Table of Content
1.3 Construction Works undertaken during the Reporting Month
1.4 Summary of
EM&A Requirements
2.4 Monitoring
Parameters, Frequency and Duration
2.5 Monitoring Procedures and
Calibration Details
3.1 Review of Environmental Monitoring Procedures
3.2 Assessment of Environmental Monitoring Results
3.4 Status of
Environmental Licensing and Permitting
3.5 Implementation Status of Environmental Mitigation Measures
3.6 Implementation
Status of Event/Action Plans
3.7 Implementation
Status of Environmental Complaint Handling Procedures
List
of Tables
Table
1.1......... Construction Activities and Their Corresponding
Environmental Mitigation Measures
Table 2.1......... Noise Monitoring Locations
Table 2.2......... Noise Monitoring Equipment
Table 2.3......... Noise Monitoring Duration and Parameter
Table 3.1......... Summary of AL Level Exceedances on Monitoring Parameters
Table 3.3......... Summary of Environmental Licensing and Permit Status
Table 3.4......... Environmental Complaints / Enquiries Received in December 2006
Table 3.5......... Outstanding Environmental Complaints / Enquiries
Carried Over
List of figures
Figure 1.1 Cable Route of
Transmission System
Figure 2.1 Location of
Manual Noise Monitoring
Appendices
Appendix B Action and Limit Levels for Noise
Appendix C Environmental
Monitoring Schedule
Appendix D Noise Monitoring Results
for December 2006
Appendix E The QA/QC Procedures and
Results
This is the sixty-ninth monthly
Environmental Monitoring and Audit (EM&A) report for the Project
“Construction of Lamma Power Station Extension” prepared by the
Environmental Team (ET). This report presents the results of impact monitoring on noise for the said
project in December 2006.
With the completion of erection works and a series of commissioning tests for Unit L9, the operational EM&A for Lamma Extension has commenced on 15 October 2006. The monthly EM&A report for Lamma Extension operation is submitted under a separate cover. The remaining construction work for the transmission system associated with Unit L9 was completed in December 2006. This is the last monthly EM&A report for the construction of Unit L9.
Noise monitoring was performed. The
results were checked against
the established Action/Limit (AL) levels. An on-site audit was conducted once per week.
The implementation status
of the environmental mitigation measures, Event/Action
Plan and environmental complaint handling procedures were also checked.
Construction
Activities Undertaken
Construction
activities for Lamma Extension during the reporting month are tabulated as
follows:
Item |
Construction
Activities |
Transmission System |
Backfilling
above portal structure for Cable
Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
Miscellaneous |
Slurry ash
piping & filling |
Environmental
Monitoring Works
All monitoring work at designated stations was
performed as scheduled satisfactorily.
Noise
No exceedance of Action and Limit levels for noise arising from the construction of Transmission System
was recorded in the reporting month.
Site Environmental Audit
Site audits
were carried out on a weekly basis to monitor environmental issues on the construction site. The site conditions were generally
satisfactory. All required mitigation
measures were implemented.
Environmental Licensing and Permitting
Description |
Permit No. |
Valid Period |
Issued To |
Date of Issuance |
|
From |
To |
||||
Varied Environmental
Permit |
EP-071/2000/C |
18/05/05 |
- |
HEC |
18/05/05 |
Registration
of Chemical Waste Producer |
WPN5213-912-K2801-03 |
15/09/04 |
- |
Contractor |
15/09/04 |
WPCO
Discharge Licence |
EP890/W2/XD008
(V.1) |
29/06/06 |
30/11/09 |
HEC |
29/06/06 |
APCO Specified Process Licence |
L-7-002(6) |
14/09/06 |
31/12/08 |
HEC |
13/09/06 |
Implementation
Status of Environmental Mitigation Measures
Environmental
mitigation measures for the construction activities
as recommended
in the EM&A manual were implemented in the reporting month.
Environmental
Complaints
No complaint against the
construction activities was received in the reporting month.
Concluding
Remarks
The environmental performance of the project was
generally satisfactory.
1.
INTRODUCTION
The Environmental Team (hereinafter called the “ET”) was formed within the
Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring
and Audit for “Construction of Lamma Power Station Extension”
(hereinafter called the “Project”). Under
the requirements of Section 6 of
Environmental Permit EP-071/2000/C, an EM&A programme for impact environmental
monitoring set out in the EM&A Manual (Construction Phase) is required to be
implemented. In accordance with the
EM&A Manual, environmental monitoring of air quality, noise and
water quality and regular environmental
audits are required for the Project. As the post-project marine water monitoring was successfully
completed in September 2002, no further water quality monitoring for the
reclamation works would be required. The air quality and noise monitoring for the
construction of Unit L9 has also been successfully completed in mid October
2006.
