Table of Contents Table of Contents
Previous Page  9 / 142 Next Page
Information
Show Menu
Previous Page 9 / 142 Next Page
Page Background

2015 ANNUAL REPORT |

9

OPERATION REVIEW

being reduced across the board in 2016. From 2008 to 2016,

net tariffs have only been marginally increased by 4.7%

compared to overall inflation of about 27% over the same

period.

The prevailing regulatory regime provides a perfect balance

whereby consumers enjoy both quality and value for money

services and investors receive a rate of return conducive to

making long-term investments in electricity infrastructure.

As such we believe that change for the sake of change

is counterproductive and the SCA should continue in its

present form.

The results of the consultation as published by the

government show widespread support for our position

that the current SCA, with its 9.99% rate of return and

10 year duration, offers an effective and stable platform

for innovation and reliability. Respondents saw the power

supply in Hong Kong as affordable and cautioned against the

introduction of competition just for the sake of bringing in

choice.

GENERATING PERFORMANCE OF A HIGH

STANDARD

Lamma Power Station (LPS), with an installed capacity of

3,737 MW, forms the heart of our generation activities.

LPS operates eight coal-fired units, two gas-fired combined

cycle units, five oil-fired open cycle gas turbine units, one

commercial-scale wind turbine, and a solar power system

consisting of 8,662 thin-film photovoltaic panels.

Following formal approval by the government, we began

construction of a new gas-fired generating unit (L10) at LPS

in January 2016. Tendering for the unit was completed as

planned and the contract was awarded in November 2015.

Preliminary engineering design layouts and piling designs

have been confirmed and piling will commence in early

2016 with a target of commissioning in 2020. The new unit

will enhance our natural gas-fired capacity, helping meet

stringent new emissions and carbon intensity targets.

The L2 coal-fired unit was taken offline during the fourth

quarter of 2015 for six months to replace aged boiler

parts and optimise the combustion system for extension

of its service life. Work on the main generation unit will be

completed during the second quarter of 2016.

During the year, work progressed on a 3-year refurbishment

project to modernise LPS various water supply systems,

which are up to 30 years old. Phase 1, involving the

replacement of fresh water pipes at the water reservoir and

slope area, was completed in December 2015.

Systematic equipment inspection and maintenance ensure supply

reliability.

Lamma Winds has generated over 8 million units of green energy

since its commissioning.