station. In accordance with the requirements stipulated in the Specified Processes Licence issued under Air Pollution Control Ordinance, various operation parameters as stated in Table 2.1 were monitored and checked against the Action/Limit Levels shown in Appendix A

 

Table 2.1    Air Quality Monitoring Parameters and Frequency

 

Sources of Emission

Parameter

Frequency

Steam boiler L5

Particulate

Once / year

 

Particulate (Opacity)

Continuous

 

SO2

Continuous

 

NOx expressed as NO2

Continuous

Fugitive Dust (Coal, PFA, Limestone, gypsum)

Total Suspended Particulate

Once every six days

Chimney emissions

Ambient air

Continuous at existing ambient air monitoring stations

 

SO2

 

NO2

 

 

2.2         Summary of Results and Observations

 

Monitoring of various parameters as listed in Table 2.1 above were conducted during the operation of Unit L5 in the reporting period.  A summary of monitoring data is shown in Appendix B

 

No Action/Limit Level exceedance was recorded in the reporting period.   

 


 

3.             WATER QUALITY

 

 

3.1         Monitoring Requirements

 

According to the EIA Report for the Project, the current monitoring programme for the Lamma Power Station can cover the Project and no additional EM&A measures are required besides those already in place.  Hence, the EM&A work on water quality should strictly follow the relevant monitoring requirements stipulated in the discharge licence for Ash Lagoon issued under the Water Pollution Control Ordinance (WPCO).

 

Water quality monitoring was carried out for FGD Waste Water Treatment Plant (WWTP) in the reporting period.  The parameters stated in Table 3.1 were monitored and checked against the Action/Limit Levels as given in Appendix A.

 

Table 3.1    Water Quality Monitoring Parameters and Frequencies

 

Item

Parameters

Frequencies

1

pH

Daily

2

Suspended Solids

Daily

3

Iron

Monthly

4

Barium

Monthly

5

Mercury

Monthly

6

Cadmium

Monthly

7

Cyanide

Monthly

8

Total Phosphorus

Monthly

9

Total Nitrogen

Monthly

 

 

3.2         Summary of Results and Observations

 

Monitoring of various parameters as listed in Table 3.1 above were carried out during the discharge of the WWTP in the reporting period.  A summary of the data is shown in Appendix C.

 

The data recorded for the monitoring parameters were all below their corresponding Action/Limit Levels.  No Action/Limit level exceedance was recorded in the reporting period.  The effluent quality was generally satisfactory.

 

 

 


4.             ENVIRONMENTAL AUDIT

 

 

4.1         Review of Environmental Monitoring Procedures

 

The environmental monitoring procedures were regularly reviewed by the Environmental Team.  No modification to the existing monitoring procedures was recommended.

 

 

4.2         Assessment of Environmental Monitoring Results

 

Monitoring results for Air Quality and Water Quality

 

The environmental monitoring results for air quality, noise and water quality are presented in Sections 2, 3 and 4 respectively are summarized in Table 4.1.

 

Table 4.1    Summary of Action/Limit Level Exceedances on Monitoring Parameters

 

Item

Parameter Monitored

Monitoring Period

No. of Exceedances In

Event/Action Plan Implementation Status and Results

Action Level

Limit

Level

Air

1

Annual analysis of dust particulate emission rates at chimney stacks.

01/07/09-30/09/09

N.A.*

N.A.*

 

2

Continuous monitoring of opacity, NOx, SO2 and CO2 in the flue gas at the chimney stacks

01/07/09-30/09/09

0

0

 

3

TSP monitoring at Lamma Power Station Boundary (ie East Gate and Reservoir).

01/07/09-30/09/09

0

0

 

4

Ambient SO2 & NOx monitoring at the Peak, Queen Mary Hospital , Victoria Road, Chung Hom Kok, Ap Lei Chau and Cheung Chau.

01/07/09-30/09/09

0

0

 

Water

1

pH in WWTP Effluent

01/07/09-30/09/09

0

0

 

2

Suspended Solids in WWTP Effluent

01/07/09-30/09/09

0

0

 

3

Iron in WWTP Effluent

01/07/09-30/09/09

0

0

 

4

Barium in WWTP Effluent

01/07/09-30/09/09

0

0

 

5

Mercury in WWTP Effluent

01/07/09-30/09/09

0

0

 

6

Cadmium in WWTP Effluent

01/07/09-30/09/09

0

0

 

7

Cyanide in WWTP Effluent

01/07/09-30/09/09

0

0

 

8

Total Phosphorus in WWTP Effluent

01/07/09-30/09/09

0

0

 

9

Total Nitrogen in WWTP Effluent

01/07/09-30/09/09

0

0

 

 

Note: * Monitoring was not scheduled in the reporting period.

 

Waste Management Records

 

The quantity of FGD gypsum and sludge collected for reuse by contractor in the reporting period are shown in Table 4.2.

 

Table 4.2    Amount of Gypsum and Sludge Collected for Reuse by Contractor

 

Period

Amount of Gypsum Collected

Amount of Sludge Collected

July 2009

10,194.2 MT

64.5 MT

August  2009

6,090.6 MT

68.3 MT

September 2009

6,178.8 MT

30.4  MT

 

4.3         Status of Environmental Licensing and Permitting

 

All permits/licenses obtained as of September 2009 are summarised in Table 4.3.

 

Table 4.3    Summary of Environmental Licensing and Permit Status

 

Description

Permit / Licence No.

Valid Period

Status

From

To

Environmental Permit

EP-248/2006

25/04/2006

-

Valid

Specified Processes Licence issued under APCO

L-7-002(7)

01/01/2009

31/12/2010

 

Valid

WPCO discharge licence for Ash Lagoon

EP890/W2/XD018

16/04/2007

31/12/2011

Valid

 

 

4.4         Implementation Status of Environmental Mitigation Measures

 

Mitigation measures detailed in the EIA Report and EP are required to be implemented.  An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix D.

 

 

4.5         Implementation Status of Event/Action Plan

 

A list of specific actions in the event of exceedances of the various threshold levels for specific emission and discharge sources is given in Appendix A.

 

As no Action/Limit level exceedance was recorded, no action has been devised.  

 

 

4.6         Implementation Status of Environmental Complaint Handling Procedures

 

There was no complaint on environmental issues against the Project in the reporting period.


 

Table 4.4      Environmental Complaints / Enquiries Received

 

Case Reference /

Date, Time Received /

Date, Time Concerned

Descriptions /

Actions Taken

Conclusion /

Status

Nil

N/A

N/A

 

 

Table 4.4    Outstanding Environmental Complaints / Enquiries Carried Over

 

Case Reference /

Date, Time Received /

Date, Time Concerned

Descriptions /

Actions Taken

Conclusion /

Status

Nil

N/A

N/A


 

 

5.             FUTURE KEY ISSUES

 

5.1         Outage Plan for the coming 3 months

 

No major outage planned for the next 3 months.

 

 

5.2         Key issues for the coming 3 months

 

Key issues to be considered in the coming 3 months include:

 

Air Impact

 

·    To continuously carry out the air quality monitoring for Unit L5.

 

Water Impact

·          To continuously carry out the water quality monitoring for FGD Waste Water Treatment Plant.

 

 


 

6.             CONCLUSION

 

Environmental monitoring was performed as required in the reporting period from July to September 2009. All monitoring results were checked and reviewed.

 

No Action/Limit level exceedance on air quality parameters were recorded in the reporting period.

 

No Action/Limit level exceedance on water quality parameters were recorded in the reporting period. 

 

Environmental mitigation measures recommended in the EIA Report and EP were implemented in the reporting period.  No complaint against the Project was received in the reporting month.  No prosecution was received for this Project in the reporting period. 

 

The environmental performance of the Project was generally satisfactory.

 

 

 


Appendix A     Event/Action Plans in Response to Exceedance of AL Levels

 

 

A.1      Air

 

Source of Emissions

Parameters to be Monitored

Frequency

Concentration Not to Be Exceeded

Action

Limit

Proposed Action

Steam boiler L5

Particulate

Particulate (Opacity)

SO2

NOx expressed as NO2

once/year

continuous

continuous

continuous

85 mg/Nm3

40% (bihourly)

200 mg/Nm3 (1h)

615 mg/Nm3 (1h)

-

35

190

585

85

40

200

615

ET Leader informs Generation Division at action level. Maintenance initiated. Temporary load shift until pollution control equipment repaired and reinstated. Report to EPD.

Fugitive dust (Coal,

PFA, limestone,

gypsum)

TSP

Once every six

days.

260 (µg/m3) (24 hours)

-

260

Investigation of sources and additional dust suppression to be employed at Limit level.

Frequency of monitoring to be increased as necessary.

Chimney emissions

Ambient air

SO2

 

NO2

Continuous at

existing

ambient air monitoring

stations

 

800 (µg/m3) (1h)

300 (µg/m3) (1h)

 

-

-

 

800

300

ET to review data on post-hoc basis and check for possible power station contribution.

 

 

 

 

 

 

 

 

A.2      Water

 

Source of Discharges

Parameters to be Monitored

Frequency

Concentration Not to Be Exceeded

Action

Limit

Proposed Action

 

FGD Wastewater

Treatment Plant

pH

Daily

6-9

-

6-9

If pH exceeds limit level, consideration to be given to adjust chemical dosing. ET Leader inform Generation Division and investigation be initiated to identify and remedy cause.

 

For all other parameters except pH, Generation Division to be informed, frequency of monitoring to be increased, and investigations to be initiated to identify cause and remedy if concentration exceeds action level. If problem persists to exceed the limit level, ET Leader verbally informs EPD and ensures remedial actions implemented.

Suspended Solids

Daily

30 mg/L

25

30

Iron

Monthly

4 mg/L

3.6

4

Barium

Monthly

1.5 mg/L

1.3

1.5

Mercury

Monthly

0.005 mg/L

0.0045

0.005

Cadmium

Monthly

0.005 mg/L

0.0045

0.005

Cyanide

Monthly

0.1 mg/L

0.09

0.1

Total Phosphorus

Monthly

8 mg/L

7.2

8

Total Nitrogen

Monthly

400 mg/L

360

400


Appendix B

 

Air Quality Monitoring Results

 

B.1      Ambient Total Suspended Particulate Monitoring at Lamma Power Station

 

Date: Third Quarter of 2009 (July - September)

 

 

 

 

 

DATE

TSP CONCENTRATION

(µg/m3)

WEATHER INFORMATION

(from Hong Kong Observatory)

 

Reservoir

 

East Gate

 

Mean

Wind Speed (km/hr)

 

Prevailing Wind Dir.

( º )

 

Mean R.H.

 

(%)

03/07/2009

67

78

32.6

220

76

09/07/2009

34

34

17.0

230

72

15/07/2009

19

(1)

25.8

090

83

17/07/2009

-

30

15.1

080

73

21/07/2009

32

26

12.0

110

83

27/07/2009

(1)

36

20.0

160

86

29/07/2009

34

-

20.0

130

82

02/08/2009

62

50

7.8

150

80

08/08/2009

85

83

29.8

260

78

14/08/2009

27

(1)

8.0

160

88

18/08/2009

-

23

9.9

110

85

20/08/2009

40

28

9.5

230

74

26/08/2009

24

23

12.0

110

79

01/09/2009

35

36

23.3

050

74

07/09/2009

35

35

17.0

090

74

13/09/2009

107

82

11.4

201

79

19/09/2009

73

(1)

17.3

220

77

22/09/2009

-

60

22.5

020

76

25/09/2009

37

34

28.6

090

73

 

Remark:  (1)      Breakdown of High Volume Air Sampler

 

   TSP (µg/m3)

Action Level                                        -

Limit     Level                                     260

 

Calibration:       Calibration at site as per attached

 

Equipment used:           Reservoir & East Gate     :        High Volume Air Sampler


B.2      Unit L5 Stack Monitoring at Lamma Power Station

 

Monthly Summary of Stack NOx and SO2

 

 

Date

Daily Maximum

SO2 concentration (mg/Nm3)*

NOx concentration (mg/Nm3)*

Opacity

(%)

1/7/2009

12

460

20

2/7/2009

22

489

25

3/7/2009

48

487

27

4/7/2009

35

467

25

5/7/2009

16

469

18

6/7/2009

36

420

24

7/7/2009

37

437

22

8/7/2009

49

475

33

9/7/2009

23

491

28

10/7/2009

30

448

26

11/7/2009

25

485

25

12/7/2009

30

382

15

13/7/2009

19

437

16

14/7/2009

10

485

17

15/7/2009

23

529

19

16/7/2009

13

475

18

17/7/2009

26

419

17

18/7/2009

54

384

17

19/7/2009

103

427

14

20/7/2009

133

427

16

21/7/2009

126

395

15

22/7/2009

28

402

17

23/7/2009

38

399

19

24/7/2009

20

508

17

25/7/2009

18

494

15

26/7/2009

15

427

16

27/7/2009

36

518

17

28/7/2009

29

476

18

29/7/2009

29

460

16

30/7/2009

24

435

15

31/7/2009

26

446

15

 

 

 

 

 

 

 

 

 

 

Date

Daily Maximum

SO2 concentration (mg/Nm3)*

NOx concentration (mg/Nm3)*

Opacity

(%)

1/8/2009

21

493

14

2/8/2009

35

498

24

3/8/2009

FGD Plant Outage

498

18

4/8/2009

FGD Plant Outage

403

27

5/8/2009

FGD Plant Outage

425

20

6/8/2009

FGD Plant Outage

326

26

7/8/2009

FGD Plant Outage

440

29

8/8/2009

9

384

23

9/8/2009

33

321

15

10/8/2009

57

345

14

11/8/2009

67

325

14

12/8/2009

64

416

14

13/8/2009

69

379

14

14/8/2009

64

420

14

15/8/2009

29

435

14

16/8/2009

FGD Plant Outage

447

23

17/8/2009

FGD Plant Outage

478

20

18/8/2009

FGD Plant Outage

451

23

19/8/2009

FGD Plant Outage

478

25

20/8/2009

FGD Plant Outage

485

21

21/8/2009

FGD Plant Outage

487

21

22/8/2009

FGD Plant Outage

417

27

23/8/2009

FGD Plant Outage

354

21

24/8/2009

FGD Plant Outage

399

25

25/8/2009

FGD Plant Outage

442

21

26/8/2009

FGD Plant Outage

439

21

27/8/2009

FGD Plant Outage

440

22

28/8/2009

FGD Plant Outage

449

19

29/8/2009

FGD Plant Outage

482

23

30/8/2009

FGD Plant Outage

331

26

31/8/2009

FGD Plant Outage

313

22

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Daily Maximum

SO2 concentration (mg/Nm3)*

NOx concentration (mg/Nm3)*

Opacity

(%)

1/9/2009

FGD Plant Outage

263

23

2/9/2009

FGD Plant Outage

287

18

3/9/2009

FGD Plant Outage

359

24

4/9/2009

FGD Plant Outage

394

25

5/9/2009

FGD Plant Outage

351

24

6/9/2009

FGD Plant Outage

420

27

7/9/2009

FGD Plant Outage

514

25

8/9/2009

FGD Plant Outage

449

22

9/9/2009

FGD Plant Outage

422

14

10/9/2009

FGD Plant Outage

418

16

11/9/2009

FGD Plant Outage

398

25

12/9/2009

FGD Plant Outage

417

25

13/9/2009

FGD Plant Outage

534

21

14/9/2009

FGD Plant Outage

502

19

15/9/2009

FGD Plant Outage

480

17

16/9/2009

FGD Plant Outage

539

20

17/9/2009

FGD Plant Outage

519

19

18/9/2009

FGD Plant Outage

552

17

19/9/2009

FGD Plant Outage

504

19

20/9/2009

FGD Plant Outage

444

18

21/9/2009

FGD Plant Outage

502

25

22/9/2009

FGD Plant Outage

409

22

23/9/2009

FGD Plant Outage

365

21

24/9/2009

FGD Plant Outage

532

22

25/9/2009

FGD Plant Outage

370

25

26/9/2009

FGD Plant Outage

406

24

27/9/2009

FGD Plant Outage

464

25

28/9/2009

50

497

21

29/9/2009

47

421

30

30/9/2009

33

440

24

 

 

Note: * -    Hourly average value.  Expressed as at 0ºC, 101.325kPa, dry and corrected to 12% CO2 condition.


 

 

B.3   Ambient SO2 and NO2 monitoring Data at Southern District and Cheung Chau during the period from July to September 2009


 Appendix C    Summary Results on Water Quality Monitoring

 

LAMMA POWER STATION

FGD WASTEWATER TREATMENT PLANT

EFFLUENT DISCHARGE TO ASH LAGOON

SUSPENDED SOLIDS AND PH

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Period : July - September 2009

 

 

 

 

 

 

 

 

 

 

 

 

 

Week Ending

No. of Samples

Suspended Solids, mg/L

pH

Maximum

Minimum

Average

Maximum

Minimum

Average

04/07/09

5*

16

13

14

8.5

8.4

8.4

11/07/09

5*

19

13

16

8.5

8.4

8.5

18/07/09

5*

14

10

13

8.5

8.4

8.4

25/07/09

5*

17

12

14

8.4

8.3

8.4

01/08/09

6*

17

14

16

8.4

8.3

8.3

08/08/09

6*

20

14

17

8.4

8.2

8.3

15/08/09

6*

22

17

19

8.3

8.1

8.2

22/08/09

4*

20

15

18

8.3

8.2

8.2

29/08/09

4*

19

14

17

8.3

8.2

8.2

05/09/09

5*

21

15

19

8.2

8.0

8.2

12/09/09

6*

20

12

16

8.2

8.0

8.2

19/09/09

4*

18

13

15

8.3

8.1

8.2

26/09/09

3*

16

12

14

8.2

8.1

8.2

 

 

 

 

 

 

 

 

Remark :

 

 

 

 

 

 

 

* - No sampling for the remaining day(s) of the week due to no discharge

 

 


 

LAMMA POWER STATION

FGD WASTEWATER TREATMENT PLANT

EFFLUENT DISCHARGE TO ASH LAGOON

TRACE METAL, TOTAL PHOSPHORUS

AND TOTAL NITROGEN ANALYSIS

 

 

 

 

 

 

 

 

 

 

 

 

Period : July - September 2009

 

 

 

 

 

 

 

 

 

 

Sampling date

 

09/07/2009

17/08/2009

03/09/2009

 

Barium,

ug/L

<150

<150

<150

 

Mercury,

ug/L

<0.5

<0.5

<0.5

 

Cadmium,

ug/L

4

<1

<1

 

Iron,

ug/L

<400

<400

<400

 

Total Phosphorous,

mg/L

<0.8

<0.8

<0.8

 

Total Nitrogen,

mg/L

126

45

210

 

Cyanide,

mg/L

0.02

0.02

<0.01

 

 

 

 

 

 

 

Remark:

 

 

 

 

 

According to the WPCO Ash Lagoon Discharge Licence, contents at exact

levels of trace metals below 1/10th of the WPCO Licence permitted limits

will not be reported. When the concentration of a metal exceeds 1/10th of

the limit, the exact value of the metal concentration will be reported.

 


Appendix D    Summary of EMIS

 

EM&A Log Ref.

Mitigation Measures

Implementation Status

 

General

 

A1

No other process, except the Wet Limestone-Gypsum process used in the FGD plants of the coal-fired Units L6, L7 and L8 within the Lamma Power Station, shall be used in the FGD plants for the coal-fired Units L4 and L5 unless otherwise agreed by EPD.

 

Complied

 

 

 

 

Water Quality

 

B1

All wastewater arising from the operation of the FGD plants for the coal-fired Units L4 and L5 shall be collected and directed to the existing wastewater treatment plant within the Lamma Power Station for treatment.

 

Complied

B2

The operational plant effluent from the FGD plants should be reused as much as possible in order to minimise discharge to the WWTP.

 

Complied

B3

Maintenance of the WWTP should be performed regularly to ensure the effluent from the WWTP would not exceed the current requirements stipulated in the WPCO licence for Ash

Lagoon.

 

Complied

 

 

 

 

waste

 

C1

No gypsum or sludge arising from the operation of the FGD plants for the coal-fired Units L4 and L5 shall be disposed of anywhere. All gypsum and sludge shall be collected and reused.

 

Complied

 

 

 

 

noise

 

D1

Equipments including the Absorber Recirculation Pump, Oxidation Air Blower, Booster Fan and Booster Fan Motor of the FGD plants shall be acoustically insulated and the Gas-Gas Heater (untreated side) of the FGD plants shall be provided with reinforced lagging to reduce the noise impact.

 

Complied