The
Project involves the construction of a gas-fired power station employing
combined cycled gas turbine technology, forming an extension to the existing
Lamma Power Station. The key elements of
the Project including the construction activities associated with the
transmission system and submarine gas pipeline are outlined as follows.
· dredging and reclamation to form approximately 22 hectares of usable area;
· construction of six 300MW class gas-fired combined cycle units;
· construction of a gas receiving station;
·
construction of a new
transmission system linking the Lamma Extension to load centres on
· laying of a gas pipeline for the supply of natural gas to the new power station
This report summarizes the environmental monitoring
and audit work for the Project for the month of December 2006.
An Environmental Management
Committee (EMC) has been set up in HEC to oversee the Project. The management structure includes the
following:
· Environmental Protection Department (The Authority);
· Environmental Manager (The Chairman of the Environmental Management Committee);
· Engineer;
· Independent Environmental Checker (IEC);
· Environmental Team (ET);
· Contractor.
The project organisation chart for the construction EM&A programme is shown in Appendix A.
1.3
Construction Works undertaken
during the Reporting Month
The remaining construction work for the transmission system associated with Unit L9 was completed in December 2006. The construction activities were backfilling above portal structure for Cable Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance. Layout plan for and transmission system are shown in Figure 1.1.
The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1. The implementation of major mitigation measures in the month is provided in Appendix H.
Table 1.1 Construction Activities and Their Corresponding Environmental Mitigation Measures
Item |
Construction Activities |
Environmental Mitigation Measures |
Construction of
Transmission System
|
||
1 |
Backfilling above portal structure for Cable Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
Terrestrial Ecology
- Special care and close monitoring to avoid disturbances to the rare plant species. -
Temporary fire fighting
equipment provided within the work area during construction. |
Miscellaneous
|
||
2 |
Slurry
ash piping & filling |
Noise
- General noise mitigation measures implemented and silent type equipment deployed. |
1.4 Summary of EM&A Requirements
The EM&A program requires environmental monitoring for air,
noise and water
quality. As the post-project marine water monitoring was successfully completed
in September 2002, no further water quality monitoring for the reclamation
works would be required. The air quality and noise monitoring for
the construction of Unit L9 has also been successfully completed in mid October
2006. The detailed EM&A noise monitoring work for the transmission system are described in Section 2. Regular environmental site audits were carried out.
The following environmental
audits are summarized in Section 4 of this report:
· Environmental monitoring results;
· Waste Management Records;
· Weekly site audit results;
· The status of environmental licensing and permits for the Project;
· The implementation status of environmental protection and pollution control/ mitigation measures.
Manual noise measurements at Pak Kok Tsui residences were
carried out for the construction work of Transmission System in this reporting month. The impact noise monitoring
data were checked against the limit levels specified in
the EM&A Manual. Appendix B shows the established Action/Limit Levels
for noise.
In accordance with the EM&A manual, the identified noise monitoring locations are listed in Table 2.1 and shown in Figure 2.1.
Table 2.1 Noise Monitoring Locations
Purpose of noise monitoring |
Monitoring Location |
Transmission System |
Pak Kok Tsui residences (No.2 and No.8) |
The sound level meter used for noise monitoring complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). The noise monitoring equipment used is shown in Table 2.2.
Table 2.2 Noise Monitoring Equipment
Equipment |
Model |
Sound
level meter |
Rion
NL-31 |
Sound level calibrator |
Rion
NC-74 |
2.4 Monitoring Parameters, Frequency and Duration
Manual noise monitoring was conducted at Pak Kok Tsui
residences. The measurement
duration and parameter of noise monitoring were presented in Table
2.3 as follows:
Table 2.3 Noise
Monitoring Duration and Parameter
Location |
Time Period |
Frequency |
Parameter |
Pak
Kok Tsui residences |
0700-1900
hrs on normal weekdays |
Twice per week |
30-min LAeq |
2.5
Monitoring Procedures and Calibration Details
Manual Noise Monitoring for
Transmission System Construction
Manual noise measurements were carried out at the Pak Kok Tsui residences in accordance with standard acoustical principles and practices for checking the impact of noise related to construction of the Transmission System.
