Table of contents
Environmental Monitoring Works
Implementation Status of
Mitigation Measures
Summary of Non-compliance of
the Environmental Quality Performance Limit
Summary of Complaints and
Prosecution
Key Issues for the Coming Month
5 CONCLUSIONS
AND RECOMMENDATIONS
lIST
OF TABLES
Table 1.1 Key Project Contacts
lIST OF FIGUREs
Figure 1.1 Layout of the Submarine Gas Pipeline
lIST OF APPENDIces
A Construction Phase
Mitigation Measures and their Implementation (Gas Pipeline)
List of Abbreviation
EIA |
Environmental
Impact Assessment |
EM&A |
Environmental
Monitoring and Audit |
ET |
Environmental
Team |
GRS |
Gas Receiving
Station |
HEC |
Hong Kong
Electric Co. Ltd |
LNG |
Liquefied
Natural Gas |
1.
This
is the seventeenth Environmental Monitoring and Audit (EM&A) Report
prepared by Cinotech Consultants Limited (ET-Cinotech) for the project “Lamma
Power Station Extension – Supply and Installation of Submarine Gas Pipeline”
(the Project). This document reported
the findings of EM&A Works conducted in June 2006.
Environmental Monitoring Works
Water Quality
2.
No water quality monitoring for the Project was carried out
in
3.
No environmental
complaint and prosecution was received during the reporting month.
Current
Key Issues
4.
No construction activity related to the Project was
undertaken in
1.1
Hong
Kong Electric Co., Ltd. (HEC) proposed to develop a 1,800 MW power station in
Hong Kong Special Administrative Region (HKSAR) to meet the forecast increase
in electricity demand to cope with the social and economical growth of the
HKSAR. The proposed power station is located at reclaimed land in the south of
the existing Lamma Power Station at the western edge of Lamma Island, termed
Lamma Power Station Extension.
1.2
The
proposed Power Station will use natural gas as fuel to generate electricity.
The natural gas will be supplied from Guandong Liquefied Natural Gas (GD LNG)
Terminal located at Cheng Tou Jiao of Shenzen PRC via a 20 inches diameter gas
submarine pipeline.
1.3
HEC
commissioned Saipem Asia Sdn. Bhd. (hereafter called “the Contractor) for the
design, engineering, supply of materials, fabrication, testing at works,
delivery to site, complete erection including pre-trenching, pipe laying, rock
dumping, testing and pre-commissioning at site, preservation during the Defects
Liability Period of Submarine Gas Pipeline under to Project titled “Lamma Power
Station Extension – Supply and Installation of Submarine Gas Pipeline”
(hereinafter called “the Project”). Cinotech Consultants Limited was
subsequently commissioned by the Contractor as the Environmental Team
(ET-Cinotech) to provide environmental consultancy services and to undertake
the Environmental Monitoring and Audit (EM&A) works for the Project.
1.4
The
Project works include Pre-Trenching works, Pipe-Lay installation, Post-Lay
Trenching (Jetting) and Rock Dumping works related to the installation of 92 km
of 20 inches diameter Submarine Gas Pipeline between Guandong Liquefied Natural
Gas Terminal (GD LNG) and the receiving point at Gas Receiving Station (GRS) at
South-West of Lamma Extension on Lamma Island of Hong Kong – SAR. An
Environmental Permit (EP) has been issued for the Lamma Power Station Extension
project. Variations to the EP
requirements have been proposed recently for the Project works and the VEP no.
EP-071/2000/C was issued on 18th May 2005.
1.5
The
Pre-Trenching works, Pipe-Lay installation, Post-Lay Trenching (Jetting) and rock
dumping have been
completed. Pipeline discharge work is the major current activity. The hydrotest medium discharge was commenced on 30 April
in Mainland China waters in accordance with instruction from HEC and the
discharge license from the PRC Authorities.
1.6
Different
parties with different levels of involvement in the project organization
include:
· Project Proponent –Hong Kong Electric Co.,
Ltd. (HEC)
· Contractor – Saipem Asia Sdn. Bhd.
· Environmental Team (ET-Cinotech) –
Cinotech Consultants Limited
1.7
The
responsibilities of respective parties are detailed in Section 3 of the
EM&A Requirements Review (Review) and the project organization chart is
presented in Figure 3.1 of the Review. The key contacts of the ET- Cinotech are
shown in Table 1.1.
Table 1.1 Key
Project Contacts
Name |
Role |
Phone No. |
Fax No. |
|
ET-Cinotech |
Dr. Priscilla Choy |
Project Manager |
2151 2089 |
3107 1388 |
Mr. Kenneth Lam |
Coordinator |
2151 2078 |
3107 1388 |
|
Mr. Henry Leung |
Monitoring Team Leader |
2151 2087 |
3107 1388 |
2.1
No water quality monitoring for the Project was carried out
in Hong Kong waters in the reporting month.
3.1
The
implementation status of mitigation measures is summarized in Appendix A.
3.2
No
non-compliance was recorded during the site audits in the reporting month.
3.3
No
environmental complaint and prosecution was received during the reporting
month.
3.4
The
complaint log for the Project is provided in Appendix B.
4.1
The
construction work was completed in this reporting month. No further
construction works will be carried out for the coming months thereafter. No
further key issue is anticipated.
5.1
No water quality monitoring for the Project was carried out
in Hong Kong waters in the reporting month.
5.2
No construction activity was undertaken in Hong
Kong waters in the reporting month.
5.3
All pipeline construction works have been
completed.