Hand‑held anemometer was used to measure the wind speed while taking noise measurements. If the wind speed is excessive, noise data
will be discarded and re-measured.
Equipment Calibration
The sound level meters and calibrators have been verified by the manufacturer or accredited laboratory.
The sound level meters used for manual noise
measurement were calibrated
with a sound level calibrator immediately before and after noise measurement in accordance with the relevant Technical Memoranda under the Noise
Control Ordinance. Calibration details are shown in Appendix E.
Manual noise monitoring was carried out at the Pak Kok Tsui residences.
All monitoring results and their
graphical presentations are provided in Appendix D. No
exceedance of noise Action/Limit Level was recorded in the month.
3.1
Review of Environmental
Monitoring Procedures
The environmental monitoring
procedures were regularly reviewed by the Environmental Team. No modification to the existing monitoring procedures was recommended.
3.2
Assessment of Environmental Monitoring Results
Monitoring results for Noise
The environmental monitoring results for Noise in the reporting month presented in Section 2 are summarized in Table 3.1.
Table 3.1 Summary
of AL Level Exceedances on Monitoring Parameters
Item |
Parameter
Monitored |
Monitoring
Period |
No. of Exceedances In |
Event/Action
Plan Implementation Status and Results |
|
Action
Level |
Limit Level |
||||
Noise |
|||||
1 |
Manual noise monitoring at the Pak Kok Tsui residences |
01/12/06-31/12/06 |
0 |
0 |
|
Site audits were
carried out by ET on a weekly basis to monitor environmental issues at the construction sites to
ensure that all mitigation measures were implemented timely and properly. The site
conditions were generally satisfactory.
All required mitigation measures were implemented. The weekly site
inspection results are
attached in Appendix G.
3.4 Status of Environmental Licensing and Permitting
All
permits/licenses obtained for the project are summarised in Table 3.3.
Table 3.3 Summary of Environmental Licensing and Permit Status
Description |
Permit No. |
Valid Period |
Highlights |
Status |
|
From |
To |
||||
Varied Environmental
Permit |
EP-071/2000/C |
18/05/05 |
- |
The whole construction
work site |
Valid |
Registration
of Chemical Waste Producer |
WPN5213-912-K2801-03 |
15/09/04 |
- |
Major Chemical Waste
Type: Spent lubricating oil, spent battery, contaminated soil with spent
flammable liquid |
Valid |
WPCO
Discharge Licence |
EP890/W2/XD008
(V.1) |
29/06/06 |
30/11/09 |
Lamma Power Station and
Extension |
Valid |
APCO Specified Process
Licence |
L-7-002(6) |
14/09/06 |
31/12/08 |
Lamma Power Station
Extension |
Valid |
3.5
Implementation Status of
Environmental Mitigation Measures
Mitigation measures
detailed in the permits and the EM&A Manual (Construction Phase) are
required to be implemented. An updated
summary of the Environmental
Mitigation Implementation Schedule (EMIS) is presented
in Appendix H.
3.6 Implementation Status of Event/Action Plans
The Event/Action Plans extracted from the EM&A Manual (Construction Phase) are presented in Appendix F.
3.7 Implementation Status of Environmental Complaint Handling Procedures
In December 2006, no complaint against the construction activities was received.
Table 3.4 Environmental Complaints /
Enquiries Received in December 2006
Case Reference / Date, Time Received / Date, Time Concerned |
Descriptions /Actions Taken |
Conclusion
/ Status |
Nil |
N/A |
N/A |
Table 3.5 Outstanding Environmental Complaints
/ Enquiries Carried Over
Case Reference / Date, Time Received / Date, Time Concerned |
Descriptions /Actions Taken |
Conclusion / Status |
Nil |
N/A |
N/A |
All monitoring work at designated stations was performed as scheduled satisfactorily. The environmental monitoring works and site inspection were performed as scheduled in the reporting month. All monitoring results were checked and reviewed.
No Action/Limit level exceedance on noise was recorded in the reporting month.
Environmental mitigation measures recommended in the EM&A manual for the construction activities were implemented in the reporting month. No complaint against the construction activities was received in the reporting month. No prosecution was received for this Project in the reporting period.
The environmental performance of the Project was
generally satisfactory. This is the last monthly EM&A report for the construction of Unit
L